J.S Construction v. Delhi Development Authority .

Delhi High Court
Nov 1, 1996
Smart Summary (Beta)

Concise Analytical Summary of the Opinion (Dr. M.K. Sharma, J.)

Factual and Procedural Background

The suit was registered after the Arbitrator filed his award together with the records of the arbitration proceedings in this Court. After registration, notice was issued to the parties informing them about the filing of the award and inviting objections within the statutory time limit. On service of notice, the respondents filed objections under Sections 30 and 33 of the Arbitration Act challenging the Arbitrator's award dated 20.10.1994; the petitioner did not file any objection. It is admitted that the Arbitrator was the named Arbitrator and a technical person. The respondents challenged various claims decided by the Arbitrator, with their principal attack directed at claims Nos. 2, 3, 5 and 6; the Court considered objections in respect of all claims raised by the respondents. No one appeared on behalf of the petitioner at the time of arguments.

Legal Issues Presented

  1. Whether parts of the arbitral award should be set aside under Sections 30 & 33 of the Arbitration Act on the ground of error apparent on the face of the record and/or for failure to give a reasoned award.
  2. Whether the Arbitrator's award of interest pendente lite and for the post-award period (awarded at 16% per annum) is legally sustainable.
  3. Whether claims found to be vitiated by lack of reasoning (specifically Claims No. 2 and 3) should be remitted to the Arbitrator for fresh decision on the merits and, if so, under what directions and timeframe.

Arguments of the Parties

Respondents' Arguments

  • The respondents filed objections under Sections 30 and 33 of the Arbitration Act challenging almost all claims decided by the Arbitrator, with primary focus on Claims Nos. 2, 3, 5 and 6.
  • As to Claim No. 2 specifically, learned counsel for the respondents argued that the Arbitrator failed to give a reasoned award and did not indicate the "thought process" or reasons for arriving at the figure of Rs. 97,796/-, which was contended to be a sufficient ground for setting aside that part of the award.
  • The respondents made submissions in respect of other claims as well (the opinion records that the respondents' counsel addressed the remaining claims), but detailed, claim-by-claim critiques beyond Claim No. 2 are not set out as discrete argument points in the opinion.

Petitioner's Position

  • The petitioner did not file objections to the award and no counsel appeared on behalf of the petitioner at the hearing to present arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Secretary, Irrigation Department v. G.C. Roy, 1991 (6) JT 349 Held that the Arbitrator is competent to award interest for the period commencing with the date of award to the date of decree or the date of realisation, whichever is earlier. The Court relied on this decision to uphold the Arbitrator's award of interest pendente lite and for the post-award period (the award of interest from 28.4.1993 to date of decree or payment).
Hindustan Construction Co. Ltd. v. State of Jammu & Kashmir, 1992 (2) Arbitration Law Reporter 412 Reiterated that award of interest by the Arbitrator for the post-award period is a matter of procedure; the principle of Section 34 CPC (award of interest pendente lite and post-decree) is applicable to proceedings before the Arbitrator even if Section 34 does not directly apply. The Court invoked this principle to support the conclusion that the Arbitrator's award of simple interest at 16% per annum (pendente lite and future interest) was lawful and should be upheld.

Court's Reasoning and Analysis

The Court addressed the respondents' objections claim-by-claim, applying the standards for interference with an arbitral award under Sections 30 and 33 and the requirement for a reasoned award where the parties had agreed to a reasoned award. The reasoning proceeds as follows:

General approach

The Court repeatedly emphasized that it cannot act as an appellate forum to re-appreciate evidence where the Arbitrator has given reasons and no error apparent on the face of the record is shown. Conversely, where the Arbitrator failed to indicate his reasoning or thought process as required, that deficiency may constitute an error apparent on the face of the record justifying interference.

Claim-by-claim analysis

  • Claim No. 1 (refund of rebate): The petitioner claimed Rs. 18,494/-. The Arbitrator awarded (the opinion records) Rs. 15,096/- in favour of the petitioner and gave reasons. The Court found that respondents could not demonstrate any mistake or error apparent on the face of the record and therefore upheld the Arbitrator's decision on Claim No. 1.
  • Claim No. 2 (final bill / extra item work): The petitioner claimed Rs. 1,51,892/-, and the Arbitrator accepted the claim in full and awarded that amount. The Arbitrator's award attributed extra payment principally to item 5.1 (stone veneering) and reached an extra-amount figure of Rs. 97,796/- based on certain rates and quantities, with an additional amount of Rs. 8,224.80 for other items. The respondents contended that the Arbitrator failed to give reasons and did not indicate his thought process. On review, the Court found that the Arbitrator had merely stated conclusions (including the Rs. 97,796/- figure and the correct rate of Rs. 324/- per sq. mtr.) without demonstrating the intermediate reasoning or calculations. Because the parties had agreed to a reasoned award, the Court concluded that this failure amounted to an error apparent on the face of the record and therefore set aside the findings on Claim No. 2, remitting it to the Arbitrator for fresh determination.
  • Claim No. 3 (escalation / extra expenditure): The petitioner claimed Rs. 2,31,088/-. The Arbitrator awarded Rs. 1,48,375/-, basing that figure on an asserted rise in the cost index for works in Delhi (from Rs. 421/- to Rs. 564/-, average 492.5) and calculated an increase of 16.86%, with "extra expenditure" during the extended period assessed at Rs. 1,28,375/- after adjusting site costs. The Court observed that the Arbitrator did not indicate how he arrived at the Rs. 1,48,375/- figure, did not disclose the calculation or the basis for site establishment costs or adjustments, and that the award appeared to reflect assessment on the basis of Clause 10CC, which the Arbitrator had itself found to be deleted in the contract copy. The Court found these deficiencies to amount to an error apparent on the face of the record and therefore set aside the award on Claim No. 3 and remitted it to the Arbitrator for fresh consideration.
  • Claim No. 5 (refund of illegal holding): Claim for Rs. 26,000/- was awarded in full by the Arbitrator, who gave reasons. The Court declined to re-appreciate evidence, found no error apparent on the face of the record shown by the respondents, and upheld the award on Claim No. 5.
  • Claim No. 6 (reimbursement for under-utilised resources due to prolongation): Claim for Rs. 3,00,000/-; prolongation of work was undisputed. The Arbitrator awarded Rs. 1,74,500/- based on the petitioner's evidence and arithmetical calculation. The Court found the award to be supported by evidence and valid arithmetical reasoning and therefore upheld it.
  • Claim No. 7 (loss of profit): Claim for Rs. 2,50,000/-; Arbitrator awarded Rs. 66,277/- by assessing profit at 8%. The Arbitrator found rescission of the contract was neither justified nor legal, entitling contractor to loss of profit; the Court noted authorities indicating that even 15% might be reasonable in some circumstances but found the Arbitrator's choice of 8% to be reasonable based on his reasoning. The Court therefore declined to interfere with this award.
  • Claim No. 8 (interest): Petitioner sought interest at 24% p.a.; Arbitrator awarded simple interest at 16% p.a. w.e.f. 28.4.1993 until decree/payment (pendente lite and future interest). The Court examined Supreme Court precedents (Secretary, Irrigation Dept. v. G.C. Roy and Hindustan Construction Co. Ltd. v. State of J&K) and held that the Arbitrator was competent to award post-award interest and that the principles of Section 34 CPC regarding interest pendente lite/post-decree are applicable in arbitration proceedings. Applying those precedents, the Court upheld the Arbitrator's award of interest at 16% p.a.

Remittal and Directions

For the parts of the award set aside (Claims Nos. 2 and 3), the Court remitted those claims to the Arbitrator to be decided afresh on merits. The Arbitrator was directed to give his decision on Claims Nos. 2 and 3 within four months from receipt of a copy of the Court's order.

Holding and Implications

Core Ruling: Petition partly allowed.

Detailed holdings and immediate consequences:

  • Set aside and remitted: The Court set aside the Arbitrator's findings in respect of Claim No. 2 and Claim No. 3 and remitted those claims to the Arbitrator to decide afresh in accordance with law within four months of receipt of this order.
  • Upheld: The Court upheld the Arbitrator's awards in respect of Claim No. 1, Claim No. 4 (the opinion references Claim No. 4 when making the award a Rule of Court), Claim No. 5, Claim No. 6, Claim No. 7, and Claim No. 8, and also upheld counterclaims 1 to 4 as part of the award made a Rule of the Court.
  • Rule of Court and decree: The portions of the award upheld by the Court were ordered to be made a Rule of the Court and a decree was to be drawn in terms of those parts.
  • Interest: The petitioners were held entitled to interest at 16% per annum in respect of the upheld portions of the award, from the date of the decree until the date of realisation.

Broader implications: The opinion enforces the requirement that, where the parties expect a reasoned award, the Arbitrator must disclose the reasoning and thought process; failure to do so may amount to an error apparent on the face of the record and justify interference. The Court applied established Supreme Court authorities concerning the Arbitrator's competence to award pendente lite and post-award interest. The opinion does not purport to lay down a new precedent beyond applying these established principles; its practical consequences are limited to the parties (remittal of Claims 2 and 3 and enforcement of the remaining award components).

Petition partly allowed.
Show all summary ...

Dr. M.K Sharma, J.— The present suit has been registered after the Arbitrator filed his award in this Court alongwith the records of the arbitration proceedings. After registration of the suit notice was issued to the parties intimating them about the filing of the award and to file objections, if any, within the statutory time limit.

2. On service of notice on the parties the respondents filed their objections under sections 30 & 33 of the arbitration act against the award passed by the Arbitrator on 20.10.1994 The petitioner however, did not file any objection against the award.

3. It is admitted position that the Arbitrator who dealt with the arbitration proceedings was the named Arbitrator and a technical person.

4. Although the respondents have filed their objection as against almost all the claims decided by the Arbitrator yet during the course of hearing the main thrust of argument advanced by learned Counsel for the respondents was directed against the decision of the Arbitrator as against claims No. 2, 3, 5 & 6. However, since the learned Counsel appearing for the respondents also made his submissions in respect of the other claims as decided by the Arbitrator as well, I propose to deal with the arguments advanced by the learned Counsel for the respondents as against all the objections raised in the objection petition filed by the respondents. None appeared on behalf of the petitioner at the time of arguments. However, since the objection is of the respondents, I proceed to decide the same.

Claim No. 1:

5. The petitioner claimed Rs. 18,494/- as refund of rebate as contingent conditions governing rebates were not fulfilled by the respondent in respect of the following issues—(a) for regular monthly payments: Rs. 9,245/-; (b) for final bill payment: Rs. 6,163/-; (c) for refund of security deposit: Rs. 3,082/- and (d) for timely sanction of EI/SI: Rs. 4/-. As against the aforesaid claims the Arbitrator has awarded Rs. 15,096/- in favour of the petitioner. The Arbitrator, while giving his decision as against the aforesaid claim and awarding Rs. 15,906/- has given reasons and the learned Counsel appearing for the respondents could not make out any case for interference with the said decision of the Arbitrator. No mistake or error apparent on the face of the record could be shown and established by the respondents and, therefore, the decision of the Arbitrator against claim No. 1 is upheld.

Claim No. 2:

6. In respect of claim No. 2 the petitioner claimed Rs. 1,51,892/- on account of final bill and the Arbitrator has accepted the claim in full and awarded Rs. 1,51,892/- against the aforesaid claim in favour of the petitioner. I have been taken through the award passed by the Arbitrator against the aforesaid claim and on perusal of the same I find that the said amount was claimed as an extra amount for extra item of work. According to the Arbitrator the extra amount against main disputed items is payable for the agreement item No. 5.1—Stone veneering, which according to the Arbitrator is an extra item payable at rate under Clause 12(v) of the agreement. The Arbitrator has held that the rate paid in R.A bills is Rs. 154.85 for quantity of 454.77 Sq. Mtrs. as against correct rate of Rs. 324/- per sq. mt. and that the final quantity of work done is 519.19 sq. mtrs. and thus extra amount payable works out to Rs. 97,796/- payable on that account.

7. The other extra amount awarded by the Arbitrator is in respect of quantities of other main agreement items viz. item amounting to Rs. 8,224.80. Learned Counsel appearing for the respondent submitted that the Arbitrator was required to give a reasoned award. According to the learned Counsel while giving his decision on the aforesaid claim the Arbitrator has failed to give reasons and to indicate is thought process which is sufficient ground for setting aside the award.

8. On a perusal of the award of the Arbitrator as against the aforesaid claim it is not clear as to how the Arbitrator has arrived at his conclusion that the extra amount payable works out to Rs. 97,796/-. I find that the Arbitrator has only given his conclusion which is not substantiated by any reason. It needs no reiteration to hold that when the parties agree that the Arbitrator would give a reasoned award, it is imperative on the part of the Arbitrator to give reasons for his conclusion and that if he does not do so the same amounts to an error on the face of the record, which would call for setting aside of the award. A bare perusal of the award of the Arbitrator would show that the Arbitrator has failed to indicate his thought process in arriving at the conclusion that the extra amount payable works out to Rs. 97,796/-. The thought process of the Arbitrator in arriving at a conclusion that correct rate applicable would be Rs. 324/- per sq. mtr. is also not indicated. I, therefore, set aside the findings of the Arbitrator on the aforesaid claim No. 2.

Claim No. 3:

9. Under claim No. 3 the petitioner claimed Rs. 2,31,088/-, as against which the Arbitrator has awarded Rs. 1,48,375/-. While awarding the aforesaid amount the Arbitrator has held that the cost index for works in Delhi rose from Rs. 421/- to Rs. 564/- with an average of 492.5 during the extended period, resulting in increase in price of materials and labour by 16.86% and that after adjusting the cost of site, extra expenditure during the extended period is assessed at Rs. 1,28,375/-. Therefore, the aforesaid award apparently is based on increase in price of the material and labour. The Arbitrator has failed to give any reason for arriving at the amount of Rs. 1,48,375/-. He has also not indicated any reason as to what was the cost of site establishment and how and in what manner the same is calculated and what was the actual figure for the same which has been adjusted. Apparently, therefore, the Arbitrator has failed to indicate his thought process and give reasons in arriving at the aforesaid amount towards extra expenditure.

10. It is also to be noted that claim of the petitioner on account of escalation in the prices of materials and wages of labour in Clause 10CC was rejected by the Arbitrator as Clause 10CC stood deleted in the copy of the contract agreement. The award given by the Arbitrator as against the aforesaid claim also appears to be assessment of an amount on the basis of Clause 10CC.

11. Therefore, there appears to be an error apparent on the face of the record and therefore, this award also cannot be sustained.

Claim No. 5:

12. Claimants had claimed Rs. 26,000/- on account of refund of illegal holding which was awarded in toto by the Arbitrator. On perusal of the award passed by the Arbitrator as against the aforesaid claim, I find that the Arbitrator had given reasons for arriving at the aforesaid finding. The Court cannot sit in appeal against the award made by the Arbitrator. Re-appreciation of evidence is beyond the purview of the Courts on an application under sections 30 & 33 of the arbitration act. The respondents have failed to prove and establish any mistake or error apparent on the face of the record and, therefore, this award is upheld.

Claim No. 6:

13. So far as claim No. 6 is concerned the same relates to claim of Rs. 3,00,000/- on account of reimbursement of losses by way of unutilized/under utilized services of Engineer, Staff, plant, machinery, shuttering and overheads due to prolongation of contract. It is not disputed that there was prolongation of work beyond the stipulated date of completion. The amount arrived at by the Arbitrator to the extent of Rs. 1,74,500/- is based on evidence adduced by the petitioner. On the basis thereof the Arbitrator held that on arithmetical calculations and valid reasons the amount arrived at as bare minimum and unavoidable. I, therefore, do not find any error apparent on the face of the record in respect of the aforesaid award and accordingly I uphold the said award.

Claim No. 7:

14. The petitioner has claimed Rs. 2,50,000/- on account of loss of profit/profitability due to prolongation of contract under Claim No. 7, as against which the Arbitrator has awarded Rs. 66,277/- in-favour of the petitioners. The aforesaid amount has been arrived at calculating the claim of profits @ 8% which in my opinion, is reasonable and justified. It has been held by the Arbitrator that the rescission of the contract was neither justified nor legal and therefore, the petitioner is entitled to profits which they could be expected to earn on completion of the entire work as per contract this Court cannot sit on appeal on the aforesaid findings recorded by the Arbitrator and reappreciate the same. Accordingly, when it is found that the recission of the contract was not legal and justified the contractor becomes entitled to claim for loss of profit. In such circumstances the Courts have held that even 15% of the total value of the contract would be reasonable and justified. The Arbitrator in the present case on consideration of the facts held that the contractor is entitled to 8% which cannot be said to be unjustified. The Arbitrator having decided to reimburse as damages to the tune of Rs. 66,277/- and having given reasons for his decision, which are found to be valid and justified, there is no reasonable ground to interfere with the aforesaid award of the Arbitrator.

Claim No. 8:

15. Claim No. 8 relates to payment of interest @ 24% per annum as against which the Arbitrator has awarded simple interest @ 16% per annum w.e.f 28.4.1993 to the date of decree or payment i.e pendente lite interest and also future interest. In the case of Secretary, Irrigation Department v. G.C Roy, 1991 (6) JT 349 the Supreme Court had occasion to deal with the power of the Arbitrator to award interest pendente lite. In the said decision it was held that the Arbitrator is competent to award interest for the period commencing with the date of award to the date of decree or the date of realisation whichever is earlier. In Hindustan Construction Co. Ltd. v. State Of Jammu & Kashmir., 1992 (2) Arbitration Law Reporter 412 the Supreme Court while referring to the decision in the case of Secretary Irrigation Department (supra) held that the award of interest by the Arbitrator for the period commencing with the date of award to the date of decree or the date of realisation whichever is earlier is logical for, while award of interest for the period prior to an Arbitrator entering upon the reference is a matter of substantive law, the grant of interest for the post-award period is a matter of procedure. It is further held that Section 34 of the Code of Civil Procedure provides both for award of interest pendente lite as well as for the post-decree period and the principle of Section 34 has been held applicable to proceedings before the Arbitrator though the section as such might not apply. In view of the aforesaid decisions of the Supreme Court the award of interest @ 16% per annum by the Arbitrator in respect of pendente lite and future interest has to be upheld.

16. Accordingly, therefore, I set aside that part of the award of the Arbitrator as against Claims No. 2 & 3 and remit it to the Arbitrator to decide these claims afresh on merits.

17. I, therefore, allow the objections to the extent indicated above and remit the matter to the Arbitrator for deciding Claims No. 2 & 3 afresh in accordance with law. The objections of the respondents in respect of the remaining claims are dismissed. The award is made a Rule of the Court as far as Claims No. 1, 4, 5, 6, 7 & 8 and counter claims 1 to 4 are concerned. The Arbitrator is directed to give his decision afresh in respect of claims No. 2 & 3 within 4 months from the date of receipt of a copy of this order.

18. Let a decree be drawn in terms of the aforesaid part of the award, which this Court has hereby upheld. It is ordered that the petitioners shall be entitled to interest @ 16% per annum in respect of the aforesaid award from the date of the decree till the date of realisation.

Petition partly allowed.