Kohinoor Ctnl Infras... v. Municipal Corporatio...
Structured Summary of the Opinion — Dr. D.Y. Chandrachud, J.
Factual and Procedural Background
The First Petitioner owns Final Plot No. 46 of Town Planning Scheme-III at N. Kelkar Road, Shivaji Park, Mumbai and is developing a high-rise complex comprising three wings (A, B and C) with three basements for captive parking. The dispute concerns Wing-C, which was planned to provide municipal public parking on the ground floor and 14 upper floors with residential premises on 18 floors above the parking facility.
Municipal and central approvals were obtained: Municipal Corporation sanctioned plans and issued an IOD on 15 February 2006; Environmental Clearance by the Union Ministry of Environment and Forests was given on 22 August 2006; a Commencement Certificate was issued on 13 September 2006 (up to the fourteenth floor for Wing-C). The IOD was subsequently amended in 2008 and 2009. The Joint Commissioner of Police (Traffic) issued an NOC on 11 December 2009; State Government gave in-principle approval for a multi-storeyed public parking lot on 2 June 2010; the Municipal Corporation issued a Letter of Intent on 27 July 2010.
On 4 March 2011 the State Government directed amendment of Development Control Regulation (DCR) 33(24) to limit the height of parking towers to four floors and to revoke sanctioned proposals without commencement certificates. The Municipal Corporation issued a circular on 22 June 2011 prescribing conditions under Clause (iv) of DCR 33(24), limiting public parking to a ground plus four upper floors and two basements and imposing caps on built-up area per parking space.
On 29 November 2011 a notice to show cause was issued to the Petitioners under section 51 of the Maharashtra Regional and Town Planning Act, 1966 calling for explanation as to why a commencement certificate issued on 30 October 2010 should not be revoked; the circular dated 22 June 2011 was relied upon in that notice. The Petitioners replied on 14 December 2011. On 22 December 2011 a stop work notice restricted the Petitioners' work to the fourth floor instead of the thirteenth floor.
On 27 April 2012 the Additional Municipal Commissioner (AMC) passed an order which examined whether the works were "substantially completed on site or otherwise" as of 30 November 2011. The AMC found that about 50% of the area had construction "beyond the stage which can be termed substantial", and allowed the already executed construction to stand for that core part, while limiting the remaining portion to ground plus four floors and directing modification of plans consistent with the modified DCR.
The Petitioners challenged the AMC's order in the present petition. This Court heard the matter (hearing took place with consent of counsel) and rendered the decision recorded in this opinion.
Legal Issues Presented
- Whether the proviso to section 51 of the Maharashtra Regional and Town Planning Act, 1966 bars an order of revocation or modification of development permission where operations have "substantially progressed" prior to such an order, and how that proviso must be interpreted and applied.
- Whether the Additional Municipal Commissioner applied the correct legal test under section 51 (particularly Clause (a) of the proviso) when determining whether operations had "substantially progressed" and whether the impugned order limiting construction to ground plus four upper floors was legally tenable in view of the facts found by the AMC.
Arguments of the Parties
Petitioners' Arguments
- The AMC misconstrued section 51 by applying a test of whether work was "substantially completed" rather than whether operations had "substantially progressed"; the proviso protects operations that have "substantially progressed" even if not completed.
- The AMC itself found that a substantial part of construction on the core portion had been completed; therefore it was impermissible to restrict the Petitioners to ground plus four upper floors.
- The Petitioners had incurred significant expenditure: the Municipal Corporation did not dispute that Rs. 59.51 Crores had been incurred on basement, ground and up to four upper floors, whereas the total civil cost for a ground plus 13 floors parking lot was estimated at Rs. 167 Crores. These incurred expenses show substantial progress.
- Foundations and construction proceeded on the basis of permissions for a ground plus 13 floors parking lot; the Petitioners were thus entitled to protection under section 51 and the impugned order should be set aside.
Municipal Corporation's Arguments
- The DCR was amended in 2008 to permit developer-constructed public parking lots with incentive FSI; on 22 June 2011 a circular added further conditions limiting area and height to three basements, ground and four upper floors, and caps on permissible area per parking space.
- In other petitions, the Corporation stated the circular would not be applied to those petitioners and that the Corporation would seek a modification of the DCR; a draft notification was published on 19 March 2012 proposing the modified regime.
- The object of the proposed modification is to ensure parking amenities are actually used by the public and to prevent developers from building tall parking towers that may remain underused; the AMC, after considering facts, reasonably concluded only part of the work had been carried out and could consider the proposed DCR amendment (draft notification) in exercising its powers under section 51.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Corporation of Calcutta v. Raj Kumar Narsing Pratap Singh Deo, AIR 1954 Calcutta 20 | Provided guidance on the meaning of "substantial" works — that "substantial" means alteration or improvement that is not illusory or nominal and must be assessed relatively by factors such as floor area or value of structures; no clear universal definition is possible. | The Court cited the decision as guidance that the determination of whether works have "substantially progressed" is relative and fact-specific; the opinion relied on that approach and declined to lay down an exhaustive definition, stating the matter must be assessed on the facts of each case. |
Court's Reasoning and Analysis
The Court analyzed the language and purpose of section 51 of the Maharashtra Regional and Town Planning Act, 1966 and its proviso. Section 51 empowers a planning authority to revoke or modify a permission to develop if expedient in light of a development plan (prepared or under preparation). The proviso to subsection (1), and specifically Clause (a), protects operations that have already been carried out and prevents passing an order after operations have "substantially progressed" or been completed.
The Court observed that Clause (a) contains two distinct protections: (1) an absolute protection for operations "previously carried out" and (2) an additional prohibition on making orders after operations have "substantially progressed" or been completed. The Court reasoned that the phrase "substantially progressed" cannot be equated with completion; if they were the same, the words would be redundant. Thus the legal test to be applied by the authority is whether operations have "substantially progressed" as distinct from being "substantially complete".
The Court found that the AMC misapplied the statutory test by asking whether the work was "substantially complete on site or otherwise" rather than whether the operations had "substantially progressed." Because the project was undisputedly not complete, the relevant inquiry (and statutory protection) was whether operations had substantially progressed as of the relevant date.
The Court then examined the factual findings recorded in the AMC's order. The AMC itself stated that, by 27 December 2011, work up to the fourth floor had been partially completed and that about 50% of the area had construction "beyond the stage which can be termed substantial." The AMC's operative order acknowledged substantial construction on the core part of the plot and permitted the already executed construction to stand while limiting the remainder to ground plus four floors.
On the basis of that factual material, and taking into account the Petitioners' pleaded cost figures (Rs. 59.51 Crores already incurred against an estimated Rs. 167 Crores for the full thirteen upper floors), the Court concluded that the operations had, in fact, substantially progressed as of the date of the show cause notice. The Court also observed that the draft notification of 19 March 2012 (proposed DCR amendment) itself recognized an exception for developments "which have progressed substantially" at the time of the amendment, reinforcing that such projects are to be treated differently.
The Court emphasized that it was not necessary to formulate an exhaustive definition of "substantially progressed"; the question is inherently fact-specific and must be decided on the record in each case. It cited the Calcutta High Court decision as guidance for that relative, contextual approach.
Because the AMC's own findings acknowledged substantial progress and yet the AMC imposed limitations inconsistent with the statutory protection in Clause (a) of the proviso to section 51, the AMC applied the wrong legal test and its order was contrary to law.
Holding and Implications
Core Ruling: Rule made absolute; the impugned order of the Additional Municipal Commissioner is quashed and set aside.
The Court quashed the part of the AMC order that restricted the Petitioners to a ground floor and four upper floors in deviation from the earlier permission. The stop work notice issued pursuant to the show cause notice dated 29 November 2011 was also quashed and set aside to the extent it was inconsistent with the Court's finding. The Rule was made absolute and there was no order as to costs.
Implications for the parties: the Petitioners obtain relief from the AMC's restrictive direction and the related stop work direction; the AMC's order is set aside. The Court did not lay down a universal definition of "substantially progressed" and expressly noted that whether work has substantially progressed must be determined on the facts of each case. Thus no broad new rule of general application was definitively established beyond the Court's interpretation that the AMC applied the wrong test in this instance.
Rule made absolute.
Dr. D.Y Chandrachud, J.:— Rule; with the consent of the Counsel for the parties returnable forthwith. With the consent of the Counsel and at their request, the Petition is taken up for hearing and final disposal.
2. The First Petitioner is the owner of a plot of land bearing Final Plot No. 46 of Town Planning Scheme-III situated at N. Kelkar Road, Shivaji Park, Mumbai. The First Petitioner is developing a highrise Information Technology Park and Residential and Public Parking Building. The development comprises of three level basements for captive parking and three wings. Wing-A consists of a ground floor and seven upper floors for shops and a restaurant; Wing-B consists of a ground floor and 48 upper floors for office units; and Wing-C consists of a ground floor and 32 upper floors. The dispute in the present case relates to Wing-C. Wing-C envisages municipal public parking on the ground floor and 14 upper floors and residential premises on eighteen floors above the parking facility.
3. The Municipal Corporation of Greater Mumbai sanctioned plans for Wings-A, B and C and issued an IOD on 15 February, 2006. The Union Ministry of Environment and Forests issued an Environmental Clearance for the development of a commercial building on 22 August 2006. A Commencement Certificate was issued by the Municipal Corporation on 13 September, 2006. Insofar as is material to the present controversy, a commencement certificate has been issued up to the fourteenth floor for Wing-C. Subsequently, the IOD was amended on 23 April, 2008 and 2 September, 2009. The Joint Commissioner of Police (Traffic) issued an NOC on 11 December, 2009 for the development of a multi-storeyed public parking lot. The State Government gave its in-principle approval on 2 June, 2010 for the construction of a multi-storeyed public parking lot on the land under Regulation 33(24) of the Development Control Regulations for Greater Mumbai, 1991. The Municipal Corporation issued a Letter of Intent on 27 July, 2010.
4. On 4 March, 2011 the State Government directed the Municipal Commissioner to send a proposal for amending Development Control Regulation 33(24) so as to limit the height of parking towers to four floors and to revoke all sanctioned proposals where commencement certificates had not been issued. The Municipal Corporation thereafter sought to incorporate new conditions in subrule (iv) of Regulation 33(24) of the Development Control Regulations inter alia to limit the height of a public parking amenity to the ground floor and four upper floors and two basements. The Corporation also sought to provide a cap on the built up area for every parking space. On 22 June, 2011, a circular was issued by the Municipal Corporation for prescribing conditions under Clause (iv) of DCR 33(24) and to stipulate that all proposals for public parking lots shall be considered subject to those conditions. The new conditions sought to limit the height of public parking to a ground and four upper floors and two basements and laid down conditions in regard to the payment of premium and a cap on the built up area per parking space.
5. On 29 November, 2011, a notice to show cause was issued to the Petitioners under section 51 of the Maharashtra Regional and Town Planning Act, 1966 calling upon them to explain as to why the commencement certificate which was issued on 30 October, 2010 should not be revoked. The notice to show cause inter alia relied upon the Circular dated 22 June, 2011. The Petitioners submitted their reply to the notice on 14 December, 2011. On 22 December, 2011, a stop work notice was issued to the Petitioners by which they were directed to restrict the work of the public parking lot to the fourth floor instead of the thirteenth floor.
6. On 27 April, 2012 an order has been passed by the Additional Municipal Commissioner. The order considered the status of the construction work as on 30 November, 2011 namely, immediately upon the issuance of a notice under section 51 of the Act. The Additional Municipal Commissioner addressed himself to a determination of whether “work is substantially completed on site or otherwise for the purpose of section 51”. On that issue, the Additional Municipal Commissioner held that in about fifty percent of the area, construction has progressed as on 27 December, 2011 “beyond the stage which can be termed substantial”. The Additional Municipal Commissioner found that it is possible to construct a public parking lot consisting of a ground floor and four upper floors on the portion where no substantial construction is done without substantial changes in the structure already constructed. The final order which is passed was in the following terms:
“As there is a substantial construction on core part of the plot, PPL done in this part shall be allowed to the extent of already executed construction as per report dated 27-12-2011. In the remaining portion of the plot, where there is no substantial construction, PPL shall be limited to G + 4, Developer is to be asked to modify his plans in consonance with modified DCR.”
7. Counsel appearing on behalf of the Petitioners submits that:
(i) The impugned order of the Additional Municipal Commissioner proceeds on an erroneous construction of the provisions of section 51 to the effect that work which has been “substantially completed” would fall within the purview of the provision. Section 51, it was submitted, inter alia protects operations that have “substantially progressed” on the date of an order revoking or modifying permission to develop. However, no such order shall affect such of the operations as have been previously carried out; or shall be passed after these operations have “substantially progressed” or have been completed.
(ii) As a matter of fact, the Additional Municipal Commissioner found that a substantial part of the construction has been completed on the core portion. Having regard to the finding of fact which has been arrived by the Additional Municipal Commissioner, it is impermissible to direct the Petitioners to restrict the work to the construction of a public parking lot comprising of only a ground floor and four upper floors;
(iii) The Municipal Corporation has, in its affidavit in reply, not disputed the factual position that the total cost incurred by the Petitioners for the construction of the basement and a ground floor and four upper floors upto the relevant date was Rs. 59.51 Crores. The civil cost of construction of a public parking lot of a ground floor and thirteen floors including the cost of construction of the basement was estimated to be Rs. 167 Crores. The expenses which have already been incurred cannot be regarded as being insignificant and would establish that the work had, in fact, substantially progressed.
(iv) The construction of a foundation has proceeded on the basis of the permission that was granted by the Municipal Corporation for construction of a public parking lot of a ground floor and thirteen floors together with the basement. In these circumstances, the Petitioners were entitled to the protection that is accorded by section 51 and the impugned order would have to be set aside.
8. Counsel appearing on behalf of the Municipal Corporation submits that in 2008, the Development Control Regulations were amended to provide for public parking lots to be constructed by developers. In consideration of the investments to be undertaken by developers, a provision was made for an incentive FSI. On 22 June, 2011 a circular was issued by the Municipal Corporation adding certain conditions for the grant of permission to construct public parking lots. The Municipal Corporation inter alia sought to restrict the permissible area and height to three basements, a ground floor and four upper floors. In Petitions which were filed before this Court under Article 226 of the Constitution, the Municipal Corporation made a statement before the Court to the effect that the circular would not be applied to the Petitioners in those petitions and the Corporation would move the State Government for an appropriate modification of the Development Control Regulations. In pursuance thereof, a draft notification was published on 19 March, 2012. Counsel submitted that the object of the proposed modification is to ensure that public parking lots would have a height that would ensure that the amenity is actually used by the members of public. Allowing construction of parking facilities beyond a certain height would be self-defeating. In the present case, it was urged that the Additional Municipal Commissioner had, upon due consideration of the facts, come to the conclusion that only a part of the work of the project had been carried out by the Petitioners and he was, therefore, justified in taking into consideration the proposed change sought to be made in the Development Control Regulations by the draft as contained in the Notification dated 19 March, 2012.
9. section 51 of the Maharashtra Regional and Town Planning Act, 1966 confers power on the planning authority to revoke or modify a permission for development where the authority considers that it is expedient to do so, having regard to the development plan prepared or under preparation. The proviso to sub-section (1) of section 51 is as follows:
“51. (1) If it appears to a Planning Authority that it is expedient, having regard to the Development plan prepared or under preparation that any permission to develop land granted [for deemed to be granted] under this Act or any other law, should be revoked or modified, the Planning Authority may, after giving the person concerned an opportunity of being heard against such revocation or modification, by order, revoke or modify the permission to such extent as appears to it to be necessary:
Provided that
(a) where the development relates to the carrying out of any building or other operation, no such order shall affect such of the operations as have been previously carried out; or shall be passed after these operations have substantially progressed or have been completed;
(b) where the development relates to a change of use of land, no such order shall be passed at any time after the change has taken place.”
This is a provision made in the interest of preserving the sanctity of a development plan. The Act refers specifically not only to a Development Plan which has been prepared but also to that which is under preparation. The intent is to ensure that a development which would impede or be detrimental to the realisation of the purposes of a development plan that is already prepared, or even one that is under preparation should be regulated. This is how sub-section (1) empowers the planning authority to modify or revoke a planning permission already granted to develop land. But the legislature was cognisant of the fact even before a permission is revoked or modified, planning permissions may have been acted upon and work may have commenced. To deal with such cases, the legislature has drawn a balance through the proviso.
10. Clause (a) of the proviso makes it clear that in a case where a building is being constructed or other operation is being carried on, an order of revocation or modification of a development permission shall not affect operations which have been previously carried out nor shall an order of revocation or modification be passed after these operations have substantially progressed or have been completed. Clause (b) deals with a situation where the development permission was for a change in the use of land and, acting on the permission, the change has taken place already.
11. Clause (a) of the proviso is in two parts. The first part of the provision protects those operations which have been previously carried out. The second part has the effect of imposing a restraint upon the passing of an order of revocation or modification where operations have either substantially progressed or have been completed. Since the second part refers to a situation where operations (i) have substantially progressed; or (ii) have been completed, the expression “substantially progressed” cannot be read to mean the same thing as the completion of operations. If the legislature intended both the phrases to mean the same thing, there was no reason to introduce a surplusage.
12. The Additional Municipal Commissioner, has in the present case, proceeded on the basis of a patently wrong appreciation of the underlying legal principles. The test which the Additional Municipal Commissioner applied is: whether the work is substantially complete on site or otherwise on the relevant date for the purpose of applying the provisions of section 51. The Additional Municipal Commissioner was required to determine as to whether the operations have substantially progressed, since there is no dispute about the fact that the project has not been completed.
13. The impugned order of the Additional Municipal Commissioner takes note of the fact that on 27 December, 2011 the work of the parking lot wing upto the fourth floor had been partially completed. The order takes note of the fact that in about 50% of the area construction has progressed as on 27 December,2011, “beyond a stage which can be termed substantial”. As a matter of fact, even the operative part of the order takes due note of the position that there is a substantial construction on the core part of the plot. In view of this finding, it is quite evident that the condition which has been laid down in Clause (a) of the proviso to section 51 is met because the order itself contains an acknowledgement of the fact that operations had substantially progressed.
14. In the Petition as amended, a valuation has been made of the estimated cost of Rs. 167 Crores of constructing a public parking lot consisting of a ground floor and 13 upper floors. The Petitioners have stated that they have incurred a total cost of Rs. 59.51 Crores towards construction of a ground floor and four floors including the basement. This aspect has not been dealt with in the affidavit in reply.
15. Looked at from either perspective, it is clear that on the basis of the material which weighed with the Additional Municipal Commissioner a substantial progress of work has been achieved and that the operation had substantially progressed on the date on which a notice was issued to the Petitioners to show cause under section 51 of the Act.
16. Development Control Regulation 33(24) provided for the governing conditions for the grant of permissions for the development of public parking lots. The Municipal Corporation decided to modify DCR 33(24) along the lines of an administrative circular dated 22 June, 2011. The Corporation may be justified in the reasons for which it proposed the modification. The Corporation has submitted that in the absence of height restrictions, it would be open to a developer to construct a building for housing a parking lot in the form of a tower which when constructed may not be fully utilised by the public. Since incentive FSI is to be conferred by the Municipal Corporation upon the developer, the proposed modification seeks to put in place a cap on the height of the parking lot and on the maximum area that would be used for the purpose of parking motor vehicles. A draft notification was issued by the Government of Maharashtra in the Urban Development Department on 19 March, 2012. The draft envisaged inter alia that the height of the public parking amenity would be limited to a ground floor plus four floors and three basements. Among the other restrictions, the draft notification imposes a cap, an outer limit on the maximum built up area per parking space. Significantly, the concluding part of the notification states that all the developments which have been given permission in accordance with the D.C Regulations of 20 October, 2008, “except those which have progressed substantially”, will have to follow the regime of the amended D.C Regulation 33(24) and would be governed by the payment of premium to the extent stipulated in the notification. Hence, consistent with the provisions of section 51, the draft notification also recognises that there may be projects which have progressed substantially before the new norms have been published, after requisite sanctions were granted and substantial progress was made in the work of development. The project in the present case would on the basis of the material on record meet that description.
17. For the purposes of the present case, it is not necessary for the Court to render an exhaustive description of when a work of development can be regarded as having substantially progressed. Ultimately whether a work of development has substantially progressed must be dealt with on the basis of the facts of each individual case and no general principle can be laid down in that regard. Perhaps some guidance can be derived from the judgment of a Division Bench of the Calcutta High Court in Corporation of Calcutta v. Raj Kumar Narsing Pratap Singh Deo, AIR 1954 Calcutta 20:
“Substantial” refers to the fact that the alteration and improvement had neither been illusory nor inconsiderable; it was not merely nominal or flimsy but it was an alteration and improvement which in comparison with the structures already standing can be deemed to materially alter the previous dispositions of the property, or the conveniences which were available. It is not possible to lay down any clear and specific definition of the word “substantial”. It must be a relative one. Sometimes, the comparison of the floor area, sometimes the value of the structures, and on other occasions other considerations may weigh with the authority for determining whether in the particular facts of a case, the alterations and improvements can or should be deemed to be substantial ones.”
18. In the facts of this case, the admitted position as accepted in the order of the Additional Municipal Commissioner indicates that the work of development had substantially progressed by the time a notice to show cause was issued under section 51 of the M.R and T.P Act, 1966. The impugned order passed by the Additional Municipal Commissioner restricting the Petitioners to a height of a ground floor and four upper floors in deviation of the permission granted earlier is therefore contrary to law. Hence, the impugned order would have to be quashed and set aside and is accordingly set aside. The stop work notice which has been issued to the Petitioners on the basis of the notice to show cause dated 29 November, 2011 is to that extent quashed and set aside. Rule is made absolute in these terms. There shall be no order as to costs.
Rule made absolute.