Union Of India v. Siri Ram & Anr.

Delhi High Court
Nov 11, 1982
Smart Summary (Beta)

Structured Summary of the Opinion by D.R. Khanna, J.

Factual and Procedural Background

These three cases concern two arbitral awards made by Miss K.P. Sarojini on 3-5-1979 arising from disputes under Agreement No. 4.EE/74 for the construction of residential accommodation (32 type I quarters, phase II) at Hauz Khas. The disputes were referred to arbitration at different stages, which necessitated two separate awards.

The contract's stipulated completion date was 15-5-1974, but extensions were granted intermittently and the work was ultimately completed by 10-9-1975. Clause 2 of the contract empowered the Engineer Incharge to levy compensation (liquidated damages) for delayed execution up to a maximum of 10% of the contract amount. Exercising that power, the Superintending Engineer levied compensation of Rs. 20,130/-, which was withheld from the contractor's bills and placed in a suspense account roughly three years after completion.

The Union of India filed objections to the arbitral awards. The objections pressed at the hearing related principally to (1) the non-allowance by the Arbitrator of the Union's claim for Rs. 19,727.96 (an amount deducted from the contractor's bills for delayed execution), and (2) the Arbitrator's award of interest at 6% per annum on the amounts allowed to the contractor. The Arbitrator's proceedings of 29-12-1978 are specifically noted in the opinion, including a question from the Arbitrator to the Executive Engineer about whether any "promissional letter of extension" had been issued subject to the right to levy liquidated damages; the Executive Engineer answered in the negative.

Legal Issues Presented

  1. Whether the Arbitrator erred in not allowing the Union of India's claim of Rs. 19,727.96 deducted for delayed execution (i.e., whether the levy of compensation under clause 2 should have been sustained).
  2. Whether the Arbitrator was justified in awarding interest at the rate of 6% per annum on the amount allowed to the contractor, given that the claim for interest had been specifically referred to arbitration.
  3. Whether the awards suffer from a patent error of law apparent on the face of the award or whether the Arbitrator committed judicial misconduct by failing to give effect to clause 2 of the contract.

Arguments of the Parties

Union of India (Objector)

  • Contended that the Arbitrator wrongly disallowed the department's deduction of Rs. 19,727.96 for delayed execution and thereby failed to give effect to clause 2 of the contract which expressly permitted the levy of compensation up to 10% of the contract amount.
  • Argued that the Arbitrator's failure to sustain the levy amounted to an apparent error of law and judicial misconduct.
  • Pointed out that clause 2 itself constituted sufficient notice that compensation could be levied, in response to the Arbitrator's inquiry about any promissional letter subjecting extensions to liquidated damages.

Contractor

  • Relied on proceedings before the Arbitrator (29-12-1978) showing that the Executive Engineer denied issuing any "promissional letter of extension" making acceptance subject to the right to levy liquidated damages; from this the contractor argued the department did not give the requisite notice under Section 55 of the Contract Act when accepting performance after the stipulated time.
  • Asserted that there were delays attributable to the department — delays in providing designs, drawings and material — which hindered progress and caused labour to be idle; the contractor sought compensation or relief on that ground and argued those circumstances were before the Arbitrator.
  • Challenged the amount withheld and the timing of the levy (noting compensation was levied almost three years after completion and the sum remained in a suspense account).

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court framed its review within the established limited scope for interference with arbitral awards. It emphasized that when entertaining objections to an award the Court must not act as an appellate authority re‑deciding the merits; rather it must confine itself to determining whether there is a mistake of law apparent on the face of the award that would warrant setting the award aside or remitting it.

The Court reiterated the following principles (as stated in the opinion):

  • The Arbitrator is the judge of facts and law and is entitled to form his own assessment of the evidence and to interpret contract terms.
  • If a conclusion of the Arbitrator is not perverse, is supported by some evidence, and is not arrived at by ignoring material evidence, the award should stand.
  • If the matter is one on which two reasonable opinions can be formed, the Court should not interfere simply because it might have reached a different conclusion on first instance.

Applying these principles, the Court reviewed the recorded circumstances: the Arbitrator's inquiry about any promissional letter and the Executive Engineer's negative response; the contractor's assertions of departmental delays in designs, drawings and material; and the timing of the levy and retention in a suspense account. The Court noted that the Arbitrator's observations about Section 55 of the Contract Act were "not happily worded" but considered the substance of the Arbitrator's approach.

On the point of interest, the Court observed that the claim for interest had been specifically referred to arbitration, and therefore the Arbitrator was competent to adjudicate that claim.

In sum, the Court concluded that the awards did not exhibit an apparent error of law or such a perverse conclusion as to justify interference: there was reason to presume the Arbitrator took into account all contentions and evidence and reached conclusions that were open to him on the record.

Holding and Implications

Final Holding: The Court rejected the Union of India's objections to the arbitral awards, made the awards rules of the Court, and passed decrees in accordance with those awards.

Implications:

  • Direct effect on the parties: The arbitral awards, including the Arbitrator's decisions on the disallowance of the department's claimed deduction and on the award of interest at 6% per annum, are confirmed and have been converted into court decrees.
  • No broader legal precedent or new legal principle was established by this opinion; the Court applied settled principles governing the limited scope of judicial review of arbitration awards and declined to disturb the Arbitrator's conclusions on the facts and law presented to him.

Note: This summary reflects only the matters and reasoning expressly contained in the provided opinion. No external facts, precedents, or inferences beyond the text have been added.

Show all summary ...

D.R Khanna, J.:— These three cases relate to two awards delivered by Miss K.P Sarojini, Arbitrator, of the date 3-5-1979 on disputes and differences inter se parties arising under agreement No. 4.EE/74. The contract was for construction of residential accommodation at Hauz Khas of 32 type I quarters phase II. The necessity for giving two awards arose as the disputes were referred to arbitration at different stages.

2. Objections have been filed to the awards by the Union of India, and those agitated at the time of arguments, relate to the non-allowance of its claim of Rs. 19,727.96 p. which had been deducted by the Union of India from the bills of the contractor for delayed execution of the work, and the awarding of interest at the rate of 6% per annum on the amount allowed to the contractor.

3. There is no dispute that the stipulated date for the completion of work was 15-5-1974. However, extensions were granted from time to time, and ultimately they were upto 10-9-1975 by which time the work was completed. Clause 2 of the contract permitted the Engineer Incharge to levy compensation for delayed execution of the contract at different stages, and the maximum that was leviable was 10% of the contract amount. The Superintending Engineer, therefore, in exercise of power available under this clause levied a compensation of Rs. 20,130/- on the contractor which was payable to the department.

4. The award while dealing with this controversy, makes certain observations which are not happily worded. There is mention of non-compliance of the mandatory requirements of Section 55 of the Contract Act. That Section enjoins that in case of a contract voidable on account of the promisor's failure to perform his promise at the time agreed, the promisee accepts performance of such promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of such acceptance, he gives notice to the promisor of his intention to do so.

5. The contractor has, in this regard, led me through the proceedings which took place before the learned Arbitrator on 29-12-1978, wherein the Arbitrator had specifically required the Executive Engineer to answer if any promissional letter of extension was issued subject to the right to levy liquidated damages during the progress of work. The reply of the Executive Engineer was in negative. From this circumstance, it appears that the Arbitrator deduced that while accepting completion of the work from the contractor after stipulated period, the Union of India did not intimate that this was subject to the intention to levy compensation. The Union of India, however, has pointed out that clause 2 of the contract itself stipulated the levy of compensation and that was by itself enough notices.

6. The contractor has also referred to a number of circumstances laid from his side before the Arbitrator to the effect that there were delays in the providing of designs, drawings and material by the department at different stages with the result that his labour had to remain idle, and the progress of the work was hindered. Compensation on this ground was claimed. The learned Arbitrator, however, has not referred to any such assertions. It is, however, pleaded that they should be presumed to have been taken into account while disallowing compensation to the Union of India.

7. The compensation was levied by the Superintending Engineer almost three years after the completion of the contract, and the amount withheld was lying in suspense account.

8. The question to be considered is whether in the totality of these circumstances, the decision of the Arbitrator can be said to suffer from a patent error of law. The Union of India has pleaded that it does, and the Arbitrator has committed judicial misconducted in not giving effect to clause 2 of the contract.

9. It is now Well settled that while entertaining objections to an award, the Court has not to assume itself the role of an appellate authority, or embark upon reviewing the decision on merits. It has to confine itself whether the award suffers from any mistake of law apparent on the face of the award, and on that score the award is liable to be set aside or remitted back. If, however, the matter is capable of two opinions, and the Court considers that the decision arrived at by the Arbitrator though possible was not such that it would have itself arrived at if the matter had come before it for the first time, there will be no justification to interfere. The Arbitrator being the judge of both facts and law, has to form his own assessment of the evidence placed before him. It is also for him to interpret the different terms of the contract. If it is found that he has come to a conclusion, which is not perverse or wholly unwarranted, and is based upon some evidence on record, and is further not arrived at by ignoring other material evidence on record, the award should be allowed to stand.

10. Looked at from these aspects, it cannot be said that the awards in the present cases are such which the Court should interfere or hold that they suffer from an apparent error of law. After all the contractor had also made allegations of delays on the part of the department in furnishing designs, drawings and material. Whether they were correct or not, was for the Arbitrator to determine. There is every reason to presume that the Arbitrator took into account all the contentions and the respective cases of the parties while giving his award.

11. Adverting to the other objections relating to the awarding of interest at the rate of 6% per annum, it is note worthy that the claim about interest was specifically referred to arbitration. The Arbitrator was, therefore, competent to adjudicate upon the same.

12. Considering all these circumstances, I am constrained to reject the objections to the awards and make them rules of the Court. Decrees in terms thereof are passed.