New Delhi Municipal Committee v. M/S. Tirath Ram Ahuja (P.) Ltd. And Another
Structured Summary of the Provided Opinion
Factual and Procedural Background
The present petition was filed under Section 20 of the Arbitration Act by the New Delhi Municipal Committee (the "Committee") seeking appointment of an arbitrator in accordance with the arbitration agreement with M/s. Tirath Ram Ahuja (P.) Ltd. (the "contractor"). The parties had entered a written contract for construction of a five-star hotel (Akbar Hotel) at Chanakyapuri, New Delhi. Construction was to start on 30 November 1966 and complete by 28 February 1969; the contractor deposited Rs. 1,00,000 as security and the work was supervised by an architect named in the agreement.
The architect issued a final certificate on 18 October 1970 certifying that a net payment of Rs. 18,001 was due to the contractor. The contractor was dissatisfied, sought appointment of an arbitrator, and an arbitrator's award was made on 9 August 1974 and filed in court on 22 October 1974.
Separately, the Chief Technical Examiner, Central Vigilance Commission (CTE) conducted a technical examination of the works; the Committee received the CTE report (allegedly in May 1972) pointing out defects. On 5 August 1974 the Committee claimed refund of certain amounts paid; the contractor repudiated the claims on 14 August 1974. The Committee sought reference to arbitration on 12 September 1974 but the contractor refused on 18 September 1974. The Committee then filed the instant petition on 23 April 1975 under Section 20 of the Arbitration Act. The contractor contested, alleging (inter alia) that no referable disputes remained and that the petition was barred by limitation for not being filed within 28 days of the architect's final certificate.
On 30 August 1978 the court framed the following issues:
- Whether the suit is barred by limitation? If so, its effect?
- Whether the disputes are not referable to arbitration as alleged by the defendants?
- Relief.
Legal Issues Presented
- Whether the petition under Section 20 of the Arbitration Act was barred by limitation (including the effect of a contractual 28-day limitation provision after the architect's final certificate and the applicability of Section 28 of the Indian Contract Act)?
- Whether disputes remained referable to arbitration (i.e., whether there were referable disputes after the contractor-initiated arbitration)?
- What relief should follow from the findings on limitation and referability?
Arguments of the Parties
Committee's Arguments
- The Committee contended that the 28-day stipulation in the arbitration clause was void under Section 28 of the Indian Contract Act, which, it was argued, invalidates any agreement that limits the time within which a party may enforce his rights.
- The Committee asserted that disputes regarding refund (arising from the CTE report) had arisen and therefore the matter should be referred to arbitration.
Contractor's Arguments
- The contractor argued that the right to refer disputes to arbitration subsisted only for 28 days after issuance of the architect's final certificate (18 October 1970) and that the Committee's application (filed 23 April 1975) was therefore barred by that contractual time-limit.
- The contractor also contended that there were no referable disputes left when the earlier arbitration (initiated by the contractor) had settled the matter.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Pearl Insurance Co. v. Atma Ram (Full Bench, Punjab High Court), AIR 1960 Punj 236 | Distinction that a contractual clause which limits the period during which the contract itself remains operative (i.e., the very existence of the right) is not the same as a clause which limits the time for enforcing a right; Section 28 of the Indian Contract Act does not invalidate the former. | The court relied on this decision to support the proposition that the contractual 28‑day period operated to limit the existence of the right to refer to arbitration (i.e., the right ceased after 28 days) and so was not void under Section 28 of the Contract Act. |
| Union of India v. Rishi Raj Co., AIR 1973 Delhi 15 | Held that parties can prescribe a period of limitation by mutual consent for arbitration-related demands; such restriction is not opposed to public policy and is not void (following Pearl Insurance). | The court cited and followed the observations in this case to reinforce that a contractual restriction on the period to demand arbitration may be binding and valid. |
| Kerala State Electricity Board v. T.P. Kunhaliumma, AIR 1977 SC 282 | Held that Article 137 (residuary article prescribing three years) of the Limitation Act, 1963 applies to applications under any law and is not confined to applications under the Code of Civil Procedure. | The court applied this precedent to conclude that Article 137 of the Limitation Act governs limitation for petitions under Section 20 of the Arbitration Act, providing a residuary period of three years from accrual of the right to apply. |
Court's Reasoning and Analysis
The court conducted a step-by-step analysis focused primarily on (a) the effect of the contractual 28-day limitation clause in arbitration clause No. 47, and (b) the applicable statute of limitation for the Section 20 petition.
1. Interpretation of the arbitration clause: The court reproduced the arbitration clause which stated that disputes must be referred "not later than twenty eight days after the Architect has issued the final certificate as provided in cl.38 of this agreement." The contractor's contention was that the Committee lost the right to refer after 28 days from the architect's final certificate (18 October 1970).
2. Section 28 Indian Contract Act: The Committee argued that the 28-day limitation offended Section 28, which voids agreements that limit the time within which a party may enforce rights. The court distinguished between (i) a provision that limits the time to enforce a right (caught by Section 28) and (ii) a provision that limits the very existence of the right (a condition that the right itself will cease to exist after a stated period). The court held that the present clause fell within the latter category — it limited the duration for which the right to refer to arbitration subsisted rather than merely imposing a procedural limitation on enforcing an existing right.
3. Reliance on precedent: The court relied on the Full Bench decision in Pearl Insurance Co. v. Atma Ram and a subsequent single-Bench decision in Union of India v. Rishi Raj Co. to support the distinction and to hold that contractual restrictions prescribing a period within which arbitration demands must be made are not void under Section 28.
4. Consequence for the present petition: Because the architect's final certificate was issued on 18 October 1970, the court calculated that the contractual 28-day period for filing an application under Section 20 ran until 15 November 1970. The Committee's Section 20 application filed on 23 April 1975 was therefore "hopelessly barred" by the contractual limitation.
5. Statutory limitation (Article 137): The court further analyzed limitation under the Limitation Act. Noting uncertainty in earlier authority, it applied the Supreme Court decision in Kerala State Electricity Board v. T.P. Kunhaliumma to treat Article 137 (residuary three-year period) as applicable to petitions under Section 20. The court observed that the right to apply under Section 20 accrued when the payment (whose refund the Committee sought) was made. The petition did not specify payment dates; the Committee therefore failed to show timely filing. Even if the court assumed payment occurred in 1971, the three-year residuary limitation would have expired in 1974, prior to filing in 1975.
6. Issue of referability (Issue No. 2): The contractor argued no referable disputes remained because the contractor had earlier initiated arbitration. The court found that the Committee subsequently discovered alleged excess payments (per the CTE report) and that the contractor repudiated the refund claims; this created a dispute referable to arbitration. Thus Issue No. 2 was decided in favour of the Committee on the merits of referability.
7. Final synthesis: Despite finding that the disputes were referable, the court concluded that the Section 20 petition had to be dismissed because it was barred by the applicable contractual and statutory limitation.
Holding and Implications
Holding: The court dismissed the petition filed by the New Delhi Municipal Committee under Section 20 of the Arbitration Act as time-barred and ordered that the parties bear their own costs. (Order in the text: "Petition dismissed.")
Implications:
- The direct effect is that the Committee's application for appointment of an arbitrator under Section 20 was denied for being filed after the expiry of the contractual 28-day period and past the residuary three-year limitation under Article 137 (as applied to Section 20 petitions by the cited Supreme Court authority).
- The court recognized that disputes existed and were referable to arbitration, but due to the limitation bar the Section 20 remedy was not available to the Committee in this petition.
- The opinion does not announce or discuss the creation of any new legal precedent; it applies existing statutory provisions and precedents to the facts before it. (No broader or novel legal principle was declared beyond the application described above.)
Petition dismissed.
Note: This summary is drawn exclusively from the text of the provided opinion. Where the opinion did not address broader implications or certain factual details (for example, the precise dates of the payments whose refund is sought), those specifics are not included here because they were not present in the source text.
The present petition is under Section 20 of the Arbitration Act for appointment of an arbitrator in accordance with agreement between New Delhi Municipal Committee (hereinafter referred to as Committee) and M/s. Tirath Ram Ahuja (P.) Ltd., (hereinafter referred to as the contractors).
2. A contract was entered into between the Committee and the contractor for construction of a Five Star Hotel now named as Akbar Hotel at Chanakyapuri, New Delhi. That contract was reduced into writing. Vide that agreement, the construction was to be started by 30th November 1966 and was to be completed by 28th February 1969. A sum of Rs. 1,00,000 was deposited as security by the contractor with the Committee. The construction was to be made by the contractor under the supervision of an architect named in the agreement. Architect issued a final certificate on 18th October 1970 certifying that net payment of Rs. 18,001 was due to the contractor. The contractor felt dissatisfied and requested for appointment of an arbitrator. Accordingly an arbitrator was appointed and award was made on 9th August 1974. That was filed in court on 22nd October 1974.
3. In the meantime Government of India directed technical examination of the works undertaken by the committee. Accordingly the work of construction of aforesaid hotel was also subjected to technical examination by Government organization named as Chief Technical Examiner Central Vigilance Commission. (hereinafter referred to as CTE).
4. It is alleged by the Committee that the report of CTE on the technical examination of the various projects including the work in question was received during May 1972 and that certain defects regarding present work were pointed out in the said report. The Committee on the basis of the said report made claims regarding refund of some of the amounts already paid by means of a letter dated 5th August 1974. The contractor repudiated those claims vide letter dated 14th August 1974. Since disputes and differences arose between the Committee and the Contractor, the former wrote on 12th September 1974 to the latter for referring the disputes to the arbitration but the latter refused to accede to the request of the former by means of a letter dated 18th September 1974. Hence the present petition was brought by the Committee on 23rd April 1975.
5. The contractor contested. He denied that there were any referable disputes left when the matter already stood nettled by means of referring the disputes to the arbitrator at his instance. It was also contended that the present application was barred by limitation inasmuch as the same should have been brought within 28 days of the issuance of the final certificate on 18th October 1970, of the architect but the same was brought after about five years of expiry of limitation. Following issues were framed on August 30, 1978 :—
1. Whether the suit is barred by limitation ? If so, its effect ? OPD
2. Whether the disputes are not referable to arbitration as alleged by the defendants ? OPD
3. Relief.
Issue No. 1.
6. Some portion of the arbitration clause is relevant for the purpose of deciding this issue because it is urged by the learned counsel for the contractor that right to refer the disputes and differences to the arbitration subsisted only for 28 days after the architect had issued final certificate as provided in cl.38 of the Agreement of carrying out the work, that admittedly final certificate by the architect had been issued on 18th October 1970 and that there was no right of the committee to refer the dispute, to the arbitrator sites the expiry of 2S days from 18th October 1970. Relevant portion of arbitration clause No. 47 of the agreement reads as under :—
“All disputes and differences of any kind whatever arising out of or in connection with the contract or the carrying out of the works whether during the progress of the work or after their completion and whether before or after the determination, abandonment or breach of the contract but not later than twenty eight days after the Architect has issued the final certificate as provided in cl.38 of this agreement shall be referred to and settled by Mr. Shivnath Prasad who shall state his decision in writing. Such decision may be in the form of final certificate or otherwise. The decision of the Architect with respect to any of the excepted matters shall be final and without appeal as stated in the preceding clause. But if either the Employer or the Contractor be dissatisfied with the decision of the Architect on any matter, question or dispute of any kind (except any of the excepted matter) or as to the withholding by the Architect of any certificate to which the contractor may claim to be entitled, then and in any such case either party (the employer or the contractor) may within twenty eight days after receiving notice of such decision give a written notice to the party through the Architect requiring that such written notice has been given and no other such (sic) shall be and is hereby referred to the arbitration and final decision of a single Arbitrator being a Fellow of the Indian institute of Architects to be agreed upon and appointed by both the pasties or in case of disagreement as to the appointment of a single arbitrator, to the arbitration of two arbitrators both being Fellow of the Indian Institute of Architects, one to be appointed by each party, which Arbitrators shall before taking upon themselves the burden of reference appoint an Umpire.”
6-A. The learned counsel for the committee contended that the aforesaid stipulation of limitation of 28 days was void in view of Section 28 of the Indian Contract Act. Section 28 of the Indian Contract Act reads as under :—
“Every agreement, by which any party thereto is restricted absolutely from enforcing his rights under or in respect of any contract by the usual legal proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights is void to that extent.
Exception 1.— This Section shall not render illegal a contract, by which two or more persons agree that any dispute which may arise between them in respect of any subject or class of subjects shall be referred to arbitration and that only the amount awarded in such arbitration shall be recoverable in respect of the dispute so referred.
Exception 2.— Nor shall this Section render illegal any contract in writing by which two or more persons agree to refer to arbitration any question between them which has already arisen or affect any provision of law in force for the time being as to reference to arbitration.”
The learned counsel pointed out that Section 28 invalidated any agreement which limited the time within which rights by parties could be enforced and that, therefore, as the stipulation to refer the matters to arbitration within 28 days of the issue of final certificate by the Architect limited the time in for enforcing right of reference, the said stipulation was void.
7. There is a distinction between limit on the enforcing of one's rights and the limit of the time when the very rights to enforce an agreement ceases to exist. The former case comes within mischief and purview of Section 28 while the latter does not. In former case the remedy to enforce certain rights is affected while in the latter case it is the very right, which is sought to be enforced, which is lost.
8. The aforesaid distinction was recognised by Full Bench of Punjab High Court in Pearl Insurance Co. v. Atma Ram, 1960 Punj 238. In that case a clause in the insurance policy ran as follows :—
“In no case whatever shall the company be liable for any loss or damage after the expiration of twelve months from the happening of the loss or damage unless the claim is the subject of pending action or arbitration.”
It was contended that the clause was rendered void by Section 28 of the Contract Act. It was held that as the clause did not limit time within which the insured could enforce his rights and only limited time during which the contract was to remain alive it was not hit by the provisions of Section 28 of the Contract Act. The aforesaid judgement was followed by a single Bench of this court in Union of India v. Rishi Raj Co., AIR 1973 Delhi 15. In that case a petition under Section 20 of the Arbitration Act was brought. There was cl.19 of the agreement between the parties, first proviso of which read that any demand for arbitration in respect of counter-claims etc. had to be made within one year from the date of the termination of the contract. It was held that such a term was binding. Following observations were made (Which are in para 10 at page 20) :—
“Even if no period of limitation is prescribed under the Limitation Act, 1963 for filing an application under Section 20 of the Act or even if Article 137 of the Limitation Act 1963 allows a period of 3 years for filing such an application it is open to the parties to prescribe the period of limitation or to restrict such period by mutual consent. That such restriction which is willingly placed by consent of both the parties is not opposed to public policy and is not void has been held by a Full Bench of the Punjab High Court in Pearl Insurance Co. v. Atma Ram, AIR 1960 Punj 236 (FB). Therefore, the counter-claim made by the respondent against the Government is barred by limitation by virtue of the first proviso to clause 19 of the agreement and the only dispute in respect of which the respondent can demand reference to arbitration under the main arbitration clause of the agreement is the claim made by the Government against the respondent. It is only this dispute that the Court can refer to arbitration under Section 20 of the Act.”
9. In the present case the very right to refer the dispute to arbitration was to be alive only for 28 days after the issue of final certificate by the architect. So the very right to refer the disputes to arbitration ceased to exist after the expiry of 28 days from issuance of final certificate of architect. There was no such right which could be enforced. Hence there was a limit to the very existence of the right and there was op limit on the enforcement of the same and that being so stipulation in the present case was not hit by the provisions of Section 28 of the Contract Act.
10. In the present case admittedly final certificate was issued by the architect on 18th October 1970. Therefore, application under Section 20 of the Arbitration Act could be filed up to 15th November 1970. The application was actually filed on 23rd April 1975 and was obviously hopelessly barred by time.
11. The present petition under Section 20 of the Arbitration Act is also barred by limitation as provided by the Indian Limitation Act. There is no specific article of the Schedule of Limitation Act which applies to such a petition. There is one residuary Article 137 which provides limitation of three years from the time right to apply accrues. Previously the view was that said article applied to petitions under the Code of Civil Procedure only and none other. This view was expressed in the judgement of this court also (AIR 1973 Delhi 15 referred to above) but the aforesaid view was changed later on and it was held by the Supreme Court in The Kerala State Electricity Board v. T.P Kunhaliumma, AIR 1977 SC 282 that the applications contemplated under Article 137 are not confined to the ones under the Code of Civil Procedure and the said article applied to all the applications under any law whatsoever. Hence in view of that judgement of the Supreme Court Article 137 has application to the petitions under S.20 of the Arbitration Act.
12. What the Committee wants in the present case is to refer the disputes regarding refund of some amount paid to the contractor in view of CTE report. Therefore, right to apply under Sec. 20 of the Arbitration Act accrued when the payment was made. There is no date of payment mentioned in the petition. It was for the petitioner to have specified the said date for the purpose of bringing this petition within the period of limitation. It appears that as on the date of the making of the application view of the Supreme Court as well as other High Courts was that there was no period of limitation for filing such petitions, no date from which limitation started, had been mentioned in the petition. Therefore, it has not been shown that the petition was within the period of limitation.
13. In any case it appears that it was some time after 18th October 1970 that the final payment must have been made by the Committee to the contractor because in para 3 of the petition it is stated by the Committee that the Architect issued final certificate on 18th October 1970 certifying net payment of Rupees 180001 to the contractor excluding security deposit. So even if we take that final payment was made sometimes in 1971 the period of limitation of three years expired in 1974. The petition was, therefore, time barred when the same was brought on 23rd April 1975. Issue is decided accordingly in favour of the contractor.
Issue No. 2.
14. It is urged by the learned counsel for the contractor that no disputes had been left and that the Committee did not raise any at the time of reference to arbitration at the instance of the contractor. But that argument has no force because it was subsequently found by the Committee that some excess payments had been made which they claimed and which were repudiated by the contractor. Hence there was dispute regarding refund of some payments to the contractor which were referable to the arbitration. Issue is decided accordingly in favour of the Committee.
Issue No. 3.
15. In view of the findings of issue No. 1, I hereby dismiss the petition of the Committee, but leave the parties to bear their own costs.
Petition dismissed.