Pishori Lal Maggo v. Delhi Development Authority .
Summary of Judgment — Dr. M.K. Sharma, J.
Factual and Procedural Background
The Arbitrator filed an award along with the arbitration proceedings. On filing of the award the present suit was registered and notices were issued directing the parties to file objections within the statutory time limit. On service the petitioner did not file any objection, but the respondents filed objections under Sections 30 and 33 of the Arbitration Act, which were registered as I.A. No. 6320/1994. The petitioner filed a reply to those objections. The respondents' objections challenged the Arbitrator's award in respect of Claim Nos. 2, 3, 4, 8 and 9. The Court heard counsel, examined the arbitration record and proceeded to dispose of the objections claim-wise.
Legal Issues Presented
- Whether the award in respect of Claim No. 2 (Rs. 7,825/- awarded for materials pilfered/damaged/transport loss) is vitiated by nondisclosure of the Arbitrator's mental process and therefore liable to be set aside.
- Whether the award in respect of Claim No. 3 (cartage claim: petitioner sought Rs. 40,000/-, Arbitrator awarded Rs. 32,100/-) is invalid for lack of disclosed reasoning and/or insufficient basis.
- Whether the award in respect of Claim No. 4 (advance to DESU and wiring expenditure: claim Rs. 6,600/-, award Rs. 3,250/-) is sustainable despite absence of supporting vouchers.
- Whether the award in respect of Claim No. 8 (damages: claim Rs. 1 lac, award Rs. 20,250/-) is legally supportable given the documentary evidence and admissions in the arbitration.
- Whether the award in respect of Claim No. 9 (loss of profit: claim Rs. 3,50,000/-, award Rs. 1,25,152/-) is permissible, having regard to the contract clause providing 10% profit and authorities on loss of profit and Section 73 of the Contract Act.
- Whether the Court may probe the arbitrator's "thought process" (i.e., mental reasoning) in reviewing the award.
Arguments of the Parties
Respondents' Arguments
- The respondents objected (under Sections 30 & 33 Arbitration Act) to the awards in respect of Claim Nos. 2, 3, 4, 8 and 9.
- For Claim No. 2: they contended the Arbitrator did not disclose the mental process or basis for fixing the amount of Rs. 7,825/-, and that Claim No. 2 should be rejected on the same ground as Claim No. 7, which was rejected because the site was not available and structural drawings were not given.
- For Claim No. 3: they objected that the award of Rs. 32,100/- lacks disclosed basis and does not reveal the reasoning by which the Arbitrator arrived at that figure.
- For Claim No. 4: implicitly they challenged the award by contesting the petitioner’s entitlement where no supporting vouchers were produced (this is reflected in the Court's consideration).
Petitioner's Arguments / Evidence
- The petitioner produced vouchers in support of the cartage claim (Exs. C-15/1 to C-15/17).
- There was an admission in arbitration that the claimant had brought certain materials to site (e.g., 2,50,000 bricks; 500 cu.m. 40 mm stone aggregate; 500 cu.m. 12 mm stone aggregate), and respondents admitted materials and that chowkidars were kept on site (attendance register Ex. C-16).
- The petitioner relied on the contractual clause (Clause 2(a) of the notice inviting tender) stating the site was available and the contractor was to start work at once, to justify bringing materials to site and claims for cartage.
- As to loss of profit (Claim No. 9), the petitioner relied on the contract provision fixing contractor's profit at 10% of estimated cost, and authorities (A.T. Brij Paul Singh & Bros. v. State of Gujarat and Metro Electric Co. v. Delhi Development Authority) together with Section 73 of the Contract Act to justify the award for loss of profit.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| A.T. Brij Paul Singh & Bros. v. State of Gujarat, (1984) 4 SCC 59 : AIR 1984 SC 1703 | Contractor is entitled to claim damages for loss of profit expected from undertaking the work contract; previous awards of damages at a given rate may support similar awards in related breaches. | The Court relied on this Supreme Court authority to support the proposition that a contractor is entitled to claim profit (here, assessed at 10% of estimated cost) as compensation for loss of expected profit in case of breach. |
| Metro Electric Co. v. Delhi Development Authority, AIR 1980 Delhi 266 | The clause regarding payment of 10% extra price/profit was applicable to facts of that case and the award of damages on that basis was proper. | The Court cited this decision to reinforce that a contractual provision entitling the contractor to 10% profit may be a proper basis for awarding damages for loss of profit. |
Court's Reasoning and Analysis
The Court proceeded claim by claim, examining the arbitration record, documentary evidence and admissions in the arbitration proceedings, and applying established legal principles (including the limitation on court review of an arbitrator's mental process):
Claim No. 2 (Rs. 7,825/- awarded)
- The respondents argued the Arbitrator did not disclose the basis for the specific amount and that, by analogy to Claim No. 7 (which was rejected for lack of site/material necessity), Claim No. 2 should also be rejected.
- The Court distinguished Claim No. 2 from Claim No. 7: Claim No. 7 related to materials required for construction above plinth level and was rejected because those materials were not necessary at that stage; Claim No. 2 related to pilfered/damaged materials and losses in transportation (stone grit, bricks, Yamuna sand, Badarpur sand), which were different in nature.
- The award itself recorded admissions that the claimant had brought to site 2,50,000 bricks and specified quantities of stone aggregate. Considering those admissions and the evidence, the Arbitrator found the petitioner entitled to Rs. 7,825/-. The Court noted the Arbitrator stated he considered the submissions and facts placed before him.
- The Court applied the well-settled principle (from Supreme Court decisions) that a court cannot probe into the arbitrator's mental thought process; where the arbitrator indicates he considered the material and there is evidentiary support, the award is not vitiated by nondisclosure of internal reasoning. The Court found no illegality in Claim No. 2 award.
Claim No. 3 (Cartage: claimed Rs. 40,000/-, awarded Rs. 32,100/-)
- The respondent objected that the basis for the Arbitrator's figure was not disclosed.
- The petitioner had produced vouchers (Exs. C-15/1 to C-15/17). The respondents admitted the claimant brought materials to site. The contract (Clause 2(a) of the notice inviting tender) stated the site was available and work was to start at once, making it necessary to bring materials to site.
- Considering the vouchers, admissions and contractual clause, the Arbitrator's award of Rs. 32,100/- was justified. Again, the Court reiterated it could not probe the Arbitrator's internal thought process, and found no illegality in the award.
Claim No. 4 (Advance to DESU/wiring: claimed Rs. 6,600/-, awarded Rs. 3,250/-)
- The Arbitrator awarded Rs. 3,250/- for wiring costs, but the petitioner admitted that no voucher was produced before the Arbitrator to substantiate the claim.
- Because the claim lacked vouchers or supporting documents, the Court found no justification for the award and set aside the Arbitrator's award in respect of Claim No. 4.
Claim No. 8 (Damages: claimed Rs. 1,00,000/-, awarded Rs. 20,250/-)
- The award of Rs. 20,250/- was supported by documentary evidence (attendance register Ex. C-16) and the respondents admitted that chowkidars were kept at the site for watch and ward of materials.
- In view of the documentary support and the admission, the Court found no illegality in the Arbitrator's award for Claim No. 8.
Claim No. 9 (Loss of profit: claimed Rs. 3,50,000/-, awarded Rs. 1,25,152/-)
- The contract provided that the contractor's profit is to be considered at 10% of the estimated cost. The Court referred to the contractual provision and cited authorities (A.T. Brij Paul Singh & Bros. and Metro Electric Co.) recognizing entitlement to damages for loss of profit and the propriety of assessing profit at a contractual rate (10%).
- The Court also relied on Section 73 of the Contract Act as the statutory basis for compensating loss of profit. Applying these principles and the contractual term, the Court found no illegality in the Arbitrator's award in respect of Claim No. 9.
Overarching Analytical Point on Review of Arbitrator's Reasoning
The Court repeatedly applied the principle that it is not its function to probe into the arbitrator's internal mental process where the arbitrator states he considered submissions and facts and where there is evidentiary support for his conclusions. Absent illegality or lack of evidentiary basis, the awards were upheld.
Holding and Implications
Core Ruling: Petition dismissed.
Further specifics of the Court's final decision and direct consequences for the parties:
- Objections in respect of Claim Nos. 2, 3, 8 and 9 are dismissed (i.e., those parts of the Arbitrator's award are upheld).
- The objection in respect of Claim No. 4 is allowed and the Arbitrator's award in respect of Claim No. 4 is set aside.
- Part of the Arbitrator's award relating to Claim Nos. 2, 3, 8 and 9 is made a Rule of the Court; the award in respect of Claim No. 4 is set aside and a decree will be drawn accordingly.
- The petitioner is entitled to interest at the rate of 12% per annum from the date of the decree until realization.
- The parties shall bear their own costs.
No broader precedent was announced beyond application of existing principles (including the limitation on courts probing an arbitrator's thought process and the application of contractual/authoritative guidance on loss of profit). The decision's practical effect is limited to upholding most parts of the arbitrator's award and setting aside the portion unsupported by vouchers (Claim No. 4).
Petition dismissed.
Dr. M.K Sharma, J.— The Arbitrator filed the award alongwith the proceedings on filing of which the present suit was registered and notices were issued to the parties directing the parties to file the objections within the statutory time limit. On service of notice the petitioner did not file any objection but the respondents filed their objections under sections 30 & 33 of the arbitration act which was registered as I.A No. 6320/1994. The petitioner filed his reply to the aforesaid objections filed by the respondents.
2. In the objections filed by the respondents objections were taken with regard to the award passed by the Arbitrator in respect of Claim No. 2, 3, 4, 8 & 9.
3. I have heard the learned Counsel for the parties who have taken me through the grounds of objections, the award passed by the Arbitrator and also the records of the arbitration proceedings. On consideration of the materials on record and upon hearing the Counsel for the parties I propose to dispose of the present objections filed by the respondents dealing with each of the objections claim-wise as follows:
Claim No. 2:
4. The objections raised against the award of the Arbitrator in respect of claim No. 2 awarding a sum of Rs. 7,825/- in favour of the petitioner relates to the nondisclosure of the mental process by the Arbitrator in arriving at an arbitrary amount of Rs. 7,825/-. According to the learned Counsel the reason to arrive at the aforesaid conclusion of awarding a sum of Rs. 7,825/- in favour of the petitioner is not disclosed in the award. According to him the basis of the amount having not been disclosed and the fact that such a claim having been rejected by the Arbitrator against claim No. 7 on the ground that site was not available and therefore, there was no necessity of bringing the material on the site, the claim in respect of claim No. 2 should have also been rejected on the same ground as the structural drawing was not given to the petitioner nor the site was made available and no work was started.
5. In respect of the aforesaid submissions of the learned Counsel for the respondent it could be said that so far as the reasons given by the Arbitrator in respect of claim No. 7 rejecting the claim of the petitioner is concerned, it appears that the same was rejected on the ground that there was no necessity of bringing the materials mentioned therein at that stage since such materials were required for construction work above the plinth level. However, so far as the claim in respect of claim No. 2 is concerned the same is for the materials pilferred, damaged and due to loss in transportation etc. in respect of stone grit, bricks, Yamuna sand and Badarpur sand which were not similar materials as that of the materials of claim No. 7. It is also stated in the award that the claimant had brought at site 2,50,000 bricks, 500 cum. 40 mm. stone aggregate and 500 cum. 12 mm. stone aggregate. In view of the aforesaid admission and on considering the evidence on record the Arbitrator has come to a finding that the petitioner is entitled to a claim of Rs. 7,825/-.
6. According to the learned Counsel for the respondents the aforesaid award is arbitrary and without any reason. However, it is well settled by the decisions of the Supreme Court that the Court cannot probe into the thought process of the Arbitrator. While giving the award against claim No. 2 the Arbitrator has stated categorically that “on consideration of the submissions and facts placed before him”, which means that he has considered the materials placed before him. Besides there is a clear admission of the respondents in the arbitration proceedings that the materials like bricks, stone aggregate to the site. Considering all those facts when the Arbitrator came to the conclusion that there was some loss of materials due to handling in transportation and storage. I do not find any illegality in respect of the aforesaid award made by the Arbitrator as against claim No. 2.
Claim No. 3:
7. So far as the aforesaid claim is concerned the same relates to claim of the petitioner to the extent of Rs. 40,000/- towards cartage of material while bringing to and taking it from the site of work for which the Arbitrator has awarded Rs. 32,100/-. The objection taken by the respondent against the aforesaid award is that the basis of the amount arrived at by the Arbitrator has not been disclosed in the award and the reason to arrive at the aforesaid conclusion has also not been stated in the award. According to the Counsel it also does not disclose the thought process of the Arbitrator in arriving at the aforesaid conclusion.
8. The petitioner has produced in the arbitration proceedings vouchers in support of the aforesaid claim which are Exs. C-15/1 to C-15/17. It further appears from the record and as stated in the award that the respondents have admitted during the arbitration proceedings that the claimant had brought to site certain materials for starting construction which was agreed upon to be started immediately. At page 11 of the agreement i.e notice inviting tender, there is Clause 2(a) which states that the site of work is available and that the contractor is to start work at once. In view of the aforesaid condition it was necessary for the petitioner to bring certain materials to the site in order to enable him to start work at once as required under the agreement. In view of the admission of the respondent that the claimant had brought certain materials to the site and the claim for cartage having been supported by the vouchers produced in the proceedings the Arbitrator was justified, after taking into consideration the aforesaid matter, in awarding Rs. 32,100/- as already held hereinabove. This Court is not justified and/or has no jurisdiction to probe into thought process of the Arbitrator as has been held by the Supreme Court.
Claim No. 4:
9. Similarly, so far as claim No. 4 is concerned the same relates to a claim of Rs. 6,600/- towards advance given to DESU as security and expenditure incurred for installation of wires etc. as against which the Arbitrator has awarded a sum of Rs. 3,250/-. The aforesaid amount of Rs. 3,250/- was awarded by the Arbitrator for payment of cost of installation of wiring in the area. However, it appears on the record and as admitted by the Counsel for the petitioner that in support of the aforesaid claim no voucher could be produced by the petitioner before the Arbitrator. Since the aforesaid claim was not supported by any voucher and/or any other supporting document, I do not see any justification in awarding the aforesaid amount in favour of the petitioner and accordingly the aforesaid award of Rs. 3,250/- awarded in favour of the petitioner as against claim No. 3 by the Arbitrator is set aside.
Claim No. 8:
10. Under this claim the petitioner claimed Rs. 1 lac. towards damages, as against which the Arbitrator has awarded a sum of Rs. 20,250/-. On perusal of the award as against the aforesaid claim it is found that the aforesaid claim to the extent of Rs. 20,250/- is supported by documentary evidence like the attendance register Ex. C-16. It further appears that the respondents also admitted during the arbitration proceedings that the claimant had kept Chowkidars at the site of work for watch and ward of the materials. In view of the admission on the part of the respondents and also in view of the fact that the claim to the extent of Rs. 20,250/- is supported by documentary evidence, I do not see any illegality in the aforesaid award passed by the Arbitrator in respect of claim No. 8.
Claim No. 9:
11. Claim No. 9 relates to the claim of the petitioner to the extent of Rs. 3,50,000/- as loss of profit as against which the Arbitrator has awarded Rs. 1,25,152/-. Considering the contractor's rate of profit at 10% of the estimated cost of the present work being at Rs. 35,19,502/- and 10% of the said amount being much less than Rs. 1,25,152/- the learned Counsel for the petitioner submits that there is legal basis in awarding the aforesaid amount against claim No. 9.
12. The agreement arrived at between the parties lays down that in respect of a work contract, claim of profit by the contractor at 10% of the estimated cost is justified. In this connection reference may be made to a decision of the Supreme Court in A.T Brij Paul Singh & Bros. v. State of Gujarat”, (1984) 4 SCC 59 : AIR 1984 SC 1703, wherein the Supreme Court has held that the contractor is entitled to claim damages for the loss of profit which he Is expected to earn by undertaking the work contract. It is further held that where there was breach of contract in respect of works contract for construction of a portion of the road by the State, it could not be said that the contractor would not be entitled to 15% of the balance price of the works contract as damages when in respect of the breach of works contract for another portion of the same road in the vicinity of the portion in question the High Court has granted to the same contractor, damages at the same rate. In Metro Electric Co. v. Delhi Development Authority”, AIR 1980 Delhi page 266, it has been held by this Court that the clause regarding payment of 10% extra price was applicable to the facts of the case and the award of damages was proper. In view of the aforesaid decision of this Court and also of the Supreme Court it could be held that a contractor is entitled to claim a profit at 10% of the estimated cost of construction in respect of a work contract. Since there was a loss of expected profit, the petitioner is entitled to be reimbursed atleast to the extent of 10% of the estimated cost in terms of Section 73 of the Contract Act. In that view of the matter, I do not find any illegality in the award of the Arbitrator passed in respect of the aforesaid claim.
13. In the result, the objections filed in respect of Claims No. 2, 3, 8 & 9 are dismissed and the same stands allowed in respect of Claim No. 4 of the award.
14. In terms of the aforesaid findings that part of the award passed by the Arbitrator relating to Claims No. 2, 3, 8 & 9 is made a Rule of the Court. The award in respect of claim No. 4 stands set aside. Let a decree be drawn in terms of the above. In addition, the petitioner shall be entitled to interest @ 12% per annum from the date of the decree till realisation. The parties shall bear their own costs.
Petition dismissed.