Basheshar Nath & Co. v. Union Of India
Factual and Procedural Background
On 4 January 1963, the plaintiff contracted with the defendant to supply 19,600 tents at Rs. 22.625 each. The plaintiff made partial deliveries but sought an extension of time for the remaining tents. The defendant began deducting 2% per month from the plaintiff's bills and agreed to a reduced rate of Rs. 21.50. Due to further delay, the contract was cancelled while 9,450 tents remained undelivered. The defendant then purchased 1,163 tents at Rs. 217 each under the risk purchase clause and claimed Rs. 72,675 from the plaintiff. The matter was referred to an arbitrator who awarded Rs. 36,000 in favor of the defendant. The plaintiff challenged this award, contending that the defendant's actual loss was much less than the awarded sum and that the award was based on no evidence. The key issues were whether there was an error of law apparent on the face of the award and whether it was based on no evidence.
Legal Issues Presented
- Whether the arbitrator's award contained an error of law apparent on the face of it.
- Whether the award was based on no evidence, specifically regarding the quantum of loss sustained by the defendant under the risk purchase clause.
- Whether the court could examine the terms of the contract incorporated by reference in the award.
Arguments of the Parties
Plaintiff's Arguments
- The defendant's actual loss was significantly less than the amount awarded by the arbitrator.
- The award was based on no evidence on record, particularly as there was no proof that the defendant purchased the full quantity of tents claimed under the risk purchase clause.
Defendant's Arguments
- The award was rightly based on the risk purchase clause of the contract.
- The arbitrator did not explicitly incorporate the contract terms in the award, so the court should not examine the contract terms.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Union of India v. M/s. Tribhuwan Das | Interpretation of clause 11(3) of the Conditions of Contract regarding recovery of losses by the Government on contractor's failure to supply goods. | Established that the Government could recover only the loss actually sustained and not damages if no loss was suffered. The Government had options to recover liquidated damages, repurchase at contractor's risk, or cancel the contract. |
| Erroll Mackav v. Maharaja Dhiraj Kameshwar Singh, AIR 1932 Privy Council 190 | Measure of damages in breach of contract cases is the difference between contract price and market price on the date of breach. | Supported the principle that damages must be based on actual loss and not merely on contract terms. |
| M/S. Allen Berry and Co. v. The Union of India | Test for incorporation of contract terms in an arbitral award. | Clarified that an arbitrator must come to a finding on the contract wording to imply incorporation; mere general reference does not suffice. |
| Upper Ganges Valley Electricity Supply Co. Ltd. v. The U. P. Electricity Board, AIR 1974 SC 683 | Principle on reading contracts or other documents into an arbitral award. | Reinforced the restrictive approach to incorporating contract terms into an award. |
Court's Reasoning and Analysis
The court examined the risk purchase clause of the contract as incorporated by explicit reference in the arbitrator's award. It noted that the defendant claimed loss based on purchasing 9,452 tents, but evidence showed only 1,163 tents were actually purchased at Rs. 217 each, which was Rs. 5.50 per tent higher than the contract price. There was no evidence on record supporting the claim that the Government bought the full quantity of tents alleged. The court emphasized that while it could not probe the arbitrator's mental process or reassess the sufficiency of evidence, it was necessary to verify whether any evidence existed to support the award. Given the absence of evidence for the larger quantity, the award was found to be unsupported by evidence. The court also addressed the defendant's argument that the contract terms could not be examined due to lack of explicit incorporation in the award, rejecting it on the basis that the arbitrator had explicitly referred to the risk purchase loss claim, thereby incorporating the relevant contract clause.
Holding and Implications
The court set aside the arbitral award in favor of the plaintiff.
The direct effect of this decision is that the award for Rs. 36,000 based on the risk purchase loss was quashed due to lack of evidential basis for the claimed loss. No broader precedent was established beyond affirming the necessity of evidentiary support for an arbitral award and the permissibility of examining incorporated contract clauses when explicitly referenced in the award.
JUDGMENT V.D. Misra, J.
(1) (PLAINTIFF on 4.1.63 contracted with defendant to supply 19,600 tents @ Rs. 22.625 Plaintiff made part supplies and then Sought extention of time for the rest. Deft. began recovering 2% P.M. from plaintiff's bills and rate was also agreed to reduction @Rs. 211.50. When there was further delay, contract was cancelled. He was still to supply 9450 tents. Deft. then bought 1163 tents @ Rs. 217 under the risk purchase clause. However it claimed Rs. 72,675.00 from plaintiff. Matter was referred to Arbitrator who gave an award for Rs. 36,000.00 Plaintiff Challenged this. One of the objections was that Deft's actual loss was much less than the sum awarded and that the award was based on no evidence on record. The issues were whether there was error of law apparent on the face and whether it was based on no evidence.) Judgment para 10 onwards is:-
(2) Clause 11 (3) of the Conditions of Contract giving the right to the Union of India to recover the losses suffered by them on account of contractor's failure to supply the contracted goods came up for interpretation before Prakash Narain, J. in Union of India v. M/s. Tribhuwan Das . The contention of the Union of India was that irrespective of whether the Government suffered any loss or not on account of the contractor's failure to supply the contracted goods, the Government was entitled to damages. After referring to a number of decisions of various High Courts and the decision of Privy Council in Erroll Mackav V. Maharaja Dhiraj Kameshwar Singh, Air 1932 Privy Council 190 196, it was observed that the measure of damages normally, in case of breach of contract is a difference between the contract price and the market price on the date of the breach. It was held that under clause 11 (3) of the Conditions of Contract on the failure of the contractor to deliver the stores or part of the stores, the Government becomes entitled at it option either to recover as liquidated damages a sum of 2% of the price of stores not supplied or if they are supplied late; or to purchase the stores not supplied or short supplied from anywhere else at the risk and expense of the contractor and claim any excess price paid by the Government or to cancel the contract. In case there is risk purchase or cancellation of contract the contractor is liable for any loss which the purchaser or the Government may sustain though the contractor would not be entitled to payment of any gain made by the Government on the repurchase. Thus the Government could recover only loss sustained by it and could not claim damages from the contractor if no loss was sustained.
(3) The award shows that the claim put up by the Union of India was on the basis of risk purchase loss. This loss was claimed admittedly for buying 9452 tents from various persons. There is no evidence on record to show that the Union of India bought all these tents. On the other hand the statement of Mr. M. N. Krishnamurthy, Deputy Director of Supplies, shows that in fact only 1163 numbers were purchased at the rate of Rs. 217.00 each inclusive of packing charges etc. The only loss thus could be in respect of these 1163 tents in respect of which the Government paid Rs. 5.50P per tent more than the con- tracted price. There is thus no evidence on record to show that the Government suffered any other loss on risk purchase.
(4) It is true that it is not open to the court to speculate or to go into evidence and try to find out as to what impelled the arbitrator to arrive at his conclusion or to trto probe the mental process by which the arbitrator reached his conclusion. But in case where the objection is that the award is not based on evidence on record, it becomes necessary for the court to look into the evidence to find out if the evidence exists. Of course, the court cannot go into the question of sufficiency of evidence. In the instant case it was alleged that there was no evidence on record to show that the Government had re-purchased the full quantity of tents not supplied by the contractor and so it was necessary to find out if any evidence was there on record about it.
(5) It has been contended on behalf of the Union of India that the award does not incorporate or make a reference to any contract and so the terms of the contract cannot be looked into. Reference is made to M/S. Allen Berry and Co., v. The Union of India , as well as The Upper Ganges Valley Electricity Supply Co. Ltd. v. The U. P. Electricity Board, AIR. 1974 Sc 683 The test laid down in Allen Berry's case is,
"Does the arbitrator come to a finding on the wording of the contract. If he does, he can be said to have impliedly incorporated the contract or a clause in it whichever be the case. But a mere general reference to the contract in the award is not to be held as incorporating it. The principle of reading contracts or the other documents into the award is not to be encouraged or extended."
(6) In this award explicit reference has been made to the claim of the defendant on the basis of risk purchase loss under the contract. The arbitrator has thus incorporated in the award the risk purchase clause of the contract which can now be looked into by the court. Issues are, therefore decided in plaintiffs favor. Award set aside.