Kandaswami Mudaliar v. Munuswami Udayar And Others.

Madras High Court
Nov 21, 1973
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The plaintiffs filed a suit for specific performance of an agreement dated 21st August, 1952, executed by the defendant in favour of the plaintiffs for conveyance of certain items of the suit properties. The plaintiffs intended to purchase a property from one Ramaswami but were unable to raise funds. They approached the defendant who, citing the Debt Relief Act, agreed to advance money on condition that the plaintiffs convey both the property proposed to be purchased and other property they owned to the defendant; the defendant would thereafter transfer the property back when the plaintiffs paid the stipulated sum with interest.

Sale deeds executed in favour of the defendant by registered documents dated 29th May, 1950 were followed by a registered agreement to sell dated 21st August, 1952. The agreement provided that the defendant agreed to sell the land to the plaintiffs for Rs. 7,000; the plaintiffs paid an advance of Rs. 10 on 21st August, 1952 and were to pay the balance of Rs. 6,990 on or before 12th April, 1957. If the balance were paid before that date and the defendant (or his heirs) failed to execute the sale deed, the plaintiffs could sue for specific performance; if the plaintiffs failed to pay by 12th April, 1957 they would forfeit the advance and the right to enforce specific performance and the agreement would be cancelled.

It is common ground that the plaintiffs did not pay Rs. 6,990 before 12th April, 1957. Before filing the suit (filed on "nth April, 1960" as recorded in the opinion), the plaintiffs gave notice stating they were ready to meet the defendant at the Sub-Registrar's Office, Tirupattur with Rs. 6,990 for taking the sale deed. The defendant repudiated liability to specifically perform the agreement.

At trial the Court found the agreement to be an agreement to sell (not an agreement to reconvey), held that time was not the essence of the contract, found the suit within time and decreed specific performance. On appeal to the District Judge the appellate Court held the document was an agreement to reconvey, that time was of the essence, and that because the plaintiffs failed to pay by 12th April, 1957 their claim for specific performance could not be enforced. The plaintiffs obtained a second appeal to this Court (Venkatadri, J.), who concluded the agreement was simpliciter to sell and not a reconveyance, and decreed the plaintiffs' suit. The defendant then filed this Letters Patent Appeal, which is the subject of the present opinion.

Legal Issues Presented

  1. Whether the document (Exhibit A-1 / the agreement dated 21st August, 1952) is an agreement simpliciter to sell the suit property or an agreement for reconveyance (i.e., whether the transaction is in the nature of a reconveyance).
  2. Whether time was the essence of the contract (specifically, whether the plaintiffs' failure to pay the balance by 12th April, 1957 barred their right to specific performance).
  3. Whether the plaintiffs were always ready and willing to perform their part of the contract (the requirement for specific performance), and whether the plaintiffs bore the burden of proving continuous readiness and willingness.

Arguments of the Parties

Appellant's (Defendant's) Arguments

  • The transaction was in the nature of an agreement of reconveyance; time was the essence of the contract and, since the plaintiffs failed to pay Rs. 6,990 before 12th April, 1957, they could not specifically enforce the contract.
  • Mr. M. S. Venkatarama Iyer (for the appellant) relied on the clause forfeiting the advance and rights if the plaintiffs failed to pay by the stipulated date, arguing that that clause made time essential and that the plaintiffs were not ready and willing to perform their part of the contract because they had stated in their notice that they were unable to find the money till 12th April, 1957.

Respondents' (Plaintiffs') Position

  • The plaintiffs treated the agreement as an agreement to sell simpliciter (not a reconveyance) and relied on the trial Court's finding that time was not the essence of the contract.
  • The plaintiffs issued a notice before filing suit indicating readiness to meet the defendant with Rs. 6,990 at the Sub-Registrar's Office, and the trial Court and the second appeal Court found that the plaintiffs were always ready and willing to perform their part of the contract.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Jamshed Khodaram Irani v. Burjorji Dhunjibhai (1916) I.L.R. 40 Bom. 289 The principle that, in equity, time fixed in a contract for sale of immovable property is not necessarily the essence; equity looks to the substance of the agreement and will enforce specific performance notwithstanding non‑literal observance of time limits unless the language unmistakably makes time essential. The Court held that this Privy Council decision is on all fours with the present case and is applicable. Applying that principle, the Court concluded that time was not the essence of the contract in the present facts despite a clause stipulating forfeiture if the plaintiffs failed to pay by the stipulated date.
Gomathinayagam Pillai v. Palaniswami Nadar Authority on the requirement that a plaintiff seeking specific performance must be ready and willing to perform his part of the contract throughout; the Court cited paragraph 10 which clarifies that lack of funds by the last date does not automatically defeat a claim for specific performance if time is not of the essence. The Court rejected the appellant's narrow reading of the case (that the plaintiff had to have funds ready by the last date). It interpreted the decision to mean that the plaintiff must remain ready and willing during the continuance of the contract but need not have had funds strictly by the last date when time is not of the essence.

Court's Reasoning and Analysis

The Court proceeded through a structured analysis addressing (a) the character of the transaction (agreement to sell simpliciter versus reconveyance), (b) whether time was the essence of the contract, and (c) whether the plaintiffs had been ready and willing to perform their contractual obligations.

On the character of the transaction, the Court accepted and relied upon the trial Judge's detailed findings (paragraph 10 of the trial judgment). The Court noted that the sale deeds in favour of the defendant were executed in 1950 while the agreement to sell was executed in 1952 (i.e., the documents were not contemporaneous). The agreed sale consideration in the earlier sale deeds (Rs. 5,500) differed from the Rs. 7,000 stipulated in the 1952 agreement. It was also pointed out that two properties were conveyed to the defendant, one belonging to the plaintiffs and another belonging to a third party (Ramaswami), and that the defence had not pleaded that the 1952 agreement was executed pursuant to an agreement to reconvey. Taking these factual circumstances together, the Court agreed with the trial Court and the learned Judge in the second appeal that the transaction was an agreement simpliciter to sell and not an agreement for reconveyance.

On whether time was the essence, the Court engaged the Privy Council authority (Jamshed Khodaram Irani v. Burjorji Dhunjibhai) and observed that equity looks to substance; time stipulated in contracts for sale is prima facie subordinate to the main purpose unless the stipulation plainly excludes the notion that the time limits were of secondary importance. The Court found the Privy Council decision to be applicable and concluded that time was not the essence of the contract in the present case despite the clause providing forfeiture and cancellation if the plaintiffs failed to pay by the specified date.

On the plaintiffs' readiness and willingness, the Court considered the contention of the appellant that the plaintiffs had admitted they were unable to find money until 12th April, 1957 and therefore were not ready and willing. The Court interpreted the Supreme Court authority (Gomathinayagam Pillai v. Palaniswami Nadar) to mean that while a plaintiff must be ready and willing to perform the essential terms during the continuance of the contract, this does not necessarily require that the plaintiff have funds strictly by the last date where time is not of the essence. The Court referred to Section 16(b) and (c) of the Specific Relief Act (XLVII of 1963) to explain the legal standard: that specific performance cannot be granted to someone who has become incapable of performing or has violated essential terms (16(b)), and that the plaintiff should aver and prove that he has performed or has always been ready and willing to perform the essential terms of the contract (16(c)), other than terms prevented or waived by the defendant.

Although the appellant argued that the plaintiffs had not proved continuous readiness (and that no oral evidence was adduced), the Court observed that this point was not specifically raised at trial or on earlier appeals. On the available materials the Court was satisfied that the plaintiffs were always ready and willing to perform their part of the contract and genuinely wished to recover the property.

Having accepted the trial Court's and the second appeal Judge's conclusion that the agreement was an agreement simpliciter to sell and that time was not the essence, and having found the plaintiffs sufficiently ready and willing to perform, the Court saw no reason to disturb the order and dismissed the Letters Patent Appeal.

Holding and Implications

Holding: The Letters Patent Appeal is dismissed with costs. The Court agreed with the trial Court and the Judge in the second appeal that the agreement dated 21st August, 1952 (Exhibit A-1) was an agreement simpliciter to sell and that time was not the essence of the contract; the plaintiffs were found to have been ready and willing to perform, and the decree for specific performance is upheld.

Implications: The direct effect is that the decree for specific performance in favour of the plaintiffs stands and the defendant's appeal is dismissed with costs. The opinion applies established equitable principles (as articulated in the cited Privy Council authority) concerning when time in a contract is treated as essential, and it clarifies the application of the requirement of readiness and willingness in specific performance claims. The Court did not state that it was laying down a new precedent beyond applying the existing authorities to the facts; the decision upholds the decree on the facts and law presented in this case.

Show all summary ...

1. The defendant in the suit is the appellant in this Letters Patent Appeal. The plaintiffs filed the suit for specific performance of an agreement dated 21st August, 1952 executed by the defendant in favour of the plaintiffs for conveyance of certain items of the suit properties. The plaintiffs wanted to purchase one item of property from one Ramaswami. They were unable to raise funds. They approached the defendant and the defendant told the plaintiffs that because of the Debt Relief Act, he would not be in a position to advance money to the plaintiffs at a high rate of interest, but if the plaintiffs agreed, he would advance money on condition that the plaintiffs should convey not only the property that was proposed to be purchased but also the property they owned to the defendant and after such conveyance, the defendant would agree to transfer the property back to the plaintiffs on their paying the entire money with interest stipulated. Accordingly, sale deeds were executed in favour of the defendant by registered documents, dated 29th May, 1950. The defendant agreed to sell the property back to the plaintiffs and executed a registered agreement to sell in favour of the plaintiffs on 21st August, 1952. The agreement provided that the defendant agreed to sell the land to the plaintiffs for Rs. 7,000 and took an advance of Rs. 10 on 21 st August, 1952 and agreed that if the plaintiffs paid the balance of Rs. 6,990 at any time before 12th April, 1957 to the defendant, the defendant or his heirs and representatives should execute and register a sale deed in favour of the plaintiffs at their cost. The defendant also agreed that if the plaintiffs paid Rs. 6,990 before 12th April, 1957 and if the defendant or his heirs and representatives failed to execute and register the sale deed in favour of the plaintiffs, the plaintiffs could file a suit for specific performance of the contract of sale. The agreement further provided that if the plaintiffs failed to pay the amount of Rs. 6,990 within 12th April, 1957 the plaintiffs would forfeit the advance paid by them and also forfeit the right to enforce specific performance and the agreement would stand cancelled. It is common ground that the plaintiffs did not pay Rs. 6,990 before 12th April, 1957 but filed the suit on nth April, 1960 for specific performance. But before filing the suit, they issued a notice saying that they were ready to meet the defendant at the Sub-Registrar's Office, Tirupattur with Rs. 6,990 for taking the sale deed. The defendant repudiated his liability to specifically perform the agreement.

2. The defence taken to the suit was that the transaction was in the nature of an agreement of reconveyance and that time is the essence of the contract and as the plaintiffs had failed to pay the balance of Rs. 6,990 before 12th April, 1957, the plaintiffs could not specifically enforce the contract.

3. The trial Court found that the agreement was an agreement to sell and not an agreement to reconvey and time is not the essence of the contract. It also found that the suit filed by the plaintiffs is within time. In this view, the trial Court decreed the suit. The defendant appealed to the District Judge, North A cot. In the appeal, the appellate Court considered two questions, namely, whether time is the essence of the contract and whether the suit is barred by time. The appellate Court held that the document Exhibit A-1 is an agreement to reconvey the property and time is the essence of the contract and that as the plaintiffs had failed to pay the money before 12th April, 1957, the time stipulated, the plaintiffs cannot enforce the agreement for specific performance.

4. The plaintiffs took the matter in second appeal to this Court. Venkatadri, J., considered the question whether Exhibit A-1 is an agreement simpliciter to sell the suit property or an agreement for reconveyance of the suit property. The learned Judge came to the conclusion that the agreement is an agreement simpliciter and that it was not an agreement for reconveyance and therefore time is not the essence of the contract and decreed the plaintiffs' suit. Hence this Letters Patent Appeal.

5. The learned trial Judge in paragraph 10 of his judgment has elaborately gone into the question as to whether the document in an agreement of reconveyance or an agreement of sale simpliciter. He has pointed out that the property was sold by the plaintiff's to the defendant for a total consideration of Rs. 5,500, while the agreement between them stipulated that the plaintiffs should pay Rs. 7,000 to the defendant on or before 12th April, 1957, Apart from the difference in the price, the sale deeds and the agreement to convey are not contemporaneous documents. The sale deeds were executed in 1950 but the agreement to convey was entered into only in 1952. It was in fact not claimed in the written statement by the defendant that the agreement was executed in pursuance of an agreement to reconvey the property. It may also be noted that out of the two properties conveyed to the defendant, one property alone belonged to the plaintiffs and another to one Ramawwami. Both the properties were conveyed in the name of the defendant as security for payment of the money due by the plaintiffs to the defendant. In such circumstances, it cannot be said, that there was any agreement of reconveyance of properties, one belonging to a stranger and another to the plaintiffs. It was an agreement entered into two years after the execution of the sale deed wherein the defendant agreed to sell the property. Taking all these facts into account, we agree with the trial Court and the learned Judge who heard the second appeal that the transaction was an agreement to sell simpliciter and not an agreement for reconveyance.

6. In all the agreements to convey immoveable property, usually time is not the essence of contract. The question has been elaborately dealt with by the Privy Council in Jamshed Khodaram Irani v. Burjorji Dhunjibhai (1916) I.L.R. 40 Bom. 289, In that case the contract provided that should the purchaser not pay the amount within the fixed period mentioned in it he was to have no right to the deposit or earnest money paid on account and any claim of his was to be void, and the vendor was, after that date, to be at liberty to re-sell. In spite of such a specific clause the Privy Council held, after referring to Section 55. of the Indian Contract Act, 1872 that the law of equity which governs the rights of the parties in cases of specific performance of contracts to sell real estate, looks not at the letter but at the substance of the agreement in order to ascertain whether the parties, notwithstanding that they named a specific time within which completion was to take place, really and in substance intended more than that it should take place within a reasonable time. Their Lordships observed:

But to have this effect the language of the stipulation must show that the intention was to make the rights of the parties depend on the observance of the time limits prescribed in a fashion which is unmistakeable. The language will have this effect if it plainly excludes the notion that these time limits were of merely secondary importance in the bargain, and that to disregard them would be to disregard nothing that lay at its foundation. Prima facie, equity treats the importance of such time limits as being subordinate to the main purpose of the parties, and it will enjoin specific performance notwithstanding that from the point of view of ? Court of Law the contract has not been literally performed by the plaintiff as regards the time limit specified.

In this case, Mr. M.S. Venkatarama Iyer, strongly relied on the provision in the agreement that if the plaintiff failed to pay the amount, the agreement not only gets cancelled, but also he would stand to lose the advance amount and shall be deemed to have lost all rights in the property. This clause in the agreement is more or less similar to the one that was dealt with by the Privy Council in Jamshed Khodaram Irani v. Burjorji Dhunibhai (1916) I. L. R. 40 Bom. 889 and that decision is on all fours and is applicable to the facts of this case. We therefore consider that time is not the essence of the contract.

7. In this Letters Patent Appeal Mr. M.S. Venkatarama Iyer, submitted that the Courts below lost sight of the essential condition that is necessary to enable the plaintiffs to succeed in a suit for specific performance, namely, that the plaintiff, should aver and prove that they were always willing and ready to perform their part of the contract. According to the learned Counsel, as in their notice the plaintiffs had stated that they were unable to find money till 12th April, 1957, the period stipulated under the agreement, it must be held that they were not ready and willing to perform their part of the contract and they were not entitled to a decree for specific performance. This plea was not taken in the trial Court. The trial Court decreed the suit and the defendant preferred an appeal. Even in the memorandum of appeal grounds, this ground was not raised. But being a question of law we allowed the learned Counsel to raise this point. In support of his contention the learned Counsel relied on the decision of the Supreme Court in Gomathinayagam Pillai v. Palaniswami Nadar submitted relying on paragraph 10 of the judgment that before a decree for specific performance could be granted, the plaintiff would have to prove his readiness and willingness continuously from the date of the contract till the date of hearing of the suit and if he failed in that his suit was liable to fail. Learned Counsel would construe this observation as meaning that the plaintiff should be ready and willing to perform his part of the contract by keeping the money ready to be paid to the defendant. We are unable to accept the interpretation put upon the sentence of the judgment of the Supreme Court by the learned Counsel. All that it means is that during the course of the continuance of the contract and subsequently the plaintiff must be ready and willing to perform his part of the contract. Section 16 of the Specific Relief Act (XLVII of 1963) provides that specific performance of a contract cannot be enforced in favour of persons specified in clause (a) (b) and (c) of that section. sub-section (b) provides that specific performance cannot be had in favour of a person who has become incapable of performing, or violates any essential term of, the contract that on his part remains to be performed, or acts in fraud of the contract, or willfully acts at variance with, or in subversion of the relation intended to be established by the contract. The sum and substance of sub-clause (b) is that the plaintiff should continue to stand by the contract and should not have become incapable of performing the contract or violated any of the terms of the contract. Sub-section (c) provides that the plaintiff should aver and prove that he has performed or has always been ready and willing to perform the essential terms of the contract which are to be performed by him, other than terms the performance of which has been prevented or waived by the defendant. This position is made clear by the Supreme Court in the latter part of the paragraph wherein it states:

A ground for rejecting the respondent's claim for specific performance will not arise merely because the respondent was not ready with the necessary funds on 30th April, 1959, if time was not of the essence.

The above sentence makes it abundantly clear that the plaintiff will not lose his right to get specific performance merely because he had not the necessary funds before the last date provided under the contract but he will not be entitled to specific performance "is the respondent was not ready and willing to perform his part of the contract. " Thus it is clear that it is not essential that the plaintiff should have money ready in contracts where time is not the essence but should always stand by and be ready and willing to perform his part of the contract. We are unable to agree with the submission of the learned Counsel that the decision of the Supreme Court in Gomathinayagam Pillai v. Palaniswami Nadar , would negative the claim of the plaintiff for specific performance.

8. The learned Counsel submitted that in any event the burden is on the plaintiffs to prove that they were always ready and willing to perform the contract and that this has not been proved as no oral evidence has been let in. This point was not specifically raised or put in issue in either the trial Court or the appellate Court or even before the learned Judge who heard the second appeal. As a matter of fact, on the materials available, we are satisfied that the plaintiffs were always ready and willing to perform their part of the contract. They wanted really to get back the property.

9. In the result, we do not see any reason for not accepting the conclusion arrived at by the learned Judge. The Letters Patent Appeal is dismissed with costs.