V.K Dewan & Co v. Municipal Corporation Of Delhi & Ors.

Delhi High Court
May 16, 1994
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Opinion (Usha Mehra, J.)

Factual and Procedural Background

This writ petition was filed by Mr. V.K. Dewan & Co. challenging an order of respondent No. 2, Delhi Water Supply and Sewage Disposal Undertaking (D.W.S. & S.D.), which debarred the company from further tendering with that undertaking for a period of three years. The petitioner had been awarded two construction contracts (for works at Wazirabad and Rohini) which were to commence and be completed within 12 months, but the work did not commence. The respondent cancelled the contracts and forfeited the earnest money; those actions were communicated to the petitioner by letter dated 8th November, 1993, said to be under the authority of an order dated 22nd October, 1993 of the Additional Commissioner (Water's). By a subsequent letter dated 23rd November, 1993 (also said to be under the authority of the same order dated 22nd October, 1993), the respondent communicated that the petitioner was debarred from further tendering for three years. That 23rd November letter was also circulated to other government organisations (CPWD, DDA, M.C.D., etc.). The petitioner contended that he could not commence work due to hindrances allegedly created by the respondent, that he was not given an opportunity of being heard in relation to the debarment/blacklisting, and that the respondent lacked competence under the contract or applicable rules to impose the debarment in addition to cancellation and forfeiture already effected.

Legal Issues Presented

  1. Whether, having cancelled the contract and forfeited the earnest money under the contract terms and rules, the respondent could additionally debar or ban the petitioner from further tendering (i.e., whether the respondent had competence to take that disciplinary action beyond contractual remedies).
  2. Whether the terms of the contract or the CPWD Manual of Instructions empowered the respondent to impose disciplinary measures such as debarring/blacklisting.
  3. Whether the disciplinary action (debarment for three years) was disproportionate, irrational, arbitrary or illegal in the circumstances and whether the petitioner was condemned without being afforded opportunity to be heard.
  4. Whether the respondent's circulation of the debarment communication to other government organisations amounted to blacklisting and constituted misuse of power (including lack of procedural fairness).

Arguments of the Parties

Petitioner's (Mr. Lekhi's) Arguments

  • Once the respondent exhausted remedies under the contract and rules (cancelling the contract and forfeiting earnest money), it could not resort to separate disciplinary action of debarring/blacklisting the petitioner from further tendering.
  • Neither the contract terms nor the CPWD Manual of Instructions empowered the respondent to take such disciplinary action (debarment/blacklisting).
  • The disciplinary action imposed (three-year debarment) was disproportionate to the alleged offence, and thus irrational, arbitrary and illegal.
  • The petitioner had not been allowed to commence work due to alleged hindrances created by the respondent (e.g., not providing working drawings, not permitting labourers to live at site, restrictions on working hours), and the respondent had not fairly considered the petitioner’s communications complaining of these grievances.
  • The circulation of the debarment letter to other government organisations indicated an intent to tarnish the petitioner’s reputation beyond the respondent undertaking, amounting to blacklisting without notice and opportunity.

Respondent's (as represented through arguments noted in the opinion) Contentions

  • The respondent relied on the CPWD Manual of Instructions and an Annexure (R-3) and certain Government (G.I.) decisions attached to R-3 to justify disciplinary measures, including blacklisting/suspension/banning in appropriate cases.
  • There was a suggestion (by the respondent or its counsel) that show cause proceedings had been conducted (the court notes a contention that a show cause notice was served, but distinguishes that the notice related to the penalty of debarring and not to blacklisting).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ranjit Thakur v. Union of India & ors., AIR 1987 SC 2386 The doctrine that the choice and quantum of punishment must suit the offence and the offender; punishment should not be vindictive or unduly harsh; it should not be so disproportionate as to "shock the conscience" and indicate bias. Irrationality and perversity are recognised grounds for judicial review; the doctrine of proportionality is part of judicial review. The court applied this principle to conclude that the respondent’s imposition of debarment (and the manner of its publicity) was disproportionate, arbitrary and vindictive in the circumstances of the case; consequently the impugned order was quashed.

Court's Reasoning and Analysis

The court proceeded by examining the contract terms and the materials relied upon by the respondent to justify the debarment. The court set out the relevant contractual provisions:

  • Clause 20 (general conditions of the tender document): After acceptance of the tender, the tenderer must sign the contract agreement within 10 days (the document as reproduced refers to 10 days; elsewhere the parties referred to 15 days). In case of delay, the Engineer-in-charge reserves the right to forfeit the earnest money without legal notice.
  • Clause 2: Provides compensation for delay and permits charging a percentage of the estimated cost where work remains uncommenced.
  • Clause 3: Empowers the Corporation to rescind the contract for breach by the contractor.
  • Clause 21: Allows rescission and forfeiture of security deposit for specified misconduct (sub-letting, bribing, insolvency, etc.), and contains consequences for such rescission; the contractor shall not assign or sublet without written approval.
  • Clause 25: Provides for arbitration in case of dispute.

The court observed that by order dated 13th August, 1991 the respondent had conveyed a decision to adopt the CPWD Manual of Instructions and CPWD General Terms and Conditions insofar as they did not differ from the respondent's rules. However, the court found that the CPWD Manual (and specifically Annexure R-3 relied on by the respondent) did not form part of the contract or the contractual terms between the parties and did not provide a disciplinary procedure applicable in the facts of this case. The court characterized Annexure R-3 as an office note or a suggestion at best, not a contractual term.

The court contrasted the remedies available under the contract (forfeiture of earnest money, rescission, forfeiture of security deposit in specified circumstances) with the disciplinary consequences described in Annexure R-3 (blacklisting/banning/suspension). The court noted that for an act like bribery the contract prescribes rescission and forfeiture of security deposit, whereas Annexure R-3 would lead to blacklisting — demonstrating that R-3 was not aligned with the contract terms and therefore was not relevant here.

The court also found that the government/instructional decisions annexed to R-3 were not part of the CPWD Manual or contract terms and did not authorize the respondent to take the stern action of debarment in this case. The court observed that government guidance indicated forfeiture of earnest money where the contractor fails to commence work and that disciplinary action was not automatic in every such case but had to depend on circumstances. The respondent did not set out the specific circumstances that would justify discipline over and above the contractual remedies already invoked.

The court further emphasized procedural fairness: the petitioner had not been condemned without opportunity to be heard. While the court recognized that disputes about non-commencement and reasons therefor could be referred to arbitration under Clause 25, the particular step of debarment and the publicity given to it amounted to misuse of power. The court noted that the 23rd November, 1993 communication was circulated to other government organisations, thereby publicising the debarment and effectively blacklisting the petitioner without a show cause notice specifically addressing blacklisting. The court held that the punishment of debarring the petitioner for three years was disproportionate to the offence alleged and inconsistent with the contractual remedies already applied.

Applying the doctrine of proportionality (as explained in Ranjit Thakur), the court concluded that the respondent's action was arbitrary, vindictive and biased, and that the facts and circumstances did not warrant such severe action when the action did not stem from the terms and conditions of the contract.

Holding and Implications

Holding: The impugned order debarring the petitioner from further tendering with respondent No. 2 for a period of three years is hereby QUASHED; the rule is made absolute. Parties are directed to bear their own costs.

Implications:

  • Direct effect on the parties: The three-year debarment imposed by respondent No. 2 is set aside; the petitioner is no longer subject to that debarment under the impugned order. The parties must bear their own costs.
  • Scope and precedent: The court relied on the established doctrine of proportionality (as stated in Ranjit Thakur) to conclude the action was disproportionate and therefore amenable to judicial review. The opinion does not purport to lay down a new legal principle or depart from binding precedent; it applies existing principles of contractual interpretation and judicial review to the facts before it.
Show all summary ...

Usha Mehra, J.— Mr. V.K Dewan & Co. by this writ petition has assailed the order of respondent No. 2, Delhi Water Supply and Sewage Disposal Undertaking, (in short the D.W.S & S.D) thereby debarring the company for further tendering in the said undertaking for a period of three years.

2. Mr. Lekhi's challenge to the impugned order dated 23rd November, 1993, is on three counts firstly the respondent having exhausted the remedy under the terms of the contract and the rules, i.e by cancelling the contract and by forfeiting the earnest money, could not resort to disciplinary action of debarring or banning the petitioner from further tendering. This amounted to blacklisting the petitioner which is not within the competence of the respondent. Secondly, neither the terms of the contract nor the rules, indicated in CPWD Mannual of Instruction empower the respondent to take such disciplinary action. Disciplinary action adopted by the respondent is dis-proportionate to the offence alleged, therefore, irrationale, arbitrary and illegal.

3. It is an admitted case of the parties that the petitioner is in the business of constrution work in the State of Delhi and the respondent No. 2 executes constrction work in the State of Delhi through contractors. The petitioner was awarded the con tract for two works at Wazirabad and Rohini. These works were to commence and were to be completed within 12 months. The work did not commence. According to the petitioner he could not commence work because of the insurmountable hindrances created by the respondent. His case is that after the tender was accepted, requisite documents were submitted by him, but the respondent instead of acknowledging the same kept on asking for those very documents and in order to harm the petitioner, the work awarded to him was cancelled and earnest money forfeited. It is also a fact on record that vide letter dated 8th November, 1983 only action communicated to the petitioner was cancellation of the contract and forfeiture of the earnest money under the authority of the Additional Commissioner (Water's) order dated 22nd October, 1993. It is on 23rd november, 1993 by the impugned letter action to debar him for further tendering for three years was communicated under the authority of the same Additional Commissioner (Water's) order dated 22nd october, 1993. It is also a fact on record that this letter dated 23rd November, 1993 was issued to various other Departments dealing with execution of construction work through contractors in Delhi namely, C.P.W.D, D.D.A and M.C.D etc. if it had been a simple ban imposed on the petitioner debarring him from tendering only with respondent No. 2 Undertaking then what prompted the respondent to send this communication to other Govt. Organisations which had nothing to do with this work or of the contract of the petitioner with respondent No. 2. For this action of the respondent, an inference should be drawn that the respondent authority wanted other organisations to know that petitioner company was not worthy of awarding work. This action, according to Mr. Lekhi, amounts to projecting the petitioner bad in the eye of other organisations and thus depriving him work from other authorities. Hence it cannot be said that the action of the respondent against the petitioner was meant only for this undertaking. By circulating it and by giving it due publicity, it amounted to blacklisting the petitioner. The order may have been couched in such a language that it may not appear apparently blacklisting the petitioner, but by its conduct i.e by circulating the said order and by giving due publicity to other departments with which petitioner company, being a contractor, could have a dealing or may have to work, amounts to blacklisting. Even otherwise how far respondent can be justified in invoking this extreme step. Admittedly, petitioner had not commenced the work nor signed the agreement on a non-judicial stamp paper within 15 days of the accceptance of the tender. As per the terms of the contract for such failure respondent is vested with power to forfeit earnest money and cancel the work. Petitioner has his own story to tell for not commencing the work and for non signing. He blames the respondent authority for creating hurdles by not providing him working drawings and depriving him the right to have the labourers live at the site and by not permitting him to work on Sundays and holidays and normal working hours. Be that as it may, the fact remains in view of this disputed questions can the respondent on its unilateral finding condemn the petitioner without affording him opportunity. The answer will be in the negative. No one can be condemned unheard. But even to condemn him, the respondent must be competent under the terms of the contrct or the rules to do so. The special and general terms and conditions of the contract do not empower the respondent to take such disciplinary action over and above cancelling the contract and forfeiting earnest money.

4. Clause 20 of the general conditions of the tender document empowers the respondent to forfeit the earnest money if the tenderer after the acceptance of the tender fails to sign the contract agreement. Clause 20 is reproduced as under:

“Clause 20—After the acceptance of the tender, the tenderer will have to sign the necessary contract agreement within 10 days of the above intimation. In case of delay, the Engineer-in-charge reserves the right to forfeit the earnest money without any legal notice.”

5. Clause 2 of the conditions of contract provides compensation for delay. It postulates that the contractor shall proceed with the work with all due diligence. The Corporation has been given the power to charge one per cent, or such smaller amount of the estimated cost of the work for every day that the work remains uncommenced. And under Clause 3, the Corportion has been empowered to rescind the contrract for the breach committed by the contractor. Under Clause 21 of the conditions of Contract the contract can be rescinded and security deposit forfeited for sub letting, bribing or if the contracotr becomes insolvent. The said Clause is reproduced as under:—

Clause 21: WORK NOT TO BE SUBLET

CONTRACT MAY BE RESCINDED AND SECURITY DEPOSIT FORFEITED FOR SUB LETTING, BRIBING OR IF CONTRACTOR BECOMES INSOLVENT.

The contractor shall not assign or sub let without the written approval of the Municipal Engineer. And if the contractor shall assign or sub let this contract or attempt to do so or become insolvent, or commence any insolvency proceedings, or make any composition with his creditors or attempt to do so, or if any bribe gratuity, gift, loan, perquisite, reward or advantage, pecuniry or otherwise, shall either directly or indirectly be given promised, or offerred by the contractor, or any of his servants or agents to any public officer or person in the employ of the Coprporation in any way relating to his office or employment, or if any such officer or person shall become in any way directly or indirectly interested in the contract the Municipal Engineer may thereupon by notice in writing rescind the contract and the security deposit of the contractor shall thereupon stand forfeited and be absolutely at the disposal of the Corporation and the same consequences shall ensure as if the contract had been rescinded under Clause 3 hereof, and in addition the contractor shall not be entitled to recover or be paid for any work there before actually performed under the contract.

And in case of dispute parties can invoke arbitration Clause No. 25 provided in the contract. It is not disputed that vide order dated 13th August, 1991 respondent issued instrution order thereby conveying its decision to adopt CPWD Mannual of Instructions and CPWD General Terms and Conditions, applicability of the same, so far as it did not differ with the rules of the respondent, was made known to all concerned. The reading of CPWD Mannual of Instructions does not help the case set up by the respondent. It does not provide any disciplinary procedure as urged by the respondent. Mr. Sapra's, placing reliance on this document is misplaced. It is not a term of the contract. This can be inferred from the following sentence used in this note.

4. POST TENDER ENQUIRY REVISION OF SLAB RATES:

(i) it has been noted that there is need to curb undesirable practices of tenderers to withdraw lower slab rates after tender opening. Suitable administrative action should also be taken in such cases.

The fact of and the reasons for suspension of business shall not be communicated to the firm concerned.

Orders regarding “Black-listing”, “Suspension of Business” or “Banning” are confidential and are not to be communicated to the firms or to other.

Normally, orders of “Black-listing” and “Banning” do not afffect current contracts pending execution by firm black-listed/banned. In the case of firms who have been punished on grounds of bribery, the discretion to cancel current contract is reserved under Clause 22 of the General Conditions of Contract.

It has also been expressed in this note that the punishment of “Black-listing”, “Banning” and “Suspension of Business” is more severe than removal as the firm so dealt with will not be eligible to do business with Government.

6. Reading of this Annexure R-3 relied by Mr. Sapra shows that it is neither a part of the terms and conditions of the contract nor of the CPWD Mannual of Instructions. It is an office note or at best suggestion submitted by some official. This was not part of the contract nor applicable to the facts of this case.

7. The non applicability of the disciplinary procedure as prescribed and mentioned in Annexure R-3 can be seen by reading Clause 21 of the contract as reproduced above. For the act of bribery under the condition of contract the offence is rescinding of contract and forfeiture of the security. Whereas under Annexure R-3 it will lead to blacklisting. This shows that this Annexure R-3 has no relevance with the terms and conditions of the contract in question.

8. Mr. Sapra's reliance on some G.1's decision annexed with Annexure R-3 by no strech of imagination can be called part of CPWD Mannual of Instructions or terms and conditions of the Contract. Nor it empowers or authorises the respondent to take such stern action. In fact, Government's decision is that in case the contractor fails to commence the work, recourse to forfeit his earnest money be taken and that action under Clauses 2 and 3 of the Contract need not be taken. Disciplinary action could be taken wherever the circumtances so warrant. Therefore, it cannot be said disciplinary action is automatic in all cases of non commencing the work. What were those circumstances which prompted the respondent to take this disciplinary action over and above cancellation of contract and forfeiture of earnest money have not been stated. There are empteen number of letters witten by the petitioner ventilating his grievances but without considering the same the extreme step has been taken. To my mind, the facts and circumstances of this case did not warrant the respondent such severe action, particularly when it has not stem out of the terms and conditions of this contract.

9. The grievance of the respondent that petitioner inspite of repeated reminders, and even after the show cause notice did not commence the work nor signed the agreement, to my mind, is a dispute which can be resorted by invoking clause 25 of the Agreement. Petitioner has tried to justify his action but this is not the proper forum to go into the disputed question of facts. However, this Court cannot over look the fact that the impugned order of 23rd November, 1993 was given due publicity by the respondent with ulterior motives. This is a misuse of the power of the respondent because of the publicity given to the order of debarring him from tendering in future. It amounts to black-listing for which no show cause notice has been served. As observed, the contention of Mr. Sapra that show cause notice was served is without force, because that was only for the penalty of debarring and not for black-listing. Even otherwise, this punishment is dis-proportionate to the offence alleged against the petitioner. For three years he will be in hypernation even though for other contracts his case may be meritorious. In the words of M.N Venkatachaliah, J. (as his Lordship then was) in the case of Ranjit Thakur v. Union of India & ors., AIR 1987 SC 2386, “the question of the choice and quantum of punishment is within the jurisdiction and discretion of the Court Martial. But the sentence has to suit the offence and the offender. It should not be vindictive or unduly harsh. It should not be so dis-proportionate to the offence as to shock the conscience and amount in itself to conclusive evidence of bias. The doctrine of proportionality, as part of the concept of judicial review, would ensure that even on ah aspect which is, otherwise, within the exclusive province of the Court Martial, if the decision of the Court even as to sentence is an outragious defiance of logic, then the sentence would not be immune from correction. Irrationality and perversity are recognised grounds for judicial review.”

10. Observation of the Hon'ble Supreme Court, quoted above, aptly apply to the facts of this case. The action of the respondent being not arising out of the terms and conditions of the Contract or the CPWD Mannual of Instructions applicable to the facts of this case, therefore, can be called arbitrary, vindictive and bias. Even otherwise it appears to be disproportionate to the offence alleged particularly when action under the contract and the rules has already been taken by the respondents.

11. For the reasons stated above, the impugned order thereby debarring the petitioner from further tendering with respondent No. 2 for a period of three years is hereby quashed. The rule is made absolute. Parties are left to bear their own costs.