Factual and Procedural Background

The writ petition challenges the first respondent's order dated 09.01.2003, which rejected the petitioners' representation to allot the portion described as "open space" and directed steps to execute a gift deed in favour of the Municipality.

The petitioners state that they are joint owners of property comprised in Old Survey No. 589 (Part), present T.S. No. 132 of Ward D, Block No. 30 of Aruppukottai Town. The first and second petitioners say they obtained undivided one-third shares each by sale deeds dated 27.18.1980 and 16.02.1983 respectively, and the third and fourth respondents (as stated in the opinion) obtained the remaining undivided one-third shares each by succession. The lands were covered by the North-East Extension Town Planning Scheme Part II, sanctioned by G.O. Ms. No. 434 L.A. dated 02.03.1969 under Section 14(3) of the Madras Town Planning Act, 1920 (Madras Act VII of 1920).

The petitioners allege that no acquisition proceedings were taken after the 02.03.1969 Notification under Section 14(3) and, after the Tamil Nadu Town and Country Planning Act, 1971 (Act 35 of 1972) replaced the old Act, the relevant detailed town planning scheme provisions continued under the new Act but retained a three-year limitation for acquisition. The petitioners contend that no steps were taken under either the old or new Act within the statutory periods, and hence the reservation for "open space" has ceased.

The petitioners applied for change of use on 01.03.1999 to the second respondent through the first respondent. The first respondent rejected the application by order dated 09.01.2003. The petitioners had earlier filed W.P. No. 23214 (date in opinion appears as 20123), which was dismissed as withdrawn on 21.08.2063 (as recorded in the opinion), with liberty to file a fresh writ petition; the present petition is that fresh petition. The petitioners also relied on other writ petitions where similar reliefs were said to have been granted.

Legal Issues Presented

  1. Whether the Notification under Section 14(3) of the Madras Town Planning Act, 1920 (sanctioning the North-East Extension Town Planning Scheme Part II dated 02.03.1969) continued to operate as a subsisting declaration of acquisition in view of the absence of acquisition steps within the statutory period.
  2. Whether, after the repeal of the Madras Town Planning Act and the saving and deeming provisions of the Tamil Nadu Town and Country Planning Act, 1971 (Act 35 of 1972), the lands reserved or designated in the town planning scheme are deemed released if no declaration or acquisition is effected within three years under Section 38 of Act 35 of 1972.
  3. Whether the Municipality (or the respondents) acquired any enforceable right to the property earmarked as "open space" absent a completed acquisition, gift or other valid transfer of title by the erstwhile owner.

Arguments of the Parties

Petitioners' Arguments

  • No acquisition proceedings were taken after the Notification under Section 14(3) dated 02.03.1969; therefore the Notification ceased to have the effect of a declaration under the Land Acquisition Act and is to be deemed no acquisition.
  • The Tamil Nadu Town and Country Planning Act, 1971 (Act 35 of 1972) deems actions under the previous Act to be actions under the new Act, and the Notification of 02.03.1969 is equivalent to a notice under Section 27 of Act 35 of 1972; the new Act also contains a three-year provision for acquisition and release if acquisition is not completed.
  • Because no steps were taken under either the old Act or the new Act within the relevant three-year periods, there is no subsisting declaration of acquisition and the reservation for "open space" has ceased; the petitioners therefore are the legal owners in joint possession and applied for change of use (application dated 01.03.1999).
  • The petitioners relied on earlier decisions of this Court in which similar reliefs were granted (W.P. No. 5630 of 2000, W.P. No. 10808 of 2001).

First Respondent's Arguments

  • The first respondent states that an extent of 0.75 acres in S.No. 132 was shown as "open space" by one Thankayya Nadar in a lay-out submitted to the second respondent, and that the portion was earmarked and allotted to the Municipality for public purposes.
  • The respondent contends that Thankayya Nadar failed to gift the said portion to the Municipality and instead sold it; such sale is asserted to be invalid and not binding on the respondents. It is also denied that the petitioners are the joint owners.
  • The first respondent asserts that once land is earmarked for public utilisation under an approved town planning scheme, nobody has any right over the same and the Municipal Town Planning authority has no right to alter the approved scheme. The respondent further contends that an approval of lay-out in 1973, showing the land as reserved for public purpose, confirms that the previous owner has no right to alter the physical features of the land.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
W.P. No. 5630 of 2000: SV.P.N.S.S. Sivaramalingam v. The Commissioner, Virudhunagar Municipality and Anr. (Order dated 20.02.2001) Held that when a detailed development plan is published and the property ear-marked for a purpose is not utilised and no steps taken to acquire it, Section 38 of the Tamil Nadu Town and Country Planning Act, 1971 leads to the property being deemed released from reservation. The court relied on this decision as an example of the consistent view that where no acquisition/steps are taken to utilise reserved land within the stipulated period, the land is deemed released under Section 38; the present case was considered to fall within the same principle.
W.P. No. 12105 of 2003: R. Jeyapal v. Sattur Municipality rep. by its Commissioner, Sattur and Anr. (Order dated 03.03.2004) Followed the view that a property not acquired or declared within the statutory period after publication of the plan is deemed released under Section 38 of Act 35 of 1972. The court noted that this later decision followed the same approach as W.P. No. 5630 of 2000 and treated it as supportive precedent for releasing land from reservation where the statutory acquisition steps were not taken.
W.P. No. 10808 of 2001 (Order dated 07.09.2001) The opinion references this case as one in which similar reliefs were granted by the Court (the specific rule is not elaborated in the provided text). The petitioners relied on this decision as an instance where this Court granted relief similar to that sought in the present petition; the court recorded that similar reliefs had been granted in that case.

Court's Reasoning and Analysis

The court proceeded by first noting as common ground (admitted in the pleadings) that the disputed property formed part of the North-East Extension Town Planning Scheme Part II sanctioned on 02.03.1969 under Section 14(3) of the Madras Town Planning Act, 1920 and notified by G.O. Ms. No. 434 L.A. dated 02.03.1969.

The court then considered the effect of the repeal of the Madras Town Planning Act by the Tamil Nadu Town and Country Planning Act, 1971 (Act 35 of 1972) and the saving provisions contained in Section 125 of the new Act. Section 125(2)(a) was quoted (and applied) to explain that anything done under the previous Act is to be deemed done under corresponding provisions of the new Act unless superseded.

The court analysed provisions of Act 35 of 1972 relevant to the case: Section 34 (deeming detailed town planning schemes under the old Act to be detailed development plans under the new Act), Section 27 (notice of preparation of detailed development plan, equivalent to Section 14(3) of the old Act), and Section 36 (power to acquire land required or reserved under a plan deemed to be needed for a public purpose within the meaning of the Land Acquisition Act). Crucially, the court focused on Section 38 of Act 35 of 1972 which provides that if within three years from publication of the relevant notice no declaration under Section 37(2) is published and the land is not acquired by agreement, the land shall be deemed to be released from reservation, allotment or designation.

On the facts, the petitioners stated in affidavits that no steps were taken either under the old Act within three years of the 1969 notification or under the new Act within the three-year period stipulated by Section 38. The first respondent's counter‑affidavit did not deny that no legally effective steps were taken to acquire possession of the land earmarked as "open space." The court emphasised that mere showing of the land for public purpose in a later lay-out approval (in 1973) cannot substitute for actual acquisition or a valid gift by the erstwhile owner; possession in a legal sense requires transfer by a proper instrument (e.g., gift) or acquisition steps.

Having found that no acquisition/declaring steps were taken within the statutory periods under either the old Act or the corresponding provisions of the new Act, and noting the consistent view of this Court in prior decisions, the court concluded that the land is deemed released from reservation under Section 38 of Act 35 of 1972.

Holding and Implications

Holding: The writ petition is allowed and the impugned order of the first respondent dated 09.01.2003 is set aside. The court ordered No costs.

Implications:

  • The direct consequence for the parties is that the first respondent's rejection of the petitioners' application (and the direction to execute a gift deed in favour of the Municipality in the impugned order) has been quashed by the court.
  • The court applied Section 38 of the Tamil Nadu Town and Country Planning Act, 1971 (Act 35 of 1972) to conclude that where no declaration/acquisition steps are taken within the prescribed three-year period, land reserved in a detailed development plan is deemed released from such reservation.
  • The opinion relies on earlier decisions of this Court adopting the same approach; the judgment addresses the parties' rights on the facts and does not purport in the provided text to lay down a new or novel legal principle beyond applying the existing statutory framework and the Court's established approach.

Note: This summary is strictly limited to the facts, arguments, statutory provisions, precedents and conclusions as set out in the provided opinion. No information not present in the opinion has been added or inferred.

Show all summary ...

1. The writ petition is filed challenging the order of the first respondent dated 09.01.2003, by which the representation of the petitioners to allot the "open space", came to be rejected with direction to take steps to execute gift deed in favour of the Municipality from the owners.

2. The petitioners are stated to be the joint owners of the property comprised in Old Survey No. 589 (Part), present T.S. No. 132 of Ward D, Block No. 30 of Aruppukottai Town. The first and second petitioners have obtained their undivided 1/3rd share each under the sale deed dated 27.18.1980 and 16.02.1983 respectively and the third and fourth respondents got the remaining undivided one third share each by succession. As stated by the petitioners, the said lands along with the other adjacent lands were covered by North-East Extension Town Planning Scheme Part II, Aruppukottai, sanctioned in G.O.Ms.No.434 LA dated 02.03.1969 under Section 14(3) of the Madras Town Planning Act, 1920 (Madras Act VII of 1920 - in short referred to as "Act VII of 1928") and published as per the said provisions of the Act.

2(a). As per the said Act, immovable property required for the Scheme can be acquired under the Land Acquisition Act, 1894 (in short, "the Act") and any Notification issued under Section 14 of Act VII of 1920, is deemed to be a declaration given under Section 6 of the Act. According to the petitioners, as per act vii of 1920, if within three years from the Notification under Section 14, the lands are not acquired, the same shall cease to have the effect of declaration under the Land Acquisition Act and it is deemed to be no acquisition. According to the petitioners there was no acquisition proceedings taken after the Notification issued under Section 14(3) dated 02.03.1969.

2(b). The Tamil Nadu Town and Country Planning Act, 1971, which has replaced the Madras Town Planning Act,1920 specifically states that any action taken under the previous Act are deemed to be the action taken under the new Act. Therefore, as stated by the petitioners, the Notification detailed in Town Planning Scheme under Section 14(3) of Act VII of 1920 dated 02.03.1969 is equivalent to the Notification of the Detailed Development Plan under Section 27 of the Tamil Nadu Town and Country Planning Act, 1971. The new Act also contain a provision for acquisition similar to Section 6 of the Land Acquisition Act and also contain a clause that after expiry of three years, the same will have no effect.

2(c). According to the petitioners, even after the new Act has come into effect, no step has been taken, therefore, there is no declaration of acquisition subsisting in respect of the above said land. Therefore, according to the petitioners, the Notification issued under act vii of 1920 dated 02.03.1969, is deemed to have not been in existence, and therefore, the purchase and inheritance made by the petitioners are legally valid and they are deemed to be the owners and according to the petitioners they are in joint possession of the property. In view of the same, the portions ear-marked as "open space" under the old Scheme has come to an end. The petitioners wanted to develop the said land and hence they jointly applied to the second respondent on 01.03.1999, through the first respondent for change of use of the land covered by the said Town Planning Scheme.

2(d). By the impugned order dated 09.01.2003, the first respondent has rejected the application of the petitioners, the petitioners have filed W.P. No. 23214 of 20123 for Mandamus directing the respondents to cancel or revoke the reservation of the lands for "open space", which was subsequently dismissed as withdrawn on 21.08.2063 by an order of this Court, giving liberty to the petitioners to file fresh writ petition challenging the order of the first respondent dated 09.01.2003. Accordingly, the present writ petition is filed.

2(e). According to the petitioners, similar reliefs have been granted by this Court in other cases, viz., W.P. No. 5630 of 2000 dated 20.02.2001 and W.P. No. 10808 of 2001 dated 07.09.2001.

3. The first respondent has filed counter affidavit. According to the first respondent, an extent of 0.75 acres comprised in S.No. 132 belonged to one Thankayya Nadar, who formed a lay out in respect of larger extent of property, and submitted before the second respondent and the said extent was ear-marked as "open space", allotting the same to the Municipality for public purposes. The said Thankayya Nadar, having shown the same as "open space" failed to gift the said portion to the Municipality and the Municipality has also failed to make arrangements to acquire the "open space" allotted to it for public purpose.

3(a). It is the case of the first respondent that the said Thankkaya Nadar instead of handing over the property to the Municipality, sold the property and the sale is invalid and not binding on the respondents. It is also denied that the petitioners are the joint owners. It is admitted that the property which is in dispute is covered by North-East Extension Town Planning Scheme Part II sanctioned by G.O.Ms. No. 434 LA dated 02.03.1969 under Section 14{3) of Act VII of 1920. According to the first respondent, when once the place is ear-marked for public utilisation, nobody will have any right over the same.

3(b). According to the first respondent, the Municipal Town Planning authority have no right to alter the approved Scheme. It is also the case of the first respondent that while getting lay-out approval in respect of the disputed land in 1973 as per T.P./DTP. No. 98/73, the disputed land was reserved as "open space" for public purpose and. according to the first respondent, when once it is reserved for public utility under the Town and Country Planning Act, the previous owner has no right to alter the physical features of the land.

4. As it is admitted in the counter affidavit filed by the respondents and also the case of the petitioners, the property which is a subject matter of this writ petition formed part of North-East Extension Town Planning Scheme Part II sanctioned on 02.83.1963 under Section 14(3) of Act VII of 1920. The above Scheme was notified by the Government under the said Section in G.O.Ms. No. 434 L.A. Dated 02.03.1969. It is not disputed by the respondents in the counter affidavit that after the publication of the said Scheme, no further action was taken by the respondents for the purpose of taking possession of the said land ear-marked as "open space" in a legal manner. Merely because in an approval of lay-out subsequently in 1973 the present property was shown as for public purpose, cannot amount to taking possession of the property which can only be by way of gift from the erstwhile owner.

5. It is true that the Tamil Nadu Town and Country Planning Act, 1971 has repealed the said Madras Town Planning Act, 1920 (Madras Act VII of 1920), however stating that any action taken under the previous Act under the corresponding provisions of the new Act shall continue to be in force unless and until superseded by or anything done under the new Act. Section 125 of the Tamil Nadu Town and Country Planning Act, 1971 (Tamil Nadu Act 35 of 1972) states as follows:

125. Repeal and saving.- (1) The Tamil Nadu Town Planning Act, 1920 (Tamil Nadu Act VII of 1920) (hereinafter referred to as the said Act) is hereby repealed.

(2) Notwithstanding such repeal-

(a) anything done or any action taken including any appointment or delegation made, notification, order, instruction or direction issued, rule, regulation or scheme framed, certificate, permit or licence granted or registration effected under the said Act shall be deemed to have been done or taken under the corresponding provisions of this Act and shall continue in force accordingly, unless and until superseded by anything done or any action taken under this Act; and

(b) the betterment fee in respect of any land which any local authority was, immediately before the commencement of this Act, entitled to levy, assess and recover under the said Act, may be levied, assessed and recovered by the local planning authority concerned under the said Act as if this Act had not been passed.

6. Under the Tamil Nadu Act 35 of 1972, Section 34 deems every detailed town planning schemes prepared under the Tamil Nadu Town Planning Act, 1920, to be detailed development plans under this Act. The said provision is as follows:

Section 34. Detailed town planning schemes prepared under the Tamil Nadu Town Planning Act, 1920 deemed to be detailed development plans under this Act.- Every detailed town planning scheme notified, submitted or sanctioned under the Tamil Nadu Town Planning Act, 1928 (Tamil Nadu Act VII of 1920) together with any variation made thereto shall, for purposes of this Act, be deemed to be a detailed development plan made under the Act and all actions taken under the said Act in respect thereof shall be deemed to have been taken under-this Act.

7. Section 27 of Tamil Nadu act 35 of 1972 provides for issuance of notice for preparation of detailed development plan, which was equivalent to Section 14(3) of Act VII of 1920. The said Section reads as under:

27. Notice of the preparation of the detailed development plan.- (1) As soon as may be, after the local planning authority has received the consent of the Director under Sub-section (2) of Section 25 to the publication of the notice, the local planning authority shall publish the notice in the Tamil Nadu Government Gazette, and in leading daily newspapers of the region of the preparation of the detailed development plan and the place or places where copies of the same may be inspected, inviting objections and suggestions, in writing, from any person in respect of the said plan within such period as may be specified in the notice:

Provided that such period shall not be less than two months from the date of the publication of the notice in the Tamil Nadu Government Gazette.

(2) After the expiry of the period mentioned in Sub-section (1), the local planning authority shall allow a reasonable opportunity of being heard to any person including representatives of Government departments and authorities, who have made a request for being so heard and make such amendments to the detailed development plan as it considers proper and shall submit the said plan with or without modifications to the Director.

8. Likewise, Section 36 of Act 35 of 1972 provides for power to acquire land required or reserved or designated in the regional plan, master plan, detailed development plan or a new town development plan are deemed to be needed for a public purpose within the meaning of the Land Acquisition Act. While it is true that by advent of the new Act, the actions taken under the earlier Act are saved, even assuming that under the earlier Act, within the time limit of three years of publication of the notification under Section 14(3) no step was taken and the development plan is deemed to be a plan under the Tamil Nadu Act 35 of 1972. Section 38 of the present Act again fixes a ceiling limit of three years from the date of notice either under Section 26 or 27 for the purpose of acquiring the land, by agreement or by way of declaration and thereafter, under Section 37(2) the property is deemed to be released from such reservation. Section 38 reads as under:

Section 38. Release of land.- If within three years from the date of the publication of the notice in the Tamil Nadu Government Gazette under Section 26 or 27-

(a) no declaration as provided in Sub-section (2) of Section 37 is published in respect of any land reserved, allotted or designated for any purpose specified in a regional plan, master plan, detailed development plan or new town development plan covered by such notice; or

(b) such land is not acquired by agreement, such land shall be deemed to be released from such reservation, allotment or designation.

9. On the facts and circumstances of the present case, the petitioners have clearly stated in the affidavit, that even under the old act vii of 1920, no steps were taken for the purpose of completing the acquisition within three years and the same has not been denied in the counter affidavit filed by the first respondent. Even assuming that the said Scheme has been taken over under the act 35 of 1972, even from the date of coming into effect of the Act within the period stipulated under Section 38, no steps have been taken by the respondents for acquiring the property for the purpose of "open space" stated to have been reserved under the North-East Extension Town Planning Scheme Part II, Aruppukottai sanctioned under G.O.Ms. No. 474 LA dated 02.03.1969.

10. This has been the consistent view taken by this Court in various cases also. In W.P. No. 5630 of 2000 SV.P.N.S.S. Sivaramalingam v. The Commissioner, Virudhunagar Municipality and Anr. K.P. Sivasubramaniam, J. by order dated 20.02.2001, while dealing with detailed development plan under act 35 of 1972 has held that after publishing the said plan on 23.05.1984, the property ear-marked for the purpose has not been utilised in terms of Notification and no steps have been taken by the authority to acquire the property and therefore, as per Section 38 of the Tamil Nadu Town and Country Planning Act, 1971, the property is deemed to be released from such reservation, allotment or designation. The same view was subsequently followed by P.D. Dinakaran, J. in W.P. No. 12105 of 2003 R. Jeyapal v. Sattur Municipality rep. by its Commissioner, Sattur and Anr. in the order dated 03.03.2004.

In view of the above said factual situation, the writ petition stands allowed and the impugned order of the first respondent is set aside. No costs.