Case Summary — Mukul Mudgal, J.
Factual and Procedural Background
This writ petition challenged respondents 1–4 (Union of India and CPWD officers) for issuing a letter dated 16.2.2001 that invited fresh price bids for the supply and installation of a Digital Wireless Interpretation System and related conference systems in the Parliament Library Building. The petitioner is a company pre‑qualified on 29.3.2000 to supply simultaneous interpretation and conference systems. The petitioner submitted technical and commercial tenders (technical/unpriced envelope and commercial envelope) during 2000. After a sequence of technical clarifications, demonstrations and written confirmations (notably in November and December 2000), revised price bids were called and opened. The petitioner's revised price bid (submitted pursuant to the December request) was opened and declared L‑1 at Rs. 2.24 crore, substantially lower than competing bids (respondent No.5: Rs. 2.49 crore; respondent No.7: Rs. 3.53 crore; respondent No.6: Rs. 3.54 crore).
The petitioner alleged that it had met the technical requirements, repeatedly supplied clarifications and demonstrations, agreed to meet technical deviations within its quoted price, and that the respondents' subsequent invitation for fresh price bids (letter dated 16.2.2001) was arbitrary, converted the tender into an auction, and was aimed at favouring competitors. The petitioner also relied on Central Vigilance Commission (CVC) guidelines incorporated in the CPWD manual to argue that negotiations must be with the lowest tenderer (L‑1).
Respondents 1–4 contended that the petitioner's technical bid was incomplete/inadequate, that the Central Works Board (CWB) appropriately sought fresh financial bids after review, and that the petitioner had waived objections by responding to the revised call and submitting revised price bids. Respondent No.5 additionally argued that under Article 226 the Court cannot direct the State to enter into a contract with a particular person and relied on the Division Bench decision in Alcatel India Ltd. v. MTNL to contend government flexibility in tender processes.
The writ petition sought quashing of the 16.2.2001 letter and a direction to award the contract to the petitioner (or otherwise to proceed lawfully having regard to the petitioner's L‑1 status and technical qualification).
Legal Issues Presented
- Whether technical deficiencies can be invoked so as to justify calling for fresh financial (price) bids after technical bids have been cleared and financial bids opened (i.e., whether the respondents could call for fresh price bids on grounds of technical deficiencies).
- Whether the clarificatory meetings held after technical-bid opening but before price-bid opening were tainted by mala fide or bias against the petitioner.
- Whether, upon opening price bids and finding the petitioner L‑1, it was mandatory to award the contract to the petitioner.
- Whether the Chief Engineer was required to refer the matter to higher authorities after opening price bids.
- Whether the Central Works Board (CWB) would have convened its meeting but for complaints from competitors about the petitioner's technical submission.
- Why BECIL (Broadcasting Engineers Consultants of India Ltd.) was appointed as consultant and whether BECIL played any role in the decision-making process of the CWB.
- Whether BECIL made remarks not based on merits that adversely influenced the CWB's decision.
- Whether CVC guidelines (filed by the petitioner) are applicable or relevant to the transaction at issue.
- In what circumstances the price bids were re‑called by the CWB (i.e., the factual basis for re‑calling price bids).
Arguments of the Parties
Petitioner's Arguments
- The petitioner was pre‑qualified and its technical bid had been accepted after demonstrations and written confirmations; the petitioner's revised price bid was opened and declared L‑1 (Rs. 2.24 crore).
- Once technical qualification and L‑1 financial status were established, respondents could not lawfully invite fresh price bids because doing so converts the tender into an auction and breaches confidentiality of financial bids.
- The petitioner had repeatedly agreed to supply any additional or altered technical specifications within its quoted price and to absorb additional costs.
- Negotiations, if any, post‑tender should have been with the L‑1 tenderer in accordance with CVC guidelines incorporated in the CPWD manual; accordingly the call for fresh price bids was contrary to those guidelines.
- There was an apprehension of bias/favour shown to competitors (notably respondent No.7) because of the involvement of a consultant whose relative had interests with a competitor.
- Acceptance of the petitioner's bid was in public interest because the bid was roughly 50–56% lower than estimated cost, leading to substantial savings to the public exchequer.
Respondent Nos. 1–4's Arguments
- The respondents contended the petitioner's technical bid was incomplete and inadequate and therefore they were entitled either to reject it or to require improvements; instead of outright rejection the petitioner was given an opportunity to improve its technical bid.
- The decision‑making process (including reference to the Central Works Board) was legitimate, fair, bona fide and taken under CPWD rules because the procurement was technically sensitive.
- The petitioner, by responding to the call for revised price bids (seeking an extension on 26.2.2001 and submitting revised bids on 28.2.2001), waived objections and was estopped from challenging the 16.2.2001 letter.
- The respondents disputed any actionable mala fide; they defended the recourse to CWB and further scrutiny as within administrative discretion for technical procurements.
Respondent No.5's Arguments
- Under Article 226 the Court cannot direct the State to enter into contract with a particular person; judicial review is concerned with the decision‑making process and not with substituting the Court's choice of whom to contract with.
- The Government may refuse to accept the lowest tender; the petitioner's claim to be awarded the contract as L‑1 is not absolute.
- Reliance was placed on the Division Bench decision in Alcatel India Ltd. v. Mahanagar Telephone Nigam Ltd., to support propositions that deficiencies in a technically accepted bid can still be examined and that the Government can scrap a tender; therefore a mandamus to award a contract is not usually available.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Alcatel India Ltd. v. Mahanagar Telephone Nigam Ltd. & Anr., 92 [2001] DLT 586 (DB) : 2001 (59) DRJ 393 | Authority for the proposition that the Government can scrap a tender, that deficiencies in a technically accepted bid may be further examined, and that a writ Court normally cannot compel the State to contract with a particular tenderer. | The court considered and distinguished Alcatel: observed that Alcatel permits scrapping of tenders, but in the present case there was no scrapping of the tender; instead the respondents had called for fresh financial bids while proceeding with the tender process. Therefore Alcatel was held not to be applicable to justify the action challenged in this petition; the court nonetheless left open the Government's right to scrap the tender for valid reasons as recognized in Alcatel. |
Court's Reasoning and Analysis
The court framed the principal question as whether technical deficiencies could legitimately be relied upon to call for fresh financial bids after technical bids had been cleared and financial bids had been opened.
The court's step‑by‑step analysis proceeded as follows:
- Distinction between fresh technical bids and fresh price bids: The court held that allegations of technical deficiency could be tenable if the respondents were inviting fresh technical bids. In the present case, respondents were not inviting fresh technical bids but fresh financial bids. Calling fresh financial bids on the ground of technical deficiency was held to be arbitrary, unreasonable and unsustainable.
-
The court relied on three factual factors (as recorded in the opinion) that supported the view that the petitioner's technical bid had been accepted and that there was no proper basis for fresh price bids:
- (a) The petitioner's bid was approximately 50% less than the estimated price, making it significantly advantageous to public exchequer.
- (b) Multiple meetings on technical parameters and the very fact that price bids were called indicated that technical bids (including the petitioner's) had been found to be in order.
- (c) The petitioner had explicitly agreed, within its quoted price, to meet any further technical deviations/requirements requested by the respondents.
- On the enforceability of CVC guidelines: The court observed that CVC guidelines formed part of the CPWD manual and therefore were binding on CPWD. Those guidelines required that any post‑tender negotiations be held with the lowest tenderer (L‑1). By calling fresh financial bids instead of negotiating with L‑1, respondents contravened these guidelines incorporated in CPWD rules.
- Confidentiality and prejudice: The court emphasized that once the technical bid is cleared, disclosure of the petitioner's financial bid to facilitate a fresh round of bidding would prejudice the petitioner and defeat the confidentiality purpose of financial bids.
- On the respondents' alternative pleas: the court treated the respondents' contention that the petitioner waived objections by participating in the process and submitting revised bids as an argument but did not allow that contention to validate the re‑call of financial bids under the circumstances. The court also declined to adjudicate the question of mala fide or bias (it expressly stated it was not dealing with mala fide).
- Application of Alcatel: The court accepted that Alcatel allows scrapping of tenders, but distinguished the present facts because there was no scrapping; instead the respondents were undertaking further processing while seeking fresh price bids. Therefore Alcatel did not justify the respondents' action here.
On balance, having endorsed that the petitioner's technical bid had been cleared and that the petitioner was L‑1, the court concluded that respondents could not call for fresh financial bids; instead respondents were required to proceed in accordance with the law and applicable guidelines (which required negotiation with L‑1 if any negotiation was to occur).
Holding and Implications
Holding:
The writ petition is allowed; the Letter dated 16.2.2001 calling for fresh price bids is quashed.
Direct implications and directions:
- The respondents 1–4 are directed to proceed with processing the tender thereafter in accordance with law (which includes compliance with CVC guidelines as incorporated in the CPWD manual).
- The court made clear that nothing in its order prevents the Government from scrapping the tender for valid reasons consistent with the law and the principle in Alcatel India Ltd. (i.e., the Government retains the power to scrap a tender where justified).
- There was no order as to costs.
Broader implications (as indicated by the opinion):
- The decision underscores that, where technical bids have been cleared and financial bids opened and a bidder is found L‑1, the administrative authority should not call for a fresh round of financial bids merely by invoking alleged technical deficiencies—especially where post‑tender negotiations and CVC/CPWD guidance contemplate negotiation with the L‑1 tenderer.
- The Court distinguished earlier authority permitting scrapping of tenders, indicating that such authority does not automatically permit reopening of financial bids without lawful justification; the correctness of any scrapping remains a separate question for the Government to justify if it chooses to exercise that power.
End of summary — prepared exclusively from the text of the provided opinion.
Mukul Mudgal, J.— This writ petition challenges the action of respondents 1 to 4 ordering fresh price bids in respect of supply of Digital Wireless Interpretation System in the Parliament Library Building and further seeks the grant of the said contract on account of its bid being the lowest and its fulfilling all the qualifications prescribed in the Notice Inviting Tender.
2. This writ petition avers as under:
The petitioner is a Company which has German collaboration and its German Principles are the leading manufacturers of Conference Public Address System renowned all over the world. The respondent No. 1 is Union of India; respondent No. 2 is the Director General (Works), CPWD, New Delhi; respondent No. 3 is the Chief Engineer, Parliament Library Project, CPWD, New Delhi, respondent No. 4 is the Executive Engineer, Parliament Library, CPWD, New Delhi, respondent No. 5 is Hi-Tech Audio System Pvt. Ltd., New Delhi, respondent No. 6 is M/s Sonic International, Delhi and respondent No. 7 is M/s Philips India Ltd., New Delhi. The petitioner is already a supplier to Lok Sabha, Pajya Sabha, Vigyan Bhavan, Vidhan Sabha, Bhopal etc. The petitioner was pre-qualified by the respondent No. 4 on 29th of March, 2000 for the installation of a Simultaneous Interpretation System and Conference System in the Auditorium & Committee Halls in the Parliament Library. Pursuant to the procurement of requisite papers by the petitioner Company on 8.6.2000 the Meeting of the Technical Committee was called by the respondent No. 1 which was attended by representative of respondent No. 2 as well as the representative of all the proposed bidders. Various clarifications were given to the bidders. The petitioner submitted its tender on 26th of June, 2000 in two different envelopes - one containing the technical & unpriced cover and the other containing the commercial bid alongwith its Letter dated 26.6.2000 There were in all 5 bidders apart from the petitioner and eventually the petitioner and respondents 5 to 7 were declared qualified. In response to a Letter dated 12th of September, 2000, received from respondent No. 3 asking for certain information alongwith catalogue & specifications of the equipment meeting the NIT specifications, the petitioner by its Letter dated 22.9.2000 furnished the clarifications and the details asked for by the respondent No. 3. Another Letter was received on 3.11.2000 from respondent No. 3 regarding confirmation for the systems description. The petitioner responded by its Letter dated 11.11.2000 to the above and demonstrated its equipment on 22.11.2000 The petitioner further confirmed the systems description by its Letters dated 27.11.2000 & 29.11.2000 On 1.12.2000 a letter was written to the petitioner by respondent No. 3 informing that the technical and the commercial issues had been reviewed and the final requirements of the Department were set out in detail in the said letter dated 1.12.2000 The bidders were asked therefore to resubmit their confirmation letter with technical information in one envelope and revised price/rates in a separate sealed envelope. The petitioner vide its letter dated 5.12.2000 submitted the clarifications sought by the respondent No. 3 alongwith the revised bid. The new price bid was opened on the date and time fixed and the petitioner's bid for Rs. 2.24 crore was declared as L-1. The bid of the respondent No. 5 was for Rs. 2.49 crore; the bid of respondent No. 7 was for Rs. 3.53 crore and the bid of respondent No. 6 was for Rs. 3.54 crore. The petitioner complied with all the additional requirements and the suggestions which the respondent No. 3 wanted within the price offered by it and also offered to absorb all additional costs which may be necessitated by any other requirement of the petitioner within the price quoted. Even thereafter on 16.2.2001 the respondent No. 4 raised further queries and sought a different kind of Digital Panel with up and down push button for selection of languages even which the petitioner agreed to provide without extra costs. Thereafter certain other clarifications was asked for and duly given by the petitioner. From the very beginning, the respondents 3 & 4 have repeatedly raised uncalled for queries/objections regarding the petitioner's equipment with a view to favour respondent No. 5 and/or respondent No. 7 so as to exclude the petitioner. The petitioner had not objected to the submission of fresh offers in December, 2000 since the earlier commercial bids had not been opened and the price offered by the each bidder was not known. The petitioner's plea is that once the petitioner's technical bid is accepted and the price bids have been opened and the prices quoted by each of the bidders known, it is not lawful for the respondents to invite for the fresh offers from the bidders which converts the tender to an auction. !t was further submitted that Mr. K.L Malhotra who runs a dealership of M/s Philips India, respondent No. 7 herein in the name of his son, had been appointed as a Consultant by M/s Broadcast Engineers Consultants India Ltd., who are the Consultants for the present contract. It is submitted that it is the at behest of Shri K.L Malhotra that fresh offers are being made to favour respondent No. 7. Thus the respondent Nos. 1-4's Letter dated 16.2.2001 for inviting fresh price bids is challenged by the present writ petition.
3. Mr. V.P Singh, learned Senior counsel for the petitioner has contended that the Committee in its report recorded all 3 findings in favour of the petitioner. Even then it made a recommendation for calling for a revised price bid which was contrary to its own findings. Similarly the Central Works Board, CPWD (hereinafter referred to as ‘the CWB’) wrongly followed the Committee's recommendation and recommended the fresh price bid which led to the impugned Order dated 16.2.2001 He contended that the petitioner having been held to be qualified in the technical bid and having been held to be L1 in the opening of financial bid by being 56% below the estimated cost, it was not open to the respondents to ask for fresh price bids, particularly when the petitioner had clarified that even if any other specifications different from those asked in N.I.T or even otherwise were required, the petitioner was prepared to supply them without any financial implications. He further submits that the acceptance of the petitioner's bid even otherwise is eminently in public interest, as the petitioner's financial bid is about 56% lower than the estimated price and its acceptance would save the public exchequer considerable expenditure, He further submitted that once the petitioner's technical bid was cleared and he was found to be L1 in the financial bid, sustained efforts have been made to somehow derail his bid. He has referred to the presence of Shri K.L Malhotra, an employee of Broadcasting Engineers Consultants of India Ltd.. a Govt. of India Enterprise (BECIL) in the all the meetings of the Advisory Committee as part of the cause for discrimination against the petitioner as K.L Malhotra's son was associated with one of the competitors i.e, M/s Philips India Ltd., respondent No. 7. He further submitted that once the petitioner was found to be L1 all post tender negotiations ought to have been with L1 alone as per CVC guidelines. He further submitted that the irrespective of the fact whether CVC guidelines were binding, the said CVC guidelines formed part of the CPWD manual and hence were binding in any event on the respondents.
4. The summary of the respondent Nos. 1-4's plea in the words of the respondents counsel, Mr. Sanjay Jain is as follows:
“(1) Whether the clarifactory meetings held between the respondents (officers of CPWD) and the parties responding to the Notice Inviting Tender (NIT) dated 4.5.2001 - after opening of their respective technical bids (26.6.2000) but before opening of their price bids (7.12.2000) - were SQ held due to any mala fide or bias against the petitioner?
(2) On 7.12.2000, when the petitioner was found to be L1 (Lowest Tenders in terms of price), whether it was mandatory to award if the contract?
(3) Whether it was imperative for CE (Chief Engineer) to refer the matter to higher authorities for decision on awarding contract, after opening of the price bids?
(4) Whether the meeting of Central Works Board (CWB) on 16.1.201 would not have been held if the competitors had not complained about the deficiencies and contradictions of the technical bid submitted by the petitioner?
(5) Why was BECIL (Broadcasting Engineers Consultants of India Ltd., a Govt. of India Enterprise) appointed as Consultant?
(6) Whether BECIL had any role to play in decision making process of awarding of the contract by CWB?
(7) Whether BECIL made any such remarks or observations not based on merits but stemming from extraneous motives, which would have adversely influenced the decision of CWB to award or not to award the contract to the petitioner?
(8) Whether CVC guidelines filed by the petitioner at page 359 are applicable or relevant to the nature of transaction, which is the subject-matter of the present writ petition?
(9) In what circumstances the price bids were re-called by CWB?”
4. The respondent Nos. 1-4 have contended accordingly that the petitioner by responding to the call for revised price bids by letter dated 26.2.2001 to seek extension of time to submit the revised price bids and by submitting the revised price bids on 28.2.2001 waived off all objections and is estopped from challenging the Letter dated 16.2.2001 It is also contended that the decision making process has been fair, equitable and bona fide and no malice actuates the call for the revised price bids. It is further submitted by the respondents 1 to 4 that the technical bud by the petitioner being incomplete and inadequate and not complying with the NIT, the respondents 1 to 4 were entitled to reject the said technical bid. Since the petitioner was being treated equitably, instead of rejecting its technical bid a sufficient and further opportunity was given to the petitioner to improve upon its technical bid. It is further submitted that the tender being of highly technical and sensitive nature, respondent No. 4, the Executive Engineer and the Chief Engineer, the respondent No. 3, had accordingly referred the entire matter to the Central Works Board which is the supreme body under the CPWD Rules and competent to take the decision on such matters.
5. In so far as the plea of mala fide is concerned, I am not dealing with the said plea in view of the judgment and the discussion which follows.
6. The respondent No. 5 while supporting the respondents 1 to 4 generally have further taken the plea that under Article 226 no direction can be given to the State to enter into a contract with any particular person and only the decision making process and not the decision itself which can be questioned in a writ Court. It is also contended that it is open to the Government not to accept the lowest tender and the petitioner cannot claim any rights merely by virtue of its being the lowest tenderer, i.e, apart from decisions which cautioned against exercise of writ jurisdiction in questioning tender evaluation, reliance was placed on the decision of the Division Bench of this Court in Alcatel India Ltd. v. Mahanagar Telephone Nigam Ltd. & Anr., 92 [2001] DLT 586 (DB) : 2001 (59) DRJ 393 to contend that even after acceptance of a technical bid, the deficiencies in technical requirements of a technically approved bid can still be examined. The above decision was also relied upon for the proposition that since no binding contract came into existence between the parties, the Government could not be prevented from scrapping the tender and a mandamus could not issue to a purchaser to place a purchase order on a particular seller.
7. The principal question involved in the present writ petition is whether technical deficiencies could be pointed out or resorted to in order to call for a fresh financial bid. In my view, the pleas of the respondents 1 to 4 that the bid of the petitioner was technically deficient would have been tenable and entertainable if the respondents were inviting fresh technical bids. In the present case, it is not the fresh technical bids which are being invited but it is the fresh price bids which could only follow if the respondents 1 to 4 were technically fully satisfied with the technical bids. The calling of the fresh financial bids though on the ground of tech nical deficiency/alteration/inadequacy is clearly arbitrary, unreasonable and un sustainable.
This Court cannot lose sight of the fact that two following factors:
(a) that the petitioner's bid is about 50% less than the estimated price for the equipment in question;
(b) that several meetings on the technical parameters, variations and alterations in the original NIT were held including the petitioner and the very factum of calling for the price bids is indicative of the fact that the technical bids of the parties including that of the petitioner was found to be in order.
(c) The third factor is that the petitioner in any event agreed within the prices quoted to meet with any other technical deviation/requirement of the respondents 1 to 4 and this has been the petitioner's plea right from the beginning and which was also reiterated by the learned counsel for the petitioner.
Another plea which was raised by the respondents 1 to 4 was that it was the discretion of the respondents 1 to 4 to scrap the bid process and call for fresh technical and financial bids and such action cannot be questioned in the writ jurisdiction. In my view, the above plea seeks the resolution of a hypothetical situation. In the present case, the respondents have not scrapped the NIT or the process initiated further to the NIT dated 5.5.2000 as well as 5.12.2000 when the petitioner-submitted that the revised bid. The piea regarding enforceability of the CVC Guidelines and whether or not the CVC Guidelines are applicable or enforceable in general is academic. In so far as CPWD Rules are concerned, these guidelines indisputably formed part of CPWD Manual and cannot therefore, be ignored. These guidelines clearly provide that any negotiation has to be held with L1 that is the petitioner as per the tenders submitted pursuant to the notice dated 5.12.2000
8. From 26th of June, 2000 when the first tender was submitted by the petitioner several times the technical information was sought alongwith catalogue and specifications which were furnished by the petitioner. Thereafter on 3.11.2000 a confirmation for the system description was sought from the petitioner which was responded by the petitioner on 11th of November, 2000 and the equipment demonstrated on 22.11.2000, 27.11.2000 and 29,11.2000 and thus the petitioner confirmed its system description. Thereafter respondent No. 3 after review of technical and commercial issues and setting out the final requirements of the department sent a letter dated 1 st of December, 2000 to the petitioner and all the bidders were asked to resubmit their confirmation letter putting the technical bid in one envelope and the revised price bids in another letter. On 5.12.2000 the petitioner had given the clarifications sought by respondent No. 3 alongwith the revised bids. Considering the above sequence of events, the technical enquiries of the respondents were answered/clarified and confirmed and demonstration given prior to the submitting of the bids on 5.12.2000, the technical bid thus stood cleared and was no longer opened to alteration particularly after the opening of the financial bids.
9. In my view, therefore, the writ petition is entitled to succeed. The petitioner had successfully cleared the technical bid. Upon the opening of the financial bid, the petitioner was found to have been the lowest tenderer. In fact the petitioner's tender was found to be more than 50 per cent less than the estimated price. Sig-nificantiy the petitioner had also offered within the quoted prices to meet/with all the variations in the technical specifications sought by the respondent. The Central Public Works Department is bound by the guidelines issued by the Central Vigilance Commission because the said guidelines formed part of its own manual. Consequently all negotiations had to be carried on post tender with the lowest tenderer. Instead the respondent had chosen to call for the fresh financial bids which are impugned in this writ petition. The resort to fresh financial bids is clearly contrary to the CVC guidelines incorporated in the CPWD manual. If it all any technical variation was required negotiations ought to have been held only with the petitioner. Not only is the petitioner's bid substantially lower than the estimated price but the petitioner has also offered within the quoted prices all other alterations and replacement suggested by the respondents. Consequently the petitioner being the lowest tenderer cannot be denied the rights accruing to it. The rivals of the petitioner cannot be part of the fresh financial bid which in fact is not called for at all.
10. I am not going into the question whether there were any mala fide or bias against the petitioner but merely proceedings on the fact that once the petitioner is found to be L1 after the opening of the price bids then the petitioner's bid could not be rejected out of hand merely on the ground that the Consultant had objected by a complaint bids deficiencies and contradictions of the technical about the submitted by the petitioner. The petitioner's technical bid had been cleared by the respondents themselves. In so far as the Alcatel India Ltd.'s Case is concerned, there is no doubt that according to the aforesaid judgment, the Government could scrap the tender but such is not the situation in the present case. I am not required to consider the issue whether the scrapping of the tender by the Government is justified as no scrapping of tender has been done by the Government of India in the present case. Accordingly, the aforesaid judgment of Alcatel is not applicable to the present case. The Government is in fact going through the tender and in that view of the matter, it is certainly open to this Court to consider the decision of the Government to ask for fresh financial bids. Once the technical bid is cleared the, petitioner would be greatly prejudiced by the disclosure of its financial bids. The very purpose of confidentiality of a financial bid of a tender is defeated by the procedure sought to be adopted by the respondents 1 to 4.
11. The plea that whether the Court under Article 226 should be the technical evaluator of the bids in my view is an academic plea because the respondents themselves had cleared the technical bid and the petitioner's right to be considered for its financial bid which was the lowest only arises after its technical bid is cleared. In the present case the Court is not sitting over the technical evaluation done by the respondents. It is in fact endorsing it. Consequently the judgments relied upon by the respondents in respect of this Court's limited jurisdiction in interfering with technical evaluation are not germane. Once the technical bid is considered and found acceptable and the petitioner found to be the lowest tenderer (L1) then it is no longer open to the respondents to call for fresh financial bids as that would directly violate the CVC guidelines forming part of the CPWD manual, requiring negotiations with the lowest tenderer.
12. The writ petition is accordingly allowed and the Letter dated 16.2.2001 calling for fresh price bids in regard to supply of Digital Wireless Interpretation System and 3 Nos. Committee Rooms and Conference System for 7 Nos. Committee rooms in the Parliament Library Building at Pandit Park Marg, New Delhi is quashed and the respondents 1 to 4 are directed to proceed with the processing of tender thereafter in accordance with law. However, it is made clear that nothing said in the aforesaid judgment would come in the way of the Government if it chooses to do so from scrapping the tender for valid reasons as per the decision of the Division Bench of this Court in the case of Alcatel India Ltd. (Supra).
13. With these observations, the petition stands allowed with no orders as to costs.