Arjuna Mudaliar v. Lakshmi Ammal And Others.

Madras High Court
Mar 24, 1948
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The plaintiff, along with his deceased brother Ramaswami Mudali (who was guardian of his minor son, the third defendant), sold certain suit properties to the second defendant on 9th January 1920 by a registered sale deed for Rs. 300. On the same day, the second defendant and his wife (the first defendant) executed an agreement to reconvey the properties upon payment of the principal sum and interest. After Ramaswami Mudali's death, his sons and widow became defendants. The plaintiff instituted a suit on 4th September 1942 claiming either redemption of the properties on the basis that the sale and reconveyance agreement amounted to a mortgage by conditional sale, or alternatively, specific performance of the reconveyance agreement.

The defendants denied the transaction amounted to a mortgage and raised limitation as a defense for the specific performance claim. The plaintiff claimed entitlement to benefits under the Madras Act IV of 1938, which the defendants denied.

The suit was dismissed by the District Munsiff, who held the unregistered reconveyance agreement could not affect the registered sale deed and that the plaintiff was not entitled to specific performance due to lack of averment of readiness and laches. The Subordinate Judge concurred with dismissal but on the ground that the third defendant was not joined as a plaintiff. On further appeal, Chandrasekhara Aiyar, J., affirmed dismissal on grounds of lack of readiness and long delay (22 years) making specific performance inequitable. The plaintiff now appeals in the Letters Patent Appeal.

Legal Issues Presented

  1. Whether the sale deed and the agreement to reconvey together constitute a mortgage by conditional sale entitling the plaintiff to redemption.
  2. Whether the plaintiff has sufficiently averred readiness and willingness to perform his part of the contract, a prerequisite for specific performance.
  3. Whether the long delay (22 years) in enforcing the agreement bars the plaintiff's claim for specific performance.
  4. Whether the agreement to reconvey is void for offending the rule against perpetuities.
  5. Whether the plaintiff is entitled to benefits under the Madras Agriculturists Relief Act.

Arguments of the Parties

Appellant's Arguments

  • The sale deed and reconveyance agreement form a single transaction amounting to a mortgage by conditional sale, entitling the plaintiff to redemption.
  • The plaintiff is ready and willing to perform his part of the contract, as indicated by his willingness to pay any sum the Court may fix.
  • The delay in enforcing the agreement should not bar specific performance as there is no evidence of abandonment or prejudice to defendants.
  • The plaintiff claims entitlement to benefits under the Madras Act IV of 1938.

Contestant Defendants' Arguments

  • The transaction does not amount to a mortgage.
  • The suit is barred by limitation due to the long delay in seeking specific performance.
  • The agreement to reconvey is void as it offends the rule against perpetuities.
  • The plaintiff is not entitled to benefits under the Madras Agriculturists Relief Act.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Rustomali v. Ahider Rahaman Mia (1940) 45 C.W.N. 837 Requirement of readiness and willingness to perform contract for specific performance. Held not applicable as plaintiff made sufficient averment of willingness to perform in accordance with Court's decision.
Bindeshri Prasad v. Mahant Jairam Gir (1887) L.R. 14 I.A. 173 : I.L.R. 9 All 705 (P.C.) Requirement of readiness and willingness to perform contract for specific performance. Held not applicable for same reason as above.
Lindsay Petroleum Co. v. Hurd (1873) L.R. 5 P.C 221, 239 Delay and lapse of time relevant to waiver or prejudice in specific performance claims. Applied to reject presumption of abandonment merely from delay without evidence of prejudice or waiver.
Athikarath Nanu Menon v. Erathanikat Komu Nayar (1897) I.L.R. 21 Mad. 42 Delay alone does not establish abandonment of rights for specific performance. Supported the view that delay must be accompanied by other factors to bar relief.
Charamudi v. Raghavulu (1915) 28 M.L.J. 471 : I.L.R. 39 Mad. 462 Validity of agreements potentially offending rule against perpetuities. Applied to reject contention that agreement to reconvey was void under rule against perpetuities.

Court's Reasoning and Analysis

The Court examined whether the plaintiff had sufficiently averred readiness and willingness to perform the contract, a necessary foundation for specific performance. The Court found that the plaintiff’s statement expressing willingness to pay any sum fixed by the Court satisfied this requirement, overruling the lower Courts’ contrary findings and distinguishing the precedents cited by defendants.

Regarding delay, the Court emphasized established principles that mere delay does not bar specific performance unless it evidences abandonment or causes prejudice to the defendant. The Court found no evidence of abandonment or prejudice here, noting the parties’ apparent understanding of a mortgage-like transaction with a 60-year redemption period. Thus, the 22-year delay was not fatal.

The Court rejected the defendants’ argument that the agreement was void under the rule against perpetuities, relying on prior authoritative precedent affirming the agreement’s validity.

Finally, the Court held that the Madras Agriculturists Relief Act did not apply, and that the plaintiff must deposit the principal and interest as per the agreement within a fixed time without extension, reflecting the long lapse.

Holding and Implications

The Court allowed the plaintiff’s appeal and granted a decree for specific performance of the agreement to reconvey the suit properties.

The plaintiff must deposit Rs. 300 with interest at 12% per annum from the date of the agreement to the date of the plaint, and thereafter at 6% per annum until deposit, within three months from the date of the order, with no extension allowed.

The Madras Agriculturists Relief Act does not apply. Costs of the Letters Patent Appeal are awarded to the appellant against defendants 1 and 2, but no costs are ordered in the second appeal or in the lower Courts.

No new precedent was established; the decision primarily clarifies the application of established principles regarding readiness for specific performance, the effect of delay, and the validity of the agreement under the rule against perpetuities.

Show all summary ...

1. The plaintiff is the appellant. He and his deceased brother, one Ramaswami Mudali, and the latter as the guardian of his minor son the third defendant, sold the suit properties to the second defendant on 9th January, 1920, by registered sale deed Ex. D. 1, for a sum of Rs. 300. On the same day, the second defendant and his wife, the first defendant, executed in favour of the vendors an agreement, Ex. P-1, agreeing to reconvey the properties on the vendors paying on any day the principal of Rs. 300, the sale price, and interest accrued on it at the rate of Re. 1 per Rs. 100 per mensem. Ramaswami Mudali died, and defendants 3 and 4 are his sons and the fifth defendant is his widow. The plaintiff instituted the suit out of which this appeal arises in the Court of the District Munsiff of Ami on 4th September, 1942, claiming one of two alternative reliefs. His first claim was on the basis that the sale deed and the agreement to reconvey formed part of the same transaction, and together amounted in law to a mortgage by conditional sale. On this footing, he claimed redemption. In the alternative, he claimed specific performance of the agreement to reconvey. The contesting defendants 1 and 2 denied that the transaction amounted to a mortgage and pleaded that the suit was barred by limitation because the agreement was sought to be enforced after the expiry of a reasonable time. The plaintiff alleged that in calculating the amount payable to the defendants he would be entitled to the benefits of Madras Act IV of 1938, but the defendants denied that he was so entitled.

2. The learned District Munsiff of Arni who tried the suit dismissed it. He held that as the agreement to reconvey was unregistered it cannot in any way affect in law the registered conveyance and the two together could not amount to a mortgage by conditional sale. He further held that the relief of specific performance could not be granted as there was no averment by the plaintiff of his willingness to perform his part of the contract and also because of his laches, as the transaction was so far back as 1920. The plaintiff appealed to the Subordinate Judge of Vellore who concurred with the District Munsiff in dismissing the suit but on a ground different from the grounds on which the District Munsiff based his decision. The learned Subordinate Judge held that the plaintiff would not be disentitled to the relief of specific performance because of delay but because one of the parties to the agreement to reconvey, namely, the present third defendant, was not joined as a plaintiff; and as he did not also pray for specific performance, the plaintiff alone would not be entitled to a decree. The plaintiff again appealed to this Court in S.A. No. 284 of 194.6. Chandrasekhara Aiyar, J., agreed with the lower Courts in dismissing the plaintiff's suit, but not exactly on the ground on which the learned Subordinate Judge negatived the plaintiff's claim. The learned Judge held that the plaintiff was not entitled to specific performance because he had not expressed his readiness and willingness to perform his part of the contract when such an averment was the foundation for an action for specific performance and also because there had been a long and unreasonable delay in enforcing the claim, and it would be inequitable to grant a decree for specific performance after the lapse of 22 years.

3. The plaintiff is again the appellant in the Letters Patent Appeal.

4. Undoubtedly, in a suit for specific per romance the plaintiff has to allege that he is ready and willing to perform his part of the contract. But we do not agree with the learned Judge that it is difficult to spell out such an averment from the plaint. It is true that he raised various pleas as regards the amount rightly payable to the contesting defendants 1 and 2, but finally in paragraph 16 he stated this:

Though the plaintiff is entitled to claim larger relief's from the defendants, the plaintiff has no objection to pay the defendants any sum that the Court should be pleased to fix.

In view of this averment, the decisions in Rustomali v. Ahider Rahaman Mia (1940) 45 C.W.N. 837 and Bindeshri Prasad v. Mahant Jairam Gir (1887) L.R.

14 I.A. 173 : I.L.R. 9 All 705 (P.C.) relied on by the learned advocate for the contesting respondents (defendants 1 and 2) have no application. The plaintiff is not asserting a right to perform the contract not as it actually was but as it is alleged to be by him. Though he puts forward his own case, he makes it clear that he is ready and willing to perform the terms of the contract in accordance with the decision of the Court. No authority has been cited to us that an averment that the plaintiff had no objection to perform the contract in accordance with the decision of the Court is not a sufficient averment of his readiness and willingness to perform his part of the contract. Such an averment the plaintiff has made in this case. On this point we agree with the learned Subordinate Judge.

5. The learned Judge held that the delay of 22 years in enforcing the agreement was fatal to the plaintiff's suit. It is now well established that mere delay does not by itself preclude the plaintiff from obtaining specific performance if his suit is otherwise in time. The delay must be such that it may be properly inferred that the plaintiff has abandoned his right or on account of the delay there must have been such a change of circumstances that the grant of specific performance would prejudice the defendant. Their Lordships of the Judicial Committee pointed out in the leading case of Lindsay Petroleum Co. v. Hurd (1873) L.R. 5 P.C 221, 239 when lapse of time and delay are most material.

Where it would be practically unjust to give a remedy either because the party has, by his conduct, done that which might fairly be regarded as equivalent to a waiver of it, or where by his conduct and neglect, he has, though perhaps not waiving that remedy, yet put the other party in a situation in which it would not be reasonable to place him if the remedy were afterwards to be asserted; in either of these cases lapse of time and delay are most material.

Vide also Athikarath Nanu Menon v. Erathanikat Komu Nayar (1897) I.L.R. 21 Mad. 42. With great respect to the learned Judge, we must say that we have not been referred to any authority in which it had been held that from long delay alone without anything further, an abandonment of rights could be presumed.

6. Now in this case, there is no evidence whatever from which it could be inferred that the plaintiff had abandoned his right. The learned Judge himself observes that it is probable that the parties thought that the transaction amounted to a mortgage and there was a period of 60 years to redeem the mortgage and recover possession. If this was likely to be the consciousness of the parties, then certainly the delay of 22 years cannot lead to an inference of an abandonment of his rights by the plaintiff. Likewise, there is no evidence that on account of the lapse of time defendants 1 and 2 would be prejudiced if the plaintiff is now granted specific performance. No rights of third parties have intervened, and it is not suggested that there are any special circumstances which make it unequitable that the plaintiff should be granted the relief to which he would be entitled on foot of the agreement to reconvey. On this point we agree with the learned Subordinate Judge that the delay is no bar to the maintainability of the suit.

7. It was contended by the learned advocate for the contesting respondents that the agreement to reconvey is void because it offends against the rule of perpetuities. But this contention cannot be accepted in view of the decision of this Court in Charamudi v. Raghavulu (1915) 28 M.L.J. 471 : I.L.R. 39 Mad. 462.

8. The plaintiff will, therefore, be entitled to specific performance of the agreement to reconvey. The Madras Agriculturists Relief Act cannot possibly apply to the case, and the plaintiff, before he gets a conveyance must, in accordance with the terms of the agreement, deposit into Court the sum of Rs. 300 with interest thereon at the rate of 12 per cent. per annum from the date of the agreement upto the date of the plaint and thereafter at 6 per cent. per annum upto the date of the deposit. The time for deposit will be three months from this date. Having regard to the long lapse of time, the plaintiff will not be entitled to any extension of time which we have now granted to deposit the money. There will be a decree for specific performance. The appellant will be entitled to his costs from the contesting respondents 1 and 2 in the Letters Patent Appeal. But there will be no order as to costs in the second appeal and in the Courts below.