Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Coastal Marine Const... v. Oil And Natural Gas ...

Bombay High Court
Feb 18, 2010
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Court Opinion

Factual and Procedural Background

The petition concerns a writ petition in which the petitioner originally sought multiple forms of relief relating to a public tender process (including correction of Bid Evaluation Criteria, injunctions against rejection of the petitioner's Technical Bid, restraining opening of Price Bids and award of contract). The petitioner, however, confined the claim before the Court to a single question: the validity of the respondents' decision holding the petitioner technically disqualified for award of the contract.

Respondent No. 1 had invited tenders for geophysical survey (Part I) and geotechnical investigation (Part II) in deep-water locations on the East Coast of India. The Bid Evaluation Criteria (BEC) required bidders (or their technical collaborators/partners) to have specified experience, including at least two years' experience as on the opening date of the tender and execution of at least one contract of a specified nature in the last ten years, with minimum water depth requirements (minimum 850 metres for certain tasks).

The petitioner submitted a bid with technical collaborators: Williamson and Associates (USA) for Part I and Carmacoring S.r.l. (Italy) for Part II. The petitioner supplied various documents (completion certificates, project reports, company profiles, internal reports, collaboration agreements and certificates) in support of its collaborators' experience. The respondent-corporation's Tender Evaluation Committee later found the documentation insufficient to meet the BEC and held the petitioner technically disqualified for both Part I and Part II work.

The petitioner alleged that the re-evaluation and disqualification were tainted by ulterior motive, bias involving a Corporation officer (Ashok Sharma) and by disclosure of information to a competitor (TDI Brooks). The petitioner relied on precedent about the "level playing field." The respondents defended the evaluation as a reasoned assessment by a Tender Evaluation Committee of senior officers and invoked authorities limiting judicial interference in tender decisions.

The Court heard senior counsel for parties, reviewed the documents, the reasons given by the respondents for rejection of the petitioner's submissions, and relevant case law, and delivered judgment dismissing the petition while extending an interim order until 4-3-2010 on stated conditions.

Legal Issues Presented

  1. Whether the decision of respondent No. 1 to hold the petitioner technically disqualified was vitiated by illegality, irrationality (Wednesbury unreasonableness) or procedural impropriety (i.e., whether judicial review can sustain interference with that decision-making process).
  2. Whether the documents and evidence produced by the petitioner established that its technical collaborators satisfied the Bid Evaluation Criteria (two years' experience as on opening date and execution of at least one contract of the specified nature within ten years).
  3. Whether allegations of mala fide, bias or improper disclosure (in particular involving Ashok Sharma and alleged supply of information to TDI Brooks) were substantiated so as to vitiate the respondents' decision-making process.
  4. Whether the doctrine of a "level playing field" required any different outcome in this case (i.e., whether equally placed bidders were denied fair treatment).

Arguments of the Parties

Petitioner's Arguments

  • The petitioner contended that voluminous documents submitted in support of the collaborators' experience were disregarded by respondents on flimsy grounds and that those documents satisfied the BEC clauses (2.1(a)(1) and (ii) or 2.1(b)).
  • For Part I (Geophysical Survey) the petitioner relied on: a work completion certificate from TYCO Telecommunications (Annexure 2), a portion of a Manus Basin geophysical survey report showing Williamson and Associates' involvement (Annexure 3), an article based on USGS material describing a deep-water Williamson survey (Annexure 4), and a list of deep-water surveys (Annexure 5).
  • For Part II (Geo Technical Investigation) the petitioner relied on Carmacoring documents: company profile, collaboration agreements, daily reports, certificates from project clients (Impresub, ISMAR, Gas S.r.l), project reports and a completion certificate, to show Carmacoring met BEC requirements.
  • The petitioner alleged an ulterior motive behind re-evaluation and disqualification, pointing to differences with an officer (Ashok Sharma) and alleging that TDI Brooks obtained secret information leading to re-evaluation. It relied on the doctrine of a "level playing field" (Reliance Energy) to stress fairness among bidders.

Respondents' Arguments

  • The respondents maintained that the documents submitted by the petitioner did not, on their face, establish the requisite two years' experience as on the tender opening date, nor did they establish execution of the requisite type of contract with satisfactory completion.
  • The Tender Evaluation Committee, composed of senior officers, carefully applied uniform standards to all bidders and found the petitioner's documents lacking (e.g., no client corroborated completion certificates, some documents dated outside the ten-year window, internal reports or supplier-role evidence rather than proof of performance).
  • The respondents argued the court should not re-appraise the merits of the tender decision or substitute its own view, relying on precedents that judicial interference in tender evaluations is limited and focused on the decision-making process rather than the substance of administrative expertise.
  • As to allegations about Ashok Sharma and leakage to TDI Brooks, the respondents argued that Sharma was not on the Tender Committee, the petitioner did not implead him or provide cogent particulars, and information about the petitioner's collaborators was available publicly on their websites—therefore the leakage allegation lacked substance.
  • The respondents relied on authorities (including Nagar Nigam v. AL Faheem, Electrical Mfg. Co. v. Power Grid) to support the position that the authority may require subjective satisfaction about satisfactory completion and that mere documentary material insufficient to establish completion may be rejected.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Reliance Energy Ltd. v. Maharashtra State Road Development Corpn. Ltd., (2007) 8 SCC 1 The doctrine of a "level playing field" — equally placed competitors must be allowed to bid so as to subserve larger public interest. The Court noted the relevance of level playing field but observed it applies only to equally placed bidders; it held that the doctrine does not require treating qualified and unqualified bidders alike and did not require interference with the respondents' decision here.
Nagar Nigam v. AL Faheem Meat Exports (P) Ltd., (2006) 13 SCC 382 Support for limited judicial interference in tender decisions; indicates court should not ordinarily interfere with tender terms. The respondents invoked this line of authority to support non-interference; the Court accepted that judicial review is restrained and focuses on decision-making process rather than reappraisal of tender terms.
Electrical Mfg. Co. Ltd. v. Power Grid Corpn. of India Ltd., (2009) 4 SCC 87 Interpretation of "satisfactory completion" — mere execution of works is insufficient unless the works are shown to have been satisfactorily completed. The Court relied on this principle to support the respondents' insistence on client corroboration, completion certificates and demonstrable satisfactory completion; it found respondents' requirement reasonable when documents did not show satisfactory completion.
Chandra Prakash Singh v. Chairman, P.G Bank, 2008 (3) SCALE 289 Allegations of bias or mala fide require cogent evidence and proper pleadings; courts will not undertake fishing inquiries in absence of particulars or impleaded parties. The Court held that petitioner had failed to implead the officer named (Ashok Sharma) or provide particulars or cogent material; therefore these allegations could not be examined.
Tata Cellular v. Union of India, (1994) 6 SCC 651 Defines scope of judicial review of administrative action: illegality, irrationality (Wednesbury), procedural impropriety; court reviews process and legality, not merits. The Court framed its review within these parameters, concentrating on whether the decision-making process was vitiated by the listed defects and reminding that sufficiency of material is generally beyond review.
State of Punjab v. V.K. Khanna (cited within Chandra Prakash Singh) Fairness in administrative action depends on facts and circumstances; concept linked to reasonableness; allegations of bias must be supported and not mere apprehension. Cited in context to explain the high threshold for proving bias and mala fide; supported the Court's approach to dismiss unparticularized allegations of bias.
Dhampur Sugar (Kashipur) Ltd. v. State of Uttaranchal (cited) Allegations of mala fide are serious, raise questions of fact, and require full particulars and materials; bare assertions are insufficient. Used to reinforce that the petitioner bore a heavy burden to prove mala fide and that the petition lacked requisite particulars and materials to warrant a probing inquiry.

Court's Reasoning and Analysis

The Court proceeded on the foundational principle that judicial review of administrative tender decisions is limited to examining the decision-making process for illegality, irrationality (Wednesbury unreasonableness) or procedural impropriety (Tata Cellular). The Court emphasized it must not act as an appellate body re-evaluating the merits or sufficiency of the material that the administrative authority considered.

The Court examined the specific reasons recorded by the respondent-corporation in relation to the two technical collaborators:

  • Part I — Williamson and Associates: The respondents found the corporate description to be self-serving without supporting client corroboration; a completion certificate/report regarding contract No. 144695 with Tyco was rejected as not meeting the two-year experience requirement; an older USGS report fell outside the ten-year window required by the BEC; overall, no contract/work order/completion certificate from clients established satisfactory completion as required.
  • Part II — Carmacoring S.r.l: The respondents concluded that the materials showed Carmacoring largely operated as supplier of instruments and technicians rather than as a contractor who had executed and satisfactorily completed the type of geotechnical work required by the BEC; completion certificates relied upon lacked reference to work orders or contracts; certain reports did not meet the two-year or ten-year timing requirements; internal reports and supplier-role documents did not establish satisfactory completion.

The Court considered the petitioner's allegations of bias and improper disclosure. It found these allegations inadequately pleaded and supported: (a) the officer alleged to have instigated disqualification (Ashok Sharma) was not impleaded as a party nor were cogent particulars provided, and he was not a member of the Tender Committee; (b) material filed by respondents showed collaborator information was available on the collaborators' websites, lending substance to the respondents' explanation for how a competitor obtained information; and (c) precedents require cogent evidence before a court will entertain allegations of mala fide or bias.

Applying Wednesbury reasonableness and relevant precedents (notably Electrical Mfg. Co.), the Court concluded that the respondents' reasons—that the documents did not establish satisfactory completion and did not meet temporal or documentary requirements of the BEC—were not irrational or unreasonable. The Court specifically observed that the standards applied to the petitioner were not different from those applied to other bidders and that the authority's view as to sufficiency of proof of completion was within its discretion and expertise.

Consequently, within the limited scope of judicial review, the Court found no fault in the decision-making process that would warrant interference under Article 226.

Finally, although dismissing the petition, the Court granted a limited, conditional extension of an earlier interim order until 4-3-2010, requiring the petitioner to give 48 hours' notice before seeking any interim orders—balancing the petitioner's desire to approach the Supreme Court with the respondents' concern about project timelines.

Holding and Implications

Holding: The writ petition is DISMISSED.

Implications:

  • Direct effect: The respondents' decision holding the petitioner technically disqualified stands; the petitioner's challenge to that disqualification is rejected by this Court on the ground that the respondents' decision-making process was not tainted by illegality, irrationality or procedural impropriety based on the material before the Court.
  • Bias and disclosure allegations: The Court declined to examine allegations regarding Ashok Sharma and alleged secret disclosure to TDI Brooks because the petitioner did not implead the person nor support the allegations with cogent particulars; the Court accepted the respondents' explanation that collaborator information was publicly available.
  • Precedential scope: The Court applied established principles of judicial review and tender law (including Wednesbury reasonableness and the need to prove "satisfactory completion"). The opinion does not purport to create a new legal precedent beyond applying those principles to the facts; it affirms that a level playing field principle does not compel treating unqualified bidders as qualified.
  • Interim relief: The Court extended the interim order until 4-3-2010 on condition that the petitioner provide 48 hours' notice before seeking any interim relief, recognizing both the petitioner's desire to approach the Supreme Court and the respondent's concern about project timing.

Order accordingly.

Show all summary ...

B.R Gavai, J.:— Though this Writ Petition has been filed seeking various reliefs, including the ones, directing the respondents to correct the terms of the Bid Evaluation Criteria, injuncting the respondents from rejecting the Technical Bid submitted by the petitioner, an injunction restraining the respondents from opening the Price Bids of various bidders and also an injunction restraining the respondents from proceeding with the award of the contract, the petitioner has restricted the claim in the petition only to the decision of the respondents in holding the petitioner to be technically disqualified for award of the contract in question.

2. The respondent No. 1 had invited tenders for hiring of services for geophysical survey and geotechnical surveys in Vashishtha, S1 and Manik fields in deep water locations of East Coast of India. The main condition of the tender document around which the dispute in the present petition revolves is as under:—

“A) Technical Criteria

The following vital technical conditions should be strictly complied:

1.0 Eligibility and experience of the bidder:

1.1(a) i) The bidder by himself should have minimum two years experience as on opening date of tender on the following —

ii) The Bidder should have executed at least one number of contracts of following nature in last ten years —

For Part-I: Geophysical Survey

a) Bathymetry.

b) Sea Bed Survey

c) Magnetometer Survey

d) Sub bottom profiler (seismic) Sparker/Boomer

In deep water minimum 850 Mtrs. or above.

For Part II: Geo Technical Investigation

Collection and Analysis of cores in deep water minimum 850 Mtrs. or above.

1.1(b) In case the bidder is an Indian company/Indian Joint venture company, the Indian company/Indian Joint venture company or its technical collaborator/joint venture partner should meet the criteria laid down above.

1.1(c) Or bidder should be a 100% subsidiary company of the parent company which itself meets the experience and financial capability criteria as stipulated in the BEC.

1.2 In case the bidder is a consortium of companies, the following requirement should be satisfied by the bidder:

a) The members of the consortium collectively should satisfy the minimum experience requirement as per para 2.1(a) above.”

3. Though, according to the petitioner, since in the notice inviting tenders there is a provision regarding pre-bid conference wherein exceptions/deviations, if any, to Tender Terms, Conditions and Specifications were to be sorted out, the petitioner has perused the matter insofar as the requirement of executing the work in water having minimum depth of 850 mtrs. is concerned and, accordingly, a prayer to that effect was made in the petition. However, since the petitioner has submitted its bid after entering into a Technical Collaboration Agreement with Williamson and Associates, USA, and Carmacoring S.r.l, Italy, the petitioner has not agitated its grievance regarding the validity of the said condition and has restricted the claim in the present petition only insofar as their grievance regarding not finding the petitioner's collaborators' technical experience sufficient enough to satisfy the condition regarding technical qualification.

4. We have heard Mr. Rajadhyaksha, the learned senior counsel appearing on behalf of the petitioner, and Mr. Dada, the learned senior counsel appearing on behalf of the respondent No. 1 at length.

5. Mr. Rajadhyaksha, the learned counsel appearing on behalf of the petitioner, submits that though voluminous documents were submitted by the petitioner in support of the experience and eligibility of their collaborators, the said documents are not taken into consideration on a flimsy and unviable grounds. He submits that even according to the respondents, the petitioner could have independently submitted its bid for part of the work i.e Geophysical Survey or Geo Technical Investigation independently. He submits that insofar as Part I of the work i.e Geophysical Survey is concerned, in response to the query made by the respondent No. 1, the petitioner was required to submit the completion certificate against contract No. 144695 between Tyco Telecommunications (US) Inc. and Williamson and Associates Inc. or work order/contract, report/completion certificate against any other project listed in the bid document and executed by the bidder or his technical collaborator, to conform with Bid evaluation criterion (bec) clause 2.1(a)(i) of Part I. He submitted that in response to the said query, the petitioner had submitted following documents:—

“i. Work Completion Certificate issued by TYCO Telecommunication (US) INC having their address at 412 Mount Kemble Avenue, Morrisstown, NJ 07960 which is placed in Annexure 2 to Petitioners clarification letter referred to above.

ii. Copy of the report for the Manus Basin Geophysical Survey for Placer Dome Asia Pte Ltd. Portion of report has been high lighted for the sake of convenience to show the name of Williamson and Associates, Equipments used and to show water depth wherever necessary which is placed in Annexure-3 of Petitioners clarification letter referred to above.

iii. Copy of an article written by US Geological Survey personal which describes a deep water survey completed by Williamson in 1990. The article clearly states that Williamson completed the survey and it also states that it is based on a USGS report. The copy of article report is annexed hereto and marked Annexure-4 to Petitioners clarification letter referred to above.

iv. A list of survey containing the contracts details executed in deep water. The contract details in blue are the contracts executed in deep water as stated in the cover email dated 11th December 2009. Copy of both the lists attached, together with forwarding email message, hereto and mark Annexure-5 to Petitioners clarification letter referred to above.”

Mr. Rajadhyaksha submitted that a perusal of the aforesaid documents would reveal that the petitioner squarely satisfies the criteria laid down as per the Bid Evaluation Criteria clause 2.1(a)(1) and (ii) or 2.1(b).

6. Insofar as Part II of the work i.e Geo Technical Investigation is concerned, it is submitted that the petitioner had entered into collaboration with M/s Carmacoring srl, Italy, and following documents were submitted by the petitioner to establish that the said M/s Carmacoring complied with the eligibility criteria:—

1. Project for Impresub

a) Carmacoring Company Profile mentions that Carmacoring carried out the geotechnical survey in the year 2006.

b) Collaboration Agreement between Car. Ma and Impresub.

c) Daily Report of the Project dated 13-4-2006.

d) Certificate dated 9-5-2006 from Impresub.

e) Carmacoring Report of the Geotechnical Survey carried out.

2. Project for ISMAR

a) Carmacoring Company Profile mentioning that Carmacoring carried out the geological survey in the year 2008.

b) Report of the Project.

c) Certificate dated 30-11-2009 from ISMAR.

3. Project for Gas S.r 1.

a) Certificate dated 5-10-2007 issued by the Managing Director of Gas S.r.l establishing that Carmacoring carried out coring.

The learned counsel submits that the aforesaid documents would clearly establish that the petitioner's collaborator M/s Carmacoring S.r.l has possessed the necessary qualification. He submits that refusal to take into consideration the aforesaid documents has resulted in arbitrariness thereby vitiating action of the respondents in holding the petitioner to be disqualified.

7. Mr. Rajadhyaksha further submitted that though initially the petitioner was found to be technically qualified, subsequently, with ulterior motive, the petitioner has been held to be disqualified.

8. An attempt has been made on behalf of the petitioner to submit that the petitioner who was already executing some works for the respondent-Corporation, had differences with one Ashok Sharma, who is an Officer in the Corporation and that the decision to hold the petitioner disqualified is at the instance of the said Sharma. It is further submitted that there was an integrity clause in the tender document and as per the integrity clause, the respondent-Corporation cannot disclose the details submitted to it, to other bidders. It is further submitted that one of the competitors of the petitioner, viz., TDI Brooks has been supplied secret information by somebody from the Corporation. It is submitted that TDI Brooks has written a letter dated 20-11-2009 to the respondent-Corporation and only after such a letter was written, the matter was re-evaluated to hold that the petitioner is disqualified.

9. The learned counsel relied on the judgment of the Apex Court in Reliance Energy Ltd. v. Maharashtra State Road Development Corpn., Ltd. (2007) 8 SCC 1 in support of the submission that the doctrine of “level playing field” is an important doctrine and that equally placed bidders are required to be allowed to bid so as to subserve the larger public interest.

10. Mr. Dada, the learned senior counsel appearing on behalf of the respondent No. 1, on the contrary, submits that the documents which were relied upon by the petitioner in support of the technical qualification show that the experience of the petitioner's collaborators has been found to be not in conformity with the requirements of the respondents. He submits that the documents were not of such a nature which would establish beyond doubt that the petitioner's collaborators had two years' experience as on the opening date of the tender and that they had executed at least one contract of the nature mentioned in the tender document. It is submitted that the respondents by applying the similar standards had evaluated the documents submitted by each of the bidders and after careful evaluation thereof by the Tender Evaluation Committee which consisted of senior Officers of the respondent-Corporation, it was found that the documents submitted did not satisfy the requirements of the technical qualification. The learned counsel submits that this Court is not expected to interfere with the conditions mentioned in the tender inviting notice. In support of this submission, the learned counsel relied on the judgment of the Apex Court in Nagar Nigam v. AL Faheem Meat Exports (P) Ltd., (2006) 13 SCC 382. The learned counsel further submitted that unless the respondents come to a subjective satisfaction that the works in question were satisfactorily completed, on the basis of the documents submitted by the party, it is well within its rights to hold that the party has not satisfied the condition regrading technical qualification. Reliance is placed in this respect on the judgment of the Apex Court in Electrical Mfg. Co. Ltd. v. Power Grid Corpn. of India Ltd., (2009) 4 SCC 87.

11. Insofar as the allegation regarding Ashok Sharma is concerned, the learned counsel submitted that neither Ashok Sharma has been made a party-respondent nor are there any specific allegations attributed to him in the petition. He, therefore, submitted that in the absence of such pleadings, it will not be permissible for this Court to go into the allegations in that respect. Reliance is placed on the judgment of the Apex Court in Chandra Prakash Singh v. Chairman, P.G Bank, 2008 (3) SCALE 289. Insofar as the allegation regarding the TDI Brooks and Fugro is concerned, it is submitted that the information regarding the technical collaborators of the petitioner was very much available on their web site and, as such, the letter written by the said TDI Brooks was on the basis of the information received on the web site of the petitioner's collaborators. It is, therefore, submitted that the allegation in this respect are without substance. The learned counsel further submitted that this Court is concerned with the decision making process and not the ultimate decision and unless it is found that the decision making process is vitiated on any of the grounds on which judicial review of an administrative action is permissible, no inference would be warranted by this Court. Reliance is placed, in this respect, on the judgment of “the Apex Court in the case of Tata Cellular v. Union Of India., (1994) 6 SCC 651.

12. At the outset, we may observe that insofar as the allegations made by the petitioner regarding the impugned action being at the behest of Ashok Sharma and the same being made to favour TDI Brooks is concerned, it will not be permissible for this Court to go into the said allegations. The Apex Court in Chandra Prakash Singh's case (supra) has observed thus:—

“15. In State of Punjab v. V.K Khanna's case (supra), this Court held that the concept of fairness in administrative action has been the subject-matter of considerable judicial debate but there is total unanimity on the basic element of the concept to the effect that the same is dependent upon the facts and circumstances of each matter pending scrutiny before the Court and no strait-jacket formula can be evolved therefor. Further it is stated that as a matter of fact, fairness is synonymous with reasonableness and on the issue of ascertainment of meaning of reasonableness, common English parlance referred to as what is in contemplation of an ordinary man of prudence similarly placed - it is the appreciation of this common man's perception in its proper perspective which would prompt the Court to determine the situation as to whether the same is otherwise reasonable or not. Similarly, the existence of mala fide intent or biased attitude cannot be put on a strait-jacket formula but depends upon facts and circumstances of each case. Further, it is said that whereas fairness is synonymous with reasonableness - bias stands included within the attributes and broader purview of the word “malice” which in common acceptation means and implies “spite” or “ill will”. Mere general statements will not be sufficient for the purposes of indication of ill will. There must be cogent evidence available on record to come to the conclusion as to whether, in fact, there was a bias or a mala fide move which resulted in the miscarriage of justice. It is also held that the test of bias is as to whether there is a mere apprehension of bias or there is a real danger of bias and it is on this score that the surrounding circumstances must and ought to be collated and necessary conclusion drawn therefrom. In the event, however, the conclusion is otherwise that there exists a real danger of bias, administrative action cannot be sustained. If on the other hand allegations pertain to rather fanciful apprehension in administrative action, question of declaring them to be unsustainable on the basis therefor, would not arise.

16. In Dhampur Sugar (Kashipur) Ltd. v. State of Uttaranchal and ors.'s case (supra), this Court dealing with the question of mala fide exercise of power, held as under:

“Allegations of mala fide are serious in nature and they essentially raise a question of fact. It is, therefore, necessary for the person making such allegations to supply full particulars in the petition. If sufficient averments and requisite materials are not on record, the Court would not make “fishing” or roving inquiry. Mere assertion, vague averment or bald statement is not enough to hold the action to be mala fide. It must be demonstrated by facts. Moreover, the burden of proving mala fide is on the person levelling such allegations and the burden is “very heavy.” In the present case, except alleging that the policy was altered by the Government to extend the benefit to IGL, no material whatsoever was placed on record by the appellant. It is, therefore, not possible to hold that the impugned action was mala fide or malicious.”

13. In the present case, it can clearly be seen that though the petitioner had number of opportunities, the petitioner has not impleaded said Ashok Sharma as party-respondent. Even otherwise, apart from making bald allegations, no particular allegation supported by any cogent material has been placed on record by the petitioner in this respect. In the absence of any such specific allegations supported by cogent evidence being brought on record and such party being made party-respondent, it will not be permissible for this Court to go into the said allegations. In any case, from the material placed on record, we find that said Ashok Sharma was not a member of the Tender Committee and the said Committee consisted of the following three senior Officers:—

“1. Shri P.K Dalai, GM(M), Head Marine Survey and Offctdg. HOW.

2. Shri A.K Srinivasan, GM (F and A).

3. Shri A.K Tewari, GM (MM)-Offctdg. Head MM.”

14. Insofar as the allegations regarding the secret information being supplied to M/s TDI Brooks is concerned, we find that the allegation in this respect is also without any substance. From the material on record which is annexed along with the affidavits filed by the respondents, it is clear that the information regarding the technical collaborators of the petitioner is very much available on the web site of the collaborators. The submission on behalf of the respondents, in this respect, that the information regarding the collaborators of the petitioner being received by the said TDI Brooks from the web site of the said collaborators, therefore, appears to be of substance. In that view of the matter, we are unable to accept the contention of the petitioner in this respect.

15. While examining the merits of the petitioner's case, we will have to remind ourselves that while judicially reviewing an administrative action, we are concerned with the decision making process of the administrative authority and not the ultimate decision. In the case of Tata Cellular (supra), the Apex Court has observed thus:—

“77. The duty of the Court is to confine itself to the question of legality. Its concern should be:

1. Whether a decision-making authority exceeded its powers?

2. Committed an error of law,

3. committed a breach of the rules of natural justice,

4. reached a decision which no reasonable tribunal would have reached or,

5. abused its powers.

Therefore, it is not for the Court to determine whether a particular policy or particular decision taken in the fulfilment of that policy is fair. It is only concerned with the manner in which those decisions have been taken. The extent of the duty to act fairly will vary from case to case. Shortly put, the grounds upon which an administrative action is subject to control by judicial review can be classified as under:

(i) Illegality: This means the decision-maker must understand correctly the law that regulates his decision-making power and must give effect to it.

(ii) Irrationality, namely, Wednesbury unreasonableness.

(iii) Procedural impropriety.”

After considering the various pronouncements of the Apex Court on the issue, the Apex Court has deduced the principles in paragraph 94, which are as under:—

“94. The principles deducible from the above are:

(1) The modern trend points to judicial restraint in administrative action.

(2) The Court does not sit as a Court of appeal but merely reviews the manner in which the decision was made.

(3) The Court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible.

(4) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts.

(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides.

(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure.”

16. We will have to, therefore, consider as to whether the action of the respondents is valid or not within the limited para-meters that are available, while reviewing the decision making process of the respondent-authority.

17. The limited scope, therefore, is as to whether the action of the respondents is vitiated by illegality, irrationality or impropriety. In this background, we will have to examine the reasons given by the respondent No. 1- Corporation while coming to the conclusion that the documents supplied by the petitioner do not satisfy the requirement of the technical qualification required for the work.

18. Insofar as the corporate description of M/s Williamson and Associates is concerned, the authority has found that the said document merely gives the company's perspective of its work without any supporting documentation. It has been found by the respondents that the said document did not establish that the said M/s Williamson and Associates had successfully completed the type of work which was required to qualify for the tender in question. Insofar as the document pertaining to contract No. 144695-TPE dated 8-10-2008 with Tyco Telecommunications dated 8-10-2008 is concerned, the petitioner has submitted a survey report and completion certificate dated 31-3-2009. However, the authority has found that the said work does not meet the requirement of the criterion of two years' experience as required under the bid document. Insofar as the reports submitted by the petitioner of Williamson and Associates dated 18-5-2005, it was not taken into consideration on the ground that the said report was the document prepared by Williamson and Associates themselves and there was no corroboration from the clients of Williamson and Associates regarding the said work being satisfactorily completed by Williamson and Associates. The report of the U.S Geological Survey which was relied upon by the petitioner was not taken into consideration as the said report was last modified on 4-4-1996 and, as such, it fell beyond the period of ten years as required under clause 2.1(a)(i). The respondent-authority has found that the petitioner has failed to produce any document in the nature of contract, work order and completion certificate from the clients of the said Williamson and Associates in support of their claim that they had experience as per the requirement of the tender document. As such, the respondent-authority has found that the petitioner had failed to establish that the petitioner was qualified insofar as Part I work i.e Geophysical Survey.

19. Insofar as Part II i.e Geo Technical Investigation is concerned, upon perusal of the documents submitted by the petitioner regarding the experience of M/s Carmacoring S.r.I working with ISMAR, it was found that the work done by M/s Carmacoring was merely supplying two technicians and instruments to ISMAR. It was further found that the work related to ISMAR does not fall within the requirement of two years' experience requirement of BEC. Insofar as the Collaboration Agreement is concerned, it was found that M/s Carmacoring were mere suppliers of equipment that was used in the project Makassar Strait in Indonesia. Insofar as the letter produced by the petitioner thanking Car. Ma of Angelo Magagnoli, it was found by the authority that the said letter does not bear out the nature of work done by Car. Ma and the authority has further found that if the said letter is read with the Collaboration Agreement, the inference that could be drawn would be that it was in the context of supplies of equipment made by Car. Ma. Insofar as the Internal Report prepared by M/s Carmacoring is concerned, it was found by the authority that this document is only an Internal Report and does not establish any experience of the category required by the BEC. Insofar as the company profile of M/s Carmacoring is concerned, the authority has found that the said company is a mere supplier of instruments and equipment for coring. The respondent-authority has relied on the following part of the said document in support of their finding in this respect:

“The technical department is supervised by Angelo Magagnoll, a former employee of CNR (Italian National Research Council) at the Marine Geology Institute in Bologna where he invented and patented some instruments which are currently on the market.”

The respondent-authority has further relied on the following part of the said document:—

“Carmacoring S.r.l provided the equipment (CP-20) and the technical personnel for IDMC Impressub S.r.l during the job performed for the client Chevron-Unocal.”

Upon entire perusal of this document, the authority has found that the work involved was supply of sampling instruments designed by Angelo Magagnoll and commercialised by Carmacoring. Insofar as the completion certificate relied on by the petitioner dated 5-10-2007 is concerned, it was found that the said letter had no reference to any work order or contract and, therefore, cannot be said to be proof of satisfactory completion of any of the work of the nature required under the tender document. The authority has further found that the petitioner had not submitted any document in support of the petitioner's claim that the said completion certificate was for completion of the job required as per the BEC and was carried out by M/s Carmacoring. Insofar as Hermes Cruise Report for ISMAR is concerned, it was found that the said document apart from not satisfying the two-year condition of the BEC does not establish that the company carried out the work required by the BEC. The authority has further found that no work order or contract in support of the said document was placed on record. Insofar as the certificate dated 30-11-2009 issued to the petitioner by ISMAR is concerned, the authority has found that the said document merely refers to mobilisation of personnel, equipment, handling system, spares on R.V Urania for the cruise called “Sassi 08” to carry out jumbo piston coring for sample collection. The authority has found that this document is not sufficient to establish that sample collection work was done by M/s Carmacoring. Insofar as the Collaboration Agreement for Impressub s.r.l and the Completion Certificate and the Daily Reports are concerned, the authority has found that the work was done by Car. Ma and not by M/s Carmacoring s.r.l who is the technical collaborator of the petitioner. It was further found that the said work was mere supply of instruments and equipment with the attending technicians of Car. Ma. The authority while arriving at its decision has relied on the following part in the said document itself:—

“A) Mr. Magnagnoli is the sole owner of the company denominated CAR. MA of Angelo Magagnoli, …………………………………dealing with the carrying out of the commercial activity of wholesale and rental of geotechnical and geophysical instruments;”

It was, therefore, found by the respondent-Corporation that insofar as Part II of the work is concerned, the petitioner has failed to produce any document which would meet the requirement as provided under the tender document and as such found it disqualified for Part II work also.

20. At the cost of repetition, we may state that while exercising powers of judicial review of administration action, we are not expected to sit in appeal over the decision of the authority. It is not permissible for us to examine as to whether the material which has been taken into consideration by the authority was sufficient enough to arrive at the decision taken by it. It is only permissible for us to examine as to whether the decision taken by the authority is fair, reasonable and rational. Sufficiency or insufficiency of the material would be beyond the scope of judicial review in such matters.

21. From the perusal of the reasons which have been set out in short hereinabove, it cannot be said that the reasons given by the authority while holding that the documents supplied by the petitioner do not meet the requirement under the tender document is either unreasonable or irrational. It cannot be said that the reasons given by the authority are such that no prudent or reasonable man would take in the facts of the case. It is also nobody's case that the yardstick applied by the respondent-authority to the petitioner are something different than those applied to other bidders. The authorities have found that none of the documents produced by the petitioner would establish the satisfactory completion of the work. The Apex Court in the case of Electrical Mfg. Co. Ltd. v. Power Grid Corpn. of India Ltd., (2009) 4 SCC 87 has observed thus:-

“19. In our opinion the expression “satisfactory completion” governs sub-clause (i) of Clause 1.1 also. Hence mere surveying, optimising tower locations, erecting and stringing with tension stringing equipment the requisite length of transmission lines will not be enough to give the necessary technical experience because it is possible that even after doing the above work the transmission lines may not function. Unless after doing the above works the line is tested and found to be successfully functioning it surely cannot be said that there was satisfactory completion of the transmission lines.”

22. In our considered view, therefore, refusal to accept the documents which are relied on by the petitioner on the ground that they did not prove that the petitioner or its collaborators had satisfactorily completed any work of the nature stipulated in the tender notice can be faulted with. No doubt, the Apex Court in the case Reliance Energy Ltd. v. Maharashtra State Road Development Corpn. Ltd., (2007) 8 SCC 1 has held that it is necessary for the authority to provide a level playing field. As observed by the Apex Court in the said judgment, the level playing field provides space within which equally placed competitors are allowed to bid for government contracts so as to subserve the larger public interest. It can thus be seen that level playing field would be applicable only if bidders are equally placed. By no stretch of imagination, the level playing field could be provided to the parties who are qualified and also parties who are not qualified. In the present case, we do not find that the decision arrived at by the authority can be termed as an unreasonable decision and that too so unreasonable that a reasonable person would not have arrived at it. Applying the principle of Wednesbury reasonableness, we do not find that the decision of the authority can be termed to be either unreasonable or irrational so as to warrant interference in our extraordinary jurisdiction under Article 226 of the Constitution.

23. In the result, the petition fails and is dismissed.

24. After the judgment was pronounced, the learned counsel appearing for the petitioner sought extension of the interim order dated 24-12-2009 for a period of two weeks from today to enable the petitioner to move the Supreme Court. The said request is strongly opposed by the learned counsel for the respondent No. 1 on the ground that this will result in delaying the project as the period will be curtailed for execution of the work which is to be done during the current season and the bid would expire. Taking into consideration that the petitioner has sought extension of the interim order for two weeks, we are inclined to extend the interim order till 4-3-2010 on condition that the petitioner shall give 48 hours' notice to the respondents before moving for any interim orders in the matter. Order accordingly.

Order accordingly.