Union Of India v. Ramesh Lalwani.

Delhi High Court
Oct 14, 1997
Smart Summary (Beta)

Factual and Procedural Background

Mr. S.S Juneja was appointed as the sole Arbitrator by the Chief Engineer (NDZ) I, C.P.W.D, New Delhi, under letter dated 19.5.92, to decide disputes arising under clause 25 of the agreement between the parties for the construction of a 75,000 litres R.C.C overhead tank at Dr. Zakir Hussain Memorial College, New Delhi. The claimant raised four claims related to additional expenditure, forfeiture of security deposit, delay in completion, and cost of cement. The Arbitrator examined these claims, particularly focusing on the rescission of the contract by the claimant and the validity of the design submissions by the respondent. The Arbitrator found the rescission unjustified and rejected the claimant’s claims. The respondent submitted counterclaims for various expenses and losses, some of which were awarded by the Arbitrator. The Award was challenged in court, which reviewed the scope of interference in arbitration awards.

Legal Issues Presented

  1. Whether the rescission of the contract by the claimant was justified under the terms of the agreement and facts of the case.
  2. Whether the claimant was entitled to recover additional expenditure and other claims arising from the alleged rescission.
  3. The scope of judicial interference in arbitration awards and under what circumstances a court may set aside such an award.

Arguments of the Parties

Claimant's Arguments

  • Claimed additional expenditure of Rs. 3,94,000 on completion of work based on clause 17(c) of the agreement.
  • Claimed forfeiture of security deposit of Rs. 65,010 under clause 17(c).
  • Claimed damages for delay in completion amounting to Rs. 65,010 under clause 16.
  • Claimed cost of cement at double rate amounting to Rs. 17,686.
  • Asserted that the respondent’s designs were not in terms of the contract, justifying rescission of the contract.
  • Argued that tenders for balance work after rescission showed higher rates, supporting their claim for additional expenditure.

Respondent's Arguments

  • Contended that the designs were submitted thrice and approved by the claimants, indicating compliance with the contract.
  • Pointed out discrepancies in architectural drawings supplied by claimants and requested independent verification of designs.
  • Asserted that steel required for casting piles was not issued by claimants despite multiple requests.
  • Maintained intention to continue work and requested reconsideration of rescission.
  • Denied that tenders were called for balance work and argued that the claim for risk and cost was hypothetical.
  • Submitted counterclaims for refund of earnest money, payment for work done, loss of advances, expenses on establishment, loss of profit, arbitration costs, and interest.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
M/s Sanykt Nirmata v. Delhi Development Authority & Anr. (1997 III AD (Delhi) 400) Established that an arbitrator’s award is conclusive and can be set aside only for misconduct, invalidity, or jurisdictional errors. Reiterated the limited scope of court interference in arbitration awards and upheld the award unless there is misconduct or procedural invalidity.
Jivaraj Bhai Ujamshi Sheth & Ors. v. Chintamanrao Balaji AIR 1965 SC 214 Clarified grounds on which an arbitration award may be set aside, emphasizing misconduct and jurisdiction. Supported the principle that errors of judgment by arbitrators do not invalidate awards.
State of Rajasthan v. M/s R.S Sharma & Co. (1988) 4 SCC 353 Confirmed limited judicial review of arbitration awards. Applied to affirm that courts should not reappraise evidence or substitute their own views for the arbitrator’s findings.
Municipal Corporation of Delhi v. M/s Jagan Nath Ashok Kumar AIR 1989 SC 2316 Held that courts cannot sit in appeal over arbitrator’s evaluation of evidence and that the arbitrator is sole judge of evidence quality and quantity. Used to emphasize that reasonableness of arbitrator’s reasons cannot be challenged if they have rational nexus to conclusions.
Puri Contractor Pvt. Ltd. v. Union of India AIR 1989 SC 777 Supports limited scope of judicial interference in arbitration awards. Affirmed the principle that courts should uphold arbitration awards within the letter of law.
New India Civil Contractors Pvt. Ltd. v. Oil and Natural Gas Corporation JT 1907 (2) SC 633 Reiterated minimal interference by courts in arbitration awards. Applied to support the principle of judicial restraint in arbitration matters.
DDA v. M/s Alka Ram AIR 1982 Delhi 365 (DB) Clarified that arbitrators need not provide detailed judgments but must indicate the trend of reasoning. Used to validate the sufficiency of the arbitrator’s reasoning in the award.
DDA v. M/s Uppal Engineering Construction Co. AIR 1982 Delhi 425 (DB) Similar to Alka Ram case regarding sufficiency of reasons in arbitration awards. Supported the adequacy of the arbitrator’s reasoning process in the present award.
Narain Dass R. Istrani v. Union of India AIR 1993 Delhi 78 Reinforced the principle that courts should not reappraise evidence but support arbitration awards. Applied to uphold the arbitrator’s findings and award.
College of Vocational Studies v. S.S Jaitley AIR 1987 Delhi 134 (DD) Confirmed that arbitrators’ reasons need not be exhaustive but must avoid arbitrariness. Used to affirm the reasonableness of the arbitrator’s award reasoning.
Mediterranean & Eastern Export Co. Ltd. v. Fortress Fabrics Ltd. (1948) 2 All ER 186 Expressed judicial deference to arbitrators especially in commercial disputes, emphasizing upholding awards unless natural justice is violated. Quoted to highlight modern judicial approach favoring arbitration awards.
Municipal Corporation of Delhi v. M/s Jainath Ashok Kumar & Anr AIR 1987 SC 2316 Approved the above principle of judicial deference to arbitration awards. Applied to endorse the limited interference approach.

Court's Reasoning and Analysis

The court meticulously reviewed the Arbitrator’s award and the evidence considered therein. It noted the Arbitrator’s detailed examination of the contract terms, submissions by both parties, and the conduct of the claimant in rescinding the contract. The Arbitrator found that the respondent had made genuine efforts to comply with design requirements and had sought independent verification, while the claimant failed to justify the rescission or provide evidence of tenders called for balance work. The court emphasized settled legal principles limiting judicial interference in arbitration awards, relying on multiple precedents to assert that awards are conclusive unless there is misconduct, invalidity, or jurisdictional error. The court recognized that the Arbitrator’s reasoning was germane, relevant, and had a rational nexus to the conclusions, and that the award was supported by the evidence on record. It also highlighted that arbitrators need not provide exhaustive reasoning but must avoid arbitrariness, a standard met in this case.

Holding and Implications

The court upheld the Arbitrator’s award dated 13th April, 1994, making it rule of the Court.

The direct effect of this decision is the rejection of the claimant’s claims and the allowance of the respondent’s counterclaims as per the Award. The respondent is entitled to interest at 12% per annum from the date of decree until realization. No costs were ordered. The decision affirms the limited scope of judicial interference in arbitration proceedings, reinforcing the principle that courts should support arbitration awards within the letter of law unless valid grounds for setting aside exist. No new precedent was established beyond the reaffirmation of existing legal principles.

Show all summary ...

Mr. S.S Juneja, Arbitrator in the Ministry of Urban Development, New Delhi was appointed by the Chief Engineer (NDZ) I, C.P.W.D, New Delhi under his letter No. 4(10)91-A & C (NDZ), dated 19.5.92 as sole Arbitrator to decide and make Award regarding the disputes falling within the purview of clause 25 of the agreement entered into between the parties for the construction of R.C.C overhead tank of 75,000 litres capacity at Dr. Zakir Hussain Memorial College, New Delhi. The claimant raised the following claims/disputes before the Arbitrator:—

“Claim No. 1: Claim on a/c of additional expenditure incurred/to be incurred on completion of the work and under clause 17(c) of the agreement-Rs. 3,94,000/-.

Claim No. 2: Claim for forfeiture of security deposit under clause 17(c) of the agreement - Rs. 65,010/-.

Claim No. 3: Claim for delaying completion of the work under clause 16 of the agreement - Rs. 65,010/-.

Claim No. 4: Claim for cost of cement 6.75 M.T(at double rate) - Rs. 17,686.”

While dealing with the Claim No. 1 the Arbitrator examined the pleas raised by both the parties and on appreciation of evidence and consideration of documents held that rescission of contract by the claimant was not in order and the claimant was not entitled to any amount. The main plea was that the design submitted by the respondent was not in terms of the contract and had deficiencies and, therefore, show cause notice was issued. The respondent failed to submit the designs as per terms of agreement and the contract was validly rescinded vide order dated 13th March, 1991. The tenders for the balance work were called after rescission of the work and the rates quoted by the lowest tenderer were higher by Rs. 3,94,000/- as compared to rates quoted by the respondent. The pleas of the claimant were rejected and the Arbitrator held as follows:—

“On consideration of documents filed and arguments advanced by the parties, I find that admittedly the designs and drawings were submitted thrice by the Respondent to the claimants for approval. Exh.C-4 filed by the Respondent shows- that the design of piles was approved by the claimants. The Respondent had confirmed with his submission dated 7.2.91 (C-9) that the central shaft was made circular as per directions of the claimants. He had also offered to get the designs submitted by him checked by an Expert like Dr. O.P Jain. The Respondent had pointed out discrepancies in architectural drawings supplied by the claimants vide his letter at Exh.C-10 which was not specifically refuted by the claimants with facts and figures. In his letter dated 21.1.91(C-7) and letter dated 7.2.91(C-11), the Respondent had requested the claimants to issue steel for casting of piles. In reply to show cause notice of the claimants, the Respondent vide his letter dated 23.2.91(C-12) explained the position and stated that the steel had not been issued to him in spite of requests for casting of piles. He also clarified that piling work of other contractors has been changed to raft due to the fact that boulders were met with during excavation. He again offered that the designs be got checked from Dr. O.P Jain or by any other authority at his cost. He reiterated that he was prepared to continue with the work of bored cast-in-situ piles if steel was issued to him by the claimants. In his letter dated 2.3.91(C-13), the Respondent again explained the position and requested the department to approve the designs. Thus Respondent had shown his intention to carry out the work. He has also made modifications in the design as suggested by the claimants and submitted the same for approval by the claimants 3 times. The claimants, however, were of the opinion that the designs were not as per agreement. In the circumstances, offer of the Respondent to get the same checked by an independent authority should have been accepted and the position could be explained by both the parties to this authority. As an alternative, the claimants could have modified the design as per agreement and claim the cost, if any, from the Respondent. The claimants have not indicated any reason as to why the steel for foundations was not issued to the Respondent for execution of work of piles when the design of piles had been approved by them. The Respondent had requested the claimants to reconsider the matter of rescission of contract even after- the work was rescinded by the claimants and had asked them to allow him to continue with the work.

In the circumstances, I am of the opinion that the claimants were not entitled to rescind the contract. The Respondent has further stated that no tenders have been called by the claimants for the balance work. The claimants have, however, stated that the tenders were called but no documents have been placed on record by the claimants to show the terms and conditions adopted for the call of tenders for the balance work and the rates received in these tenders. The work was rescinded on 13.3.91 Enough time has already passed. Admittedly, no work has been awarded for the balance work by the claimants and the claimed amount is only hypothetical. Non execution of balance work by the claimants shows that there is force in the contention of the Respondents that the Department wanted to abandon this work. The claim of the claimants for the risk and cost amount is, therefore, not justified. Nothing is awarded in favour of claimants against this claim.”

Similarly the other claims of the Union of India had obviously to be rejected in view of the findings as arrived at while disposing of Claim No. 1. The respondent submitted his counter claim which may be reproduced as follows:—

“Countcr Claim No. 1: Claim for refund of Earnest money including interest thereon- Rs. 13,002/-.

Counter Claim No. 2: Claim for the work done but not paid-Rs. 1,71,535/- which is sub-divided as follows:—

a) Excavation Rs. 7,560/-

b) Badarpur sand Rs. 3,600/-

b) Stone aggregate 20mm nominal size 90M Rs. 12,375/-

c) Shuttering plates 100 Nos.Rs 1 per plate for 120 days. Planks & Rs. 12,000/- Bailies 1000 Nos. @ Rs. 60,000/- 0.50 per day for 120 days.

d) 2 mixer @ 300/- per day for 120 days Rs. 36,000/-

e) Consultation charges other expense of consultants for Rs. 40,000/- redesigning & designing.

Counter Claim No. 3: Claim as loss of advances paid to the people for piling work - Rs. 15,000/-

a) C/water lank, labour hutment, cement, Rs. 5,000/- godown etc.

b) Cartage of cement & storage charges Rs. 4,000/-

c) Loss of advances for materials & labour Rs. 30,000/-

Counter Claim No. 4: Claim on a/c of expenses incurred on maintaining establishment i.e” watchman. Munshi etc. - Rs. 25,000/-.

Counter Claim No. 5: Claim on a/c of loss of profit - Rs. 54,700/-.

Counter Claim No. 6: Cost of arbitration proceedings-Rs. 15,000.

Counter Claim No. 7: Claim for interest by way of damages on the aforesaid amounts -18% p.a”

The amounts awarded in rcspect of the same can be stated as under.-

1. Counter Claim No. 1 Rs. 13,002/-

2. Counter Claim No. 2(a) Rs. 693/-

3. Counter Claim Nos. 2(b) & (b)(i) NIL

4. Counter Claim No. 2(c) Rs. 22,000/-

5. Counter Claim No. 2(d) Rs. 8,000/-

6. Counter Claim No. 2(e) Rs. 15,000/-

7. Counter Claim No. 3 Rs. 5,000/-

8. Counter Claim No. 3(a) Rs. 3,000/-

9. Counter Claim No. 3(b) Rs. 250/-

10. Counter Claim No. 3(c) Rs. 8,250/-

11. Counter Claim No. 4 Rs. 12,000/-

12. Counter Claim No. 5 NIL

13. Counter Claim No. 6 Rs. 4,000/-

Similarly the respondent was awarded interest at the rate of 12% per annum on the net awarded amount against the counter claims No. 1 and 2 and claim No. 4 from 16.6.92 to the date of publishing of the award as pendente lite interest.

Reading of the Award will clearly show that the Arbitrator has considered the evidence as well as the documents on record and on appreciation of the same has come to a finding that recission of the contract was not in order and, therefore, prima facie on that ground the claims of the Union of India were rejected and counter claims of the respondent were allowed to the extent as indicated in the Award. The law is well settled that an Award made by the Arbitrator is conclusive and the Court is only entitled to set aside the same if the Arbitrator has misconducted himself and the scope in this regard is rather limited. The law is reiterated and stated in judgment of this Court as reported in M/s Sanykt Nirmata v. Delhi Development Authority & Anr. 1997 III AD (Delhi) 400. Paragraphs 12, 14, 17 and 18 of the said judgment may be reproduced as under:

“12. It is well established that an award made by an Arbitrator is conclusive as a judgment between the parties and the Court is entitled to set aside the award only if the Arbitrator has misconducted himself for the proceedings or when the award has been made after the issue of an order by the Court superseding the arbitration or if the Arbitration proceedings have become invalid under section 35 of the Act, or where an award has been improperly procured or he has proceeded beyond jurisdiction or is otherwise invalid under section 30 of the Act. The award may be set aside by the Court on the ground of error on the face of the award but an award is not invalid merely because by a process of inference and argument it may be demonstrated that the Arbitrator had committed some mistake in arriving at some conclusion. (Jivaraj Bhai Ujamshi Sheth & Ors. v. Chintamanrao Balaji AIR 1965 SC 214), State of Rajasthan v. M/s R.S Sharma & Co. (1988) 4 SCC 353

14. The scope of interference by the Court is limited. Appraisement of evidence by the Arbitrator is ordinarily never a matter which the Court questions and considers. The parties have selected their own forum and the deciding forum must be conceded the power of appraisement of evidence. The Court has no jurisdiction to sit in appeal and examine the correctness of the award on merits. The Arbitrator is the sole Judge of the quality as well as quantity of the evidence and it is not for the Court to take upon itself the task of being a Judge of the evidence before the Arbitrator. It may be possible that on the same evidence the Court might arrive at different conclusions than the one arrived at by the Arbitrator but that by itself is no ground of setting aside the award of an Arbitrator where there is no violation of principles of natural justice nor there is any allegations of misconduct nor that the Arbitrator has not considered the material produced before him or has not heard the panics or has not given opportunity to lead evidence. Municipal Corporation of Delhi v. M/s Jagan Nath Ashok Kumar AIR 1989 SC 2316. Puri Contractor Pvt. Ltd. v. Union of India AIR 1989 SC 777. As held in New India Civil Contractors Pvt. Ltd. v. Oil and Natural Gas Corporation JT 1907 (2) SC 633 normally the Court would not interfere. The attempt of the Court should always be to support the Award within letter of law.

Following observations made by Lord Goddard, C.J in Mediterranean & Eastern Export Co. Ltd. v. Fortress Fabrics Ltd. (1948) 2 All ER 186 at pages 188-189 have been referred to with approval by the Supreme Court in Municipal Corporation of Delhi v. M/s Jainath Ashok Kumar & Anr: AIR 1987 SC 2316 in respect of an award made by an arbitrator who is a knowledgeable person on the subject matter of the dispute:—

The day has long gone by when the Courts looked with jealousy on the jurisdiction of the Arbitrators. The modern Tendency is in my opinion more especially in commercial arbitrations, to endeavour to uphold awards of the skilled persons that the parties themselves have selected to decide the questions at issue between them. If an arbitrator has acted within the terms of his submission and has not violated any rules of what is so. often called natural justice the Courts should be slow indeed to set aside his award.”

17. When an Arbitrator is required to give reasons for the award, he is not required to write a detailed judgment setting out each logical step of his reasoning but it is sufficient if he indicates the Irend of his thought process,' so that errors can be eliminated and arbitrariness avoided. What reasons are sufficient in any particular case must depend upon the facts of that case (DDA v. M/s Alka Ram AIR 1982 Delhi 365 (DB); DDA v. M/s Uppal Engineering Const action Co. AIR 1982 Delhi 425 (DB); Narain Dass R. Istrani. v. Union of India AIR 1993 Delhi 78). In College of Vocational Studies v. S.S Jaitley AIR 1987 Delhi 134 (DD) also no different principle has been laid down.

18. In Municipal Corporation of Delhi v. M/s Jagan Nath Ashok Kumar AIR 1987 SC 2316 it was held thai when the reasons given by the Arbitrator are germane, relevant and have rational nexus with the conclusions arrived at by him, the reasonableness of the reasons cannot be challenged and it cannot be said to be unreasonable. The word “reasonable” has in law the prima facie meaning of reasonable in regard to those circumstances of which the actor called on to act reasonably knows or ought to know. Reasons vary in its conclusions according to the idiosyncrasy of the individual and the times and circumstances in which he thinks.”

In view of the settled position of law it will not be open for this Court to reappraise evidence: and arrive at contrary conclusions which have already been rendered by the Arbitrator on cogent grounds. The Award dated 13th April, 1994 is, accordingly, made rule of the Court. The respondent shall also be entitled to interest @ 12% p.a from the date of decree till realisation. Let the decree in terms thereof be drawn. There will be no order as to costs.