Parmar Construction Co. v. Delhi Development Authority

Delhi High Court
Nov 1, 1995
Smart Summary (Beta)

Structured Summary of the Opinion (Devinder Gupta, J.)

Factual and Procedural Background

This opinion concerns objections by the Delhi Development Authority (D.D.A.) to an arbitration award dated 13th November, 1992, made by Shri Shyam Narayan, the Sole Arbitrator. The disputes arose out of the execution of the redevelopment work of Kingsway Camp (SH; Construction of SW drains at Outran Lines) awarded under Agreement No. 3.EE/CD.VLL/85-86.

The D.D.A.'s objections challenged (a) the rejection by the arbitrator of the D.D.A.'s counterclaim (a claim of Rs. 9,408/- pursuant to clause 2 of the agreement as compensation for delay), and (b) various awards made in favour of the claimants under claim Nos. 1 to 4 and 6. The matter came before Devinder Gupta, J., who reviewed the arbitrator's reasoning, the arbitrability of certain issues, and the sufficiency of reasons provided for awards on individual claims.

Legal Issues Presented

  1. Whether the quantum of levy (compensation levied under clause 2 for delay) is arbitrable.
  2. Whether the arbitrator had jurisdiction to go into the merits of the levy of compensation by Executive Engineer/Superintending Engineer and to reject the D.D.A.'s counterclaim.
  3. Whether the arbitrator's awards on claim Nos. 1, 2, 3, 4 and 6 suffer from an error apparent on the face of the record for lack of reasons or for deciding on materials to which the objector had no opportunity to reply.
  4. The extent to which a court may interfere with an arbitrator's award on grounds of error apparent on the face of the record.

Arguments of the Parties

Delhi Development Authority (Objector / Respondent)

  • Maintained a counterclaim for Rs. 9,408/- as compensation levied under clause 2 for delay and objected to the arbitrator's rejection of that counterclaim.
  • Contended that the arbitrator should have given reasons for certain awards (in particular claim Nos. 1, 2, 3 and 4) and that the failure to provide reasons amounted to an error apparent on the face of the record.
  • Argued that in respect of claim No. 2 the claimant filed details only on the last date of hearing (22nd September, 1992) and the arbitrator awarded on that basis without affording the D.D.A. opportunity to rebut the revised statement.
  • Challenged the lump-sum award under claim No. 4 on the ground that the arbitrator did not specify how much was awarded against each sub-head and failed to explain the basis for distribution among sub-heads.
  • Challenged awards of pendente lite and future interest on the ground that the arbitrator was not empowered to grant future interest.

Claimant

  • Claimant asserted entitlement to various payments, including final bill amounts and payments under clause 10-C, and sought recovery of those amounts through the arbitration process.
  • Claimant contended the final bill was ready (noting a communication on 13th April, 1988) and that amounts were not paid despite reminders; disputed recoveries such as penal recovery of steel and withholding for unsanctioned extra items.
  • Filed details of amounts (including a revised statement) before the arbitrator, which the arbitrator considered when making awards.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Vishwa Nath Sood v. Union of India, A.I.R. 1989 S.C. 962 Principle that the quantum of levy (compensation) imposed by departmental authorities is non-arbitrable. The arbitrator relied on this decision to hold that quantum of levy was non-arbitrable. The court agreed that quantum is non-arbitrable but held that the arbitrator erred in going further and adjudicating the merits of the levy and rejecting the D.D.A.'s counterclaim; such merits are outside arbitrator's jurisdiction under the cited authority.
Delhi Development Authority v. Sudhir Bros, 1995 (32) D.R.J. 366 Authority that an arbitrator has no jurisdiction to go into the merits of levy of compensation by a Superintending Engineer. The court noted that a Division Bench had set aside an arbitrator's award insofar as the arbitrator had gone into the Engineer's decision on levy of compensation. The present court applied the same reasoning to set aside the arbitrator's findings that rejected the D.D.A.'s counterclaim.
Metro Electric Co…. v. Delhi Development Authority, AIR 1980 Delhi 266 Support for entitlement to payment under clause 10-C of the agreement in appropriate circumstances. The arbitrator relied on this decision in holding that the claimant was entitled to payment under clause 10-C. The court found the arbitrator's reliance justified and that the award under claim No. 2 was properly founded.

Court's Reasoning and Analysis

The court analysed the objections in two broad strands: (A) the scope of the arbitrator's jurisdiction regarding the levy of compensation, and (B) whether the arbitrator's awards on the individual claims were vitiated by want of reasons or error apparent on the face of the record.

A. Jurisdiction over levy/compensation:

  • The court accepted the arbitrator's initial conclusion — based on Vishwa Nath Sood (supra) — that the quantum of levy of compensation is non-arbitrable.
  • However, the court held that the arbitrator erred by going further and entering into the merits of the levy (i.e., assessing the justification for the levy and concluding the D.D.A. had waived its right). In the court's view, once the quantum/levy is non-arbitrable, the arbitrator lacked jurisdiction to adjudicate justification or demerits of the compensation.
  • Relying on the Division Bench decision in Delhi Development Authority v. Sudhir Bros, the court reiterated that an arbitrator has no jurisdiction to decide the merits of a levy imposed by the Superintending Engineer; where an arbitrator has done so, that portion of the award is liable to be set aside.
  • The court therefore set aside the arbitrator's finding rejecting the D.D.A.'s counterclaim and observed that the D.D.A. is at liberty to pursue recovery of the compensation by other proceedings permissible in law.

B. Scope of interference with the arbitrator's awards on individual claims:

  • The court emphasised the limited scope of judicial interference with an arbitrator's award: an arbitrator's award on facts and law is final and the court cannot review or correct mistakes of adjudication unless there is a legal error apparent on the face of the award.
  • The court explained that an "error of law apparent on the face of the record" must be discernible from the award or documents incorporated in it; extraneous documents cannot be used to demonstrate such an error.
  • Applying these principles, the court examined the arbitrator's reasons on the challenged claims and found that the arbitrator had provided reasons and had based findings on material on record. The court concluded that the assessments of evidence and factual findings were within the arbitrator's province and not susceptible to interference on the grounds advanced by the D.D.A.

C. Application to specific claims (as summarised by the court):

  • Claim No. 1 (final bill and withholdings): The arbitrator examined clauses 12 and 42 of the agreement and explained why withholding Rs. 9,177/- for over five years and the penal recovery were not justified. The court found the reasons adequate and not vitiating the award.
  • Claim No. 2 (payment under clause 10-C): The arbitrator held delay was not attributable to the claimant and relied on Metro Electric Co. v. D.D.A. The court found the award justified. The court also observed that the record of proceedings on 22nd September, 1992 afforded the respondent time to rebut the claimant's revised statement, which the respondent did not use.
  • Claim No. 4 (prolongation/profit/overheads): The arbitrator reduced the prolongation period after scrutinising suspensions and shortages and explained the calculation leading to the consolidated figure awarded. The court held the arbitrator had assigned adequate reasons and that a consolidated award (as opposed to an item-by-item breakdown) was not impermissible under the agreement.
  • General point on claim-heads and consolidated awards: The court found that the arbitrator had dealt with sub-heads and explained the basis for proportionate reductions; there was no requirement in the agreement to award separate amounts against each sub-head, so the consolidated award was not vitiated on that basis.
  • Claims asserted to lack reasons (generally): The court concluded that the award was a reasoned one and that the objector's specific contentions had been addressed before the arbitrator and were not grounds for setting aside the awards.

Holding and Implications

Holding:

The objections were partly allowed. The court set aside the portion of the arbitrator's award that went into the merits of the levy of compensation and rejected the D.D.A.'s counterclaim; that portion was beyond the arbitrator's jurisdiction and therefore liable to be set aside. The remainder of the arbitrator's award (including awards on the claimants' claims which the court found to be reasoned and supported by the record) was upheld.

Immediate consequences and decree:

  • The award, as modified by the court, was made a rule of court and a decree for Rs. 3,30,412.68 was passed in favour of the claimant against the respondent.
  • Interest was directed at 13% per annum: on Rs. 1,16,670.00 from 27th September, 1991 until the date of the award; and on Rs. 3,30,412.68 from the date of the award until payment.
  • The D.D.A. was left free to pursue recovery of the compensation it claimed (the Rs. 9,408/- under clause 2) by taking such other proceedings as may be permissible in law; the arbitrator had no jurisdiction to decide that matter.

Broader implications:

The court reiterated and applied existing authorities limiting an arbitrator's jurisdiction where the subject-matter (here the quantum of levy of compensation imposed by departmental authorities) is non-arbitrable. The decision clarifies that an arbitrator cannot itself determine the merits of such non-arbitrable departmental levies and that courts will set aside any portion of an award in which an arbitrator has done so. The opinion did not purport to lay down a new legal principle beyond the application of cited precedents.

Show all summary ...

Devinder Gupta, J.— Objections by Delhi Development Authority are against the award made and published on 13th November, 1992 by Shri Shyam Narayan, the Sole Arbitrator on the disputes pertaining to the execution of the work of redevelopment scheme of Kingsway Camp (SH;Construction of SW drains at Outran Lines) awarded vide agreement No. 3.EE/CD.VLL/85-86.

2. The objections are against the rejection of D.D.A's counter claim and against the award made in claimants' favour for claim Nos. 1 to 4 and 6. Against its counter claim the objector laid a claim for Rs. 9,408/- towards compensation levied under clause 2 of the agreement on account of delay in the completion of the work.

3. The arbitrator placing reliance upon the decision of the Supreme Court in Vishwa Nath Sood v. Union of India, A.I.R 1989 S.C 962, held the quantum of levy to be non-arbitrable. The arbitrator held that the power of Superintending Engineer had been kept outside the scope of arbitration but its justification is covered by Arbitration Clause which had been referred for adjudication. Going into the merits of the counter claim the arbitrator held that the Executive Engineer/Superintending Engineer took an unbalanced view in a hurry and levied 5% compensation although delayed performance was accepted without making clear the intention t6 levy damages. D.D.A was held to have waived its right to claim compensation. Thus the counter claim was rejected.

4. Though the arbitrator was right in holding that quantum of levy of compensation, in view of the decision in Vishwanath's case (supra) was non-arbitrable but went wrong in making further observations that justification thereof is covered by arbitration clause. The arbitrator further went wrong in observing that the counter claim of the respondent is not justified and was thus wrong in rejecting the same. In view of the ratio of the decision in Vishwa Nath's case (supra), the arbitrator could not have gone into the merits of the levy of compensation. In terms of clause 2 of the agreement, in case the Delhi Development Authority considered that it was entitled to the amount towards compensation, since it was a matter outside arbitration, it could recover the said amount in accordance with law from the claimant instead of asking the arbitrator to include the said amount in his award. The findings of the arbitrator are not in consonance with the decision in Vishwa Nath's case (supra). It will be for the Delhi Development Authority to take appropriate steps for enforcing its claim, as it may be deemed fit and proper in accordance with law. The matter regarding levy of compensation or its justifiability could not have been referred for adjudication by the arbitrator and arbitrator also would not get any jurisdiction to enter into the merits or demerits of the compensation. In Delhi Development Authority v. Sudhir Bros, 1995 (32) DRJ 366, a Division Bench of this Court considered such an objection and held that arbitrator in such like situation has no jurisdiction to go into the merits of the levy of compensation by the Superintending Engineer. The award to this extent of the arbitrator, wherein he has gone into decision of the Engineer was set aside. In the instant case also the award of the arbitrator to the extent to which the arbitrator held the counter claim as not justified is liable to be set aside with liberty reserved to the Delhi Development Authority to recover the said amount of compensation from the claimant by taking recourse to such other proceedings as may be permissible in law.

5. As regards claims No. 1, 2, 4 and 6, the objections of the respondent are that the arbitrator was required to give reasons for the award. While rejecting the recovery of Rs. 9,177/- on account of extra item, the arbitrator failed to assign any reason, therefore, there is an error apparent on the face of the record in so far as claim No. 1 is concerned. Claim No. 2 was for Rs. 2,47,611/- on account of payment due under clause 10-C of the agreement. The objection is that details of the amount were filed by the claimant on the last date of hearing, namely, 22nd September, 1992 before the arbitrator and the arbitrator proceeded to make his award on that basis alone, without affording any opportunity to the objector to rebut the same. The arbitrator also failed to give any justification in awarding the amount of Rs. 35,233.68 in claimants' favour. Award under claim No. 3 for a sum of Rs. 13,092/- by way of security deposit and Rs. 86,908/- by way of bank guarantee is also challenged as without any justification or reasoning. Claim No. 4, it is alleged that the arbitrator ought to have given details of various sub heads under which he considered proper to make an award instead of making the award of a lumpsum amount of Rs. 2,13,742/-. Without indicating as to how much amount had been awarded against each of the heads and on what basis, the award is vitiated being totally erroneous and unjustified. Under claim No. 5, award of pendente lite and future interest is also challenged by the objector on the ground that the arbitrator was not empowered to grant future interest and his award suffers on account of error apparent on the face of the record.

6. The award of the arbitrator is a reasoned one and reasons have been assigned for making award against each claim. Learned counsel for the objector, during the course of arguments, dealt specifically with each claim and questioned the findings recorded by the arbitrator thereupon.

7. The scope of interference to the arbitrator's award in such like case where objections are to the effect that the same is bad on the ground of error apparent on the face of the record is limited. Arbitrator's award both on facts and law is final. Court cannot review and correct any mistake in his adjudication unless objection is to the legality of award which is apparent on the face of it. An error of law apparent on the face of the record means that you can find in the award or a document actually incorporated thereto some legal proposition which is the basis of the award, which you can then say is erroneous. It is not permissible to refer to any other document to show that the award is erroneous. Court cannot substitute its own decision for that of the arbitrator. Assessment of evidence is a matter within the province of the arbitrator.

8. Claim No. 1 was for Rs. 68,345/- on account of final bill. Claimant's case was that on 13th April, 1988, the respondent informed that final bill was ready but the amount was not paid despite several reminders. Withholding of Rs. 9.177/- as penalty and recovery of Rs. 432.90 in the final bill on account of unsanctioned extra items in excess of theoretical consumption was also objected to by the claimants on the plea that it was against the provision of clause 12 and 42 of the agreement. It was not disputed that the respondents had worked out the final bill of Rs. 70,218/- from which Rs. 9,177/- had been with-held for want of sanction of Engineer-in-Charge and Rs. 1,573/- for income tax, Rs. 432.90 for penal recovery of steel thereby leaving a balance of Rs. 59,035/-. The arbitrator on going through the respective contentions of the parties held withholding of Rs. 9,177/- for over 5 years and penal recovery as not justified saying:

“Perusal of Clause 12 of Agreement reveals that if the Engineer-in-Charge who alone has power to order extra items for which rates are to be sanctioned, in accordance with principles laid down therein. Superintending Engineers sanction may be departmental requirement, but not as per Clause 12 stipulation. Hence with-holding of Rs. 9,177/- for over 5 years after completion is not justified. Theoretical consumption of Steel is governed by Clause 42(iii) of Agreement, according to which the theoretical consumption should be based on design requirement or as authorised by Engineer-in-charge, including authorised lappages plus 5% wastage due to cutting into pieces, over which plus 5% or minus 4% shall be allowed as variation, due to wastage being more or less. Dia-wise theoretical consumption is not contemplated in this Clause, which might be required to see, if any particular dia. has been used in excess of actual issue or there has been no adequate consumption of a particular dia. as compared to quantity issued, so as to find out misuse of Steel. But the idea of allowing separate percentage for wastage and variation is to cover for wastage being more or less in a particular diameter, on account of odd sizes of requirements or issues and this is to be applied to overall quantity (and not dia-wise).”

9. There is nothing wrong in the reasonings assigned by the arbitrator. Also for the 2nd claim delay in completion was held to be not attributable to the claimant and entitlement to payment under clause 10-C was held justified in view of the decision of this Court in Metro Electric Co…. v. Delhi Development Authority AIR 1980 Delhi 266. The argument that claimant filed revised statement only on 22nd September, 1992 and no opportunity was allowed to rebut the same is not tenable in view of the proceedings recorded on that date, which allowed time to the respondent to rebut the same. It was not done. The submission of the respondent that reasons are not assigned is also factually not correct.

10. Against the fourth claim due to prolongation of contract period for Rs. 26,17,000.00, the arbitrator allowed a sum of Rs. 2,13,742.00 only, after recording findings of fact, which are based on material on record and are not challengeable. The reasons assigned are:

“Scrutinising claims on this basis, entire period of 16.64 months is to be reduced to actual period of suspension, which would hardly be 8.5 months for non-approval of Deviation and 3.3 months on account of shortage of Cement from 1.11.86 to 31.1.87 and delay in payments, as recommended by Executive Engineer. Thus the prolongation period would get reduced from 16.64 months to 11.8 months, when no work could be carried out. Balance period was needed to complete the additional work. Disallowing 15% contractor's profit on actual expenses on above overheads, the amount would get reduced to Rs. 3,05,346/- and for 11.8 months, the figure would work out to Rs. 2,13,742/-, which the Claimants had to incur, without deriving any revenue, during idle period of 11.8 months.”

11. The argument, that the claim was under five sub heads but award is consolidated one without dealing with each sub-head separately or saying that to what extent amount separately under each head is awarded, therefore, the award is vitiated; is also not tenable. Elaborate reasons have been assigned dealing with each sub-head separately. Claim under the three sub-heads was found to be maintainable, which was to the extent of Rs. 3,51,147.00 for the entire period as claimed. It was held to be justifiable only for a shorter period and thus after making proportionate reduction the amount awarded was arrived at. It is not shown that the agreement required the arbitrator to make award separately for the amounts under separate sub-heads. Award for a consolidated amount thus is not bad.

12. The objections, in view of the above, to the award made in claimant's favour are liable to be dismissed.

13. In the result objections are partly allowed. Award as modified is made a rule of court and decree in terms thereof for a sum of Rs. 3,30,412.68 is passed in favour of the claimant against the respondent with interest @ 13% p.a on Rs. 1,16,670.00 from 27th September, 1991 till the date of award and on Rs. 3,30,412.68 from the date of award till payment. Decree be drawn accordingly.