Raja Bahadur Motilal Poona Mills Ltd. And Another Petitioners v. State Of Maharashtra And Others S

Bombay High Court
Jul 26, 2002
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The petitioner, a textile mill declared a sick unit and undergoing rehabilitation, owned certain properties in Pune. The Board for Industrial and Financial Reconstruction sanctioned a rehabilitation scheme directing the petitioner to develop surplus assets to repay debts. Permission was granted to develop 2 lakh sq ft from the property, with Respondent 7 acting as co-developer under an agreement dated 29-4-1997. Respondent 7 later applied for permission to construct using Transferable Development Rights (TDR) of 1.6 lakh sq ft acquired by it. The petitioner challenged the sanction granted by Pune Municipal Corporation for this development, seeking writ relief to quash the permission and restrain construction activities.

Legal Issues Presented

  1. Whether the writ petition challenging the development permission granted under Section 45 of the MRTP Act is maintainable in the presence of an efficacious alternate remedy by way of civil suit.
  2. Whether the grant of permission under Section 45 of the MRTP Act is a judicial/quasi-judicial act amenable to writ jurisdiction or a purely administrative act.
  3. Whether principles of natural justice require hearing of objectors before granting permission under Section 45 of the MRTP Act.
  4. Whether the provisions of Section 149 of the MRTP Act bar civil suits challenging such permissions.

Arguments of the Parties

Petitioner’s Arguments

  • The petitioner challenges the sanction granted to Respondent 7 to develop using TDR on the petitioner’s land, asserting that Respondent 7 has no right to use such TDR as per the agreements between the parties.
  • The petitioner contends that the order granting permission under Section 45 of the MRTP Act has attained finality under Section 149, barring civil suits, thereby making writ jurisdiction the only remedy.
  • The petitioner asserts that principles of natural justice were violated as it was not heard before granting the permission.

Respondent 7’s Arguments

  • The petition is not maintainable as an effective alternate remedy by way of civil suit is available to resolve contractual disputes.
  • The grant of building plan under Section 45 is a purely administrative act and not judicial or quasi-judicial, hence not amenable to writ jurisdiction.
  • There is no requirement to hear objectors under Section 45; the process is mechanical and administrative, and principles of natural justice do not apply.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Election Commission, India v. Saka Venkata Rao, AIR 1953 SC 210 Art. 226 is intended for enforcement of fundamental rights and other vital rights, not for resolving private disputes. The court emphasized writ jurisdiction is a remedy for protection of fundamental rights, not a forum for intra-party contractual disputes.
K.S Rashid v. Income Tax Investigation Commission, AIR 1954 SC 207 Writ jurisdiction is discretionary and should be refused if adequate alternative remedy exists. The court held that relief sought by the petitioner can be obtained by civil suit, thus writ petition is not maintainable.
Union Of India v. T.R Varma, AIR 1957 SC 882 Alternate remedy should be pursued before invoking writ jurisdiction; writ is not appropriate for disputed factual questions. The court noted serious disputes requiring evidence should be resolved in civil courts, not by writ petition.
State Of U.P v. Mohammad Nooh, AIR 1958 SC 86 Superior courts should decline writ interference until statutory remedies are exhausted. The court reaffirmed the need to exhaust alternate remedies before writ intervention.
D.L.F Housing Construction (P) Ltd. v. Delhi Municipal Corpn, 1976 3 SCC 160 Writ courts should not decide complicated factual and legal issues requiring evidence. The writ petition should be dismissed on preliminary ground of alternate remedy without going into merits.
State of H.P v. Raja Mahendra Pal, 1999 4 SCC 43 Writ jurisdiction is discretionary and not for mere contractual claims where efficacious alternative remedy exists. The court held that no special circumstances justified writ jurisdiction in contractual matters.
Kerala SEB v. Kurien E. Kalathil, 2000 6 SCC 293 Disputes arising out of contracts with statutory bodies are to be settled by ordinary contract law principles, not writ petitions. The court ruled that contractual disputes are not amenable to writ jurisdiction even if one party is a statutory body.
Chairman, Grid Corpn. of Orissa Ltd. v. Sukumari Das, 1999 7 SCC 298 Writ jurisdiction should not be exercised where alternate civil remedy is available, especially in disputed factual matters. The court held that writ petitions involving disputed facts should be directed to civil courts.
U.P State Coop. Land Development Bank Ltd. v. Chandra Bhan Dubey, 1999 1 SCC 741 Writ jurisdiction is a public law remedy and should be exercised only when public duty is involved. The court emphasized that contractual disputes are not public law matters and should be resolved in civil courts.
Rohtas Industries Ltd. v. Staff Union, 1976 2 SCC 82 Writ jurisdiction is extraordinary and should be exercised with restraint except in exceptional circumstances. The court cautioned against indiscriminate use of writ jurisdiction akin to "a bull in a china shop".
LIC v. Asha Goel, 2001 2 SCC 160 High Courts should not entertain writ petitions for enforcement of purely contractual rights involving disputed facts. The court reiterated the principle of alternate remedy and discretionary nature of writ jurisdiction in contractual disputes.

Court's Reasoning and Analysis

The Court analyzed the provisions of the MRTP Act, particularly Sections 44, 45, 47, and 149, to determine the nature of the permission granted and the availability of alternate remedies. It noted that Section 45 contemplates an administrative and mechanical process for granting development permission, which may be unconditional, conditional, or refused, with a deemed permission if no order is passed within 60 days. The Court observed that appeals are provided against orders granting or refusing permission but not against deemed permissions.

Section 149 bars questioning of final orders under the Act in civil suits, but the Court held this bar is limited and does not extend to deemed permissions nor prevent suits aimed at preventing unauthorized use or breach of contractual rights.

The Court found that the dispute between the parties concerns contractual rights regarding the use of TDR, which is a private law matter requiring interpretation of agreements and evidence. Such disputes are not suitable for writ jurisdiction, which is intended for protection of fundamental or legal rights and public law remedies, not for resolving intra-party contractual disagreements.

The Court emphasized the well-settled legal principle, supported by Supreme Court precedents, that writ jurisdiction should not be exercised where an alternate efficacious remedy, such as a civil suit, is available. It rejected the petitioner’s contention that principles of natural justice were violated, holding that Section 45 does not require hearing of objectors and is purely administrative.

The Court also highlighted concerns about the increasing misuse of writ jurisdiction to circumvent alternate remedies, causing delays and burdening courts unnecessarily. It underscored the need for judicial restraint and adherence to the established principle of exhausting alternate remedies before invoking writ jurisdiction.

Holding and Implications

The writ petition is dismissed.

The Court held that the petitioner has an alternate efficacious remedy in a civil suit to resolve contractual disputes regarding the use of TDR and to seek injunctions against unauthorized development. The administrative permission granted under Section 45 of the MRTP Act is not amenable to writ jurisdiction in this context. The Court extended the interim stay previously granted in favor of the petitioner for a period of four weeks to enable the petitioner to initiate appropriate civil proceedings. No new precedent was created; the decision reinforces the settled principle that writ jurisdiction should not be invoked where alternate remedies are available, especially in contractual disputes without public interest.

Show all summary ...

The Judgment of the Court was delivered by

V.G Palshikar, J.— By this petition, the petitioner has challenged the sanction granted by the Pune Municipal Corporation to certain development plans submitted by Respondent 7.

2. The petitioner is a textile mill which was declared as sick unit by the Board for Industrial and Financial Reconstruction and steps were taken for rehabilitation and revival of the unit. The Company i.e the petitioner owned certain properties bearing Final Plots Nos. 100 and 101 of T.P Scheme (Final), Sangamwadi, Pune in all measuring 1.02 lakh sq m (approximately) situated at Kennedy Road, Pune city within the limits of Pune Municipal Corporation. Therefore, in July 1996 the Board directed the petitioner Company to undertake development of surplus assets as part of the rehabilitation scheme so that the Company can be brought out of the debts to be paid to some extent. Permission therefore was granted to develop up to the extent of 2 lakh sq ft of land from out of the abovesaid plots. This rehabilitation scheme was sanctioned by the Board on 18-3-1997. The development was allowed to be undertaken along with Respondent 7 as co-developer or co-promoter. On 29-4-1997 an agreement was entered into between the petitioner and Respondent 7 to carry out jointly the development activity of 2,00,000 sq ft as earmarked from out of the plot mentioned above.

3. The development activity continued and thereafter Respondent 7 made an application for permission to construct and develop on the said construction by utilising or consuming Transferable Development Rights (TDR) of 1.6 lakh sq ft acquired by Respondent 7. This grant of permission to Respondent 7 is impugned in this petition by the petitioner.

4. The prayers made by the petitioner read as under:

“(a) That this Hon'ble Court may be pleased to exercise its power under Art. 226 of the Constitution and issue a writ of certiorari or appropriate writ, order or direction calling for the records and proceedings pertaining to the development permission granted vide commencement certificate dated 11-4-2001, Ext. ‘K’ hereto.

(b) That this Hon'ble Court may be pleased to issue a writ of mandamus or any other appropriate writ, order or direction directing and commanding Respondents 2 to 6 to forthwith cancel and/or withdraw the development permission granted vide commencement certificate dated 11-4-2001 Ext. ‘K’ hereto permitting Respondent 7 to carry out development on the said earmarked portion.

(c) That this Hon'ble Court may be pleased to issue a writ, order or direction directing and commanding Respondents 2 to 6 to forthwith revoke the order allowing TDR acquired by Respondent 7 to be used on the said property of Petitioner 1.

(d) That this Hon'ble Court may be pleased to issue a permanent order and injunction restraining Respondent 7, their servants, agents and officers or persons claiming through them from in any manner acting upon or in furtherance of the development permission issued vide commencement certificate dated 11-4-2001, Ext ‘K’ hereto and carry on any construction on the property bearing Final Plots Nos. 100 and 101 of T.P Scheme (Final), Sangamwadi, Pune more particularly described in the map at Ext. ‘A’ hereto.

(e) That pending the hearing and final disposal of this petition, this Hon'ble Court may be pleased to issue a temporary order and injunction restraining Respondent 7, their servants, agents and officers or persons claiming through them from in any manner acting upon or in furtherance of the development permission issued vide commencement certificate dated 11-4-2001, Ext. ‘K’ hereto and carry on any construction on the property bearing Final Plots Nos. 100 and 101 of T.P Scheme (Final), Sangamwadi, Pune more particularly described in the map at Ext. ‘A’ hereto.

(f) Ad interim reliefs in terms of prayer (c) above be granted.

(g) The costs of this petition be provided for.”

5. All these prayers are stoutly opposed on behalf of Respondent 7 as also other respondents. All the contentions raised by the petitioner for grant of these prayers are opposed by the respondents. However, Mr. S.G Aney, the learned counsel appearing on behalf of Respondent 7 raised a preliminary objection of maintainability of this petition, on the ground that effective alternate remedy by way of civil suit is available. In fact his contention is that civil suit is the only remedy available to the petitioner as his claim of existence and execution of certain rights between the parties created by the agreement between his client and the petitioner and therefore no writ to effectuate contractual obligations or rights is maintainable. His objections in brief are that:

All the facts are in dispute. Interpretation of agreements between the petitioner Company and Respondent 7 Company is involved. Whether such contractual rights flow from their agreements or not is required to be decided and which cannot be done by this Court, under Art. 226 of the Constitution. The grant of the building plan is not a judicial or quasi-judicial act. It is purely an administrative act and therefore it is not amenable to writ jurisdiction of this Court. There is no question of principles of natural justice being violated as the action of granting building plan is purely administratory. It does not entail obedience of principles of natural justice. Therefore, the writ petition is liable to be dismissed without going into the merits of the matter.

6. Mr. V.V Tulzapurkar the learned counsel on behalf of the petitioner replied to this contention by saying that the petitioner is challenging in this Court by writ jurisdiction, an order passed under S. 45 of the MRTP Act. The order has acquired finality by reason of S. 149 and unless that order is set aside, he cannot move the civil court against Respondent 7. According to the learned counsel such civil suit is barred by the provisions of the Act. Therefore, writ is liable to be maintained. He relied on certain judgment of this Court as also the Supreme Court in support of his proposition that where the impugned order has acquired finality by statute, a writ for quashing of that order is maintainable. We will have to examine these objections and its reply in the light of the provisions of the Act as also the settled law on the question of interfering in writ jurisdiction where alternate remedy of efficacious nature is available.

7. The MRTP Act, 1966 was enacted to make provision for planning the development and use of land in regions established for that purpose and for the constitution of Regional Planning Boards therefor; to make better provision for the preparation of development plans with a view to ensuring that town planning schemes are made in a proper manner and their execution is made effective, to provide for the creation of new towns by means of development authorities; to make provision for the compulsory acquisition of land required for public purposes in respect of the plan, and for purposes connected with the matters aforesaid.

8. It is a code in itself and adequate provisions are made for development activity in a controlled and planned manner. S. 44 provides an opportunity to individual, not being the Central or State Government, or the local authority, intending to carry out any development of any land to make an application in writing for that purpose. S. 45 reads as under:

“45. Grant or refusal of permission.—(1) On receipt of an application under Section 44 the Planning Authority may, subject to the provisions of this Act, by order in writing—

(i) grant the permission, unconditionally;

(ii) grant the permission, subject to such general or special conditions as it may impose with the previous approval of the State Government; or

(iii) refuse the permission.

(2) Any permission granted under sub-section (1) with or without conditions shall be contained in a commencement certificate in the prescribed form.

(3) Every order granting permission subject to conditions, or refusing permission shall state the grounds for imposing such conditions or for such refusal.

(4) Every order under sub-s. (1) shall be communicated to the applicant in the manner prescribed by regulations.

(5) If the Planning Authority does not communicate its decision whether to grant or refuse permission to the applicant within sixty days from the date of receipt of his application, or within sixty days from the date of receipt of reply from the applicant in respect of any requisition made by the Planning Authority, whichever is later, such permission shall be deemed to have been granted to the applicant on the date immediately following the date of expiry of sixty days.

Provided that the development proposals for which the permission was applied for, is strictly in conformity with the requirements of all the relevant development control regulations framed under this Act or bye-laws or regulations framed in this behalf under any law for the time being in force and the same in no way violates either the provisions of any draft or final plan or the same in no way violates either the provisions of any draft or final plan or proposals published by means of notice, submitted for sanction under this Act.

Provided further that, any development carried out in pursuance of such deemed permission which is in contravention of the provisions of the first proviso, shall be deemed to be an unauthorised development for the purposes of Ss. 52 to 57.

(6) The Planning Authority, shall, within one month from the date of issue of commencement certificate, forward duly authenticated copies of such certificate and the sanctioned building or development plans to the Collector concerned.”

9. The application under S. 44 made by any person is therefore required to be decided by an order in writing. It is further stipulated by sub-s. (5) of S. 45 that if such order is not made within 60 days such permission as is prayed for by an application under S. 44 shall be deemed to have been granted to the applicant. It will thus be seen that the permission may be granted unconditionally or conditionally or it may be refused, and if nothing is done, deemed permission is to be granted by the provisions of S. 45(5) of the Act.

10. Then comes S. 47 which reads as under:

“47. Appeal.—(1) Any applicant aggrieved by an order granting permission on conditions or refusing permission under Section 45 may, within forty days of the date of communication of the order to him, prefer an appeal to the State Government or to an Officer appointed by the State Government in this behalf, being an officer not below the rank of a Deputy Secretary to Government, and such appeal shall be made in such manner and accompanied by such fees (if any) as may be prescribed.

(2) The State Government or the officer so appointed may, after giving a reasonable opportunity to the appellant and the Planning Authority to be heard, by order dismiss the appeal, or allow the appeal by granting permission unconditionally or subject to the conditions as modified.”

11. An appeal is therefore provided against the order granting permission or refusing permission under S. 45. There is obviously no appeal against deemed permission under S. 45(5) of the Act. The necessary corollary of this legal situation is that there can be a deemed permission under s. 45(5) of the mrtp act against which there is no appeal provided and there being no order made by any of the authorities there is no question of which acquiring finality as contemplated by S. 149. S. 149 reads thus:

“149. Finality of orders.—Save as otherwise expressly provided in this Act, every order passed or direction issued by the State Government or order passed or notice issued by any Regional Board, Planning Authority or Development Authority under this Act shall be final and shall not be questioned in any suit or other legal proceedings.”

12. What is necessary under S. 149 to acquire finality and invite the bar of civil suit is, it should be an order passed or direction issued by the State Government or it should be an order passed or notice issued by any Regional Board, Planning Authority or Development Authority under this Act. It is provided by this section that no such order shall be questioned in any suit or in any legal proceedings. It is obvious therefore that a suit or legal proceeding for quashing a deemed permission under S. 45(5) is maintainable. Even otherwise under S. 149 what is barred is questioning of an order made under the Act in the civil suit. It does not bar any suit whereby a party to it can be prevented from acting on an action and order made under the Act. The bar spelt out by S. 149 is therefore very limited.

13. In our opinion therefore, the contention of Mr. V.V Tulzapurkar that a civil suit is barred by reason of the provisions of s. 149 of the mrtp act is unacceptable.

14. According to the parties, both the petitioner and Respondent 7, there are certain agreements in existence and operative. According to the petitioner those agreements do not give Respondent 7 any right to use TDR acquired by him somewhere else on the land which forms the subject-matter of the agreement. That being the claim of the petitioner that as the consequence of the permission granted under S. 45 to Respondent 7, Respondent 7 will be able to use the TDR on the land belonging to the petitioner and it will affect the right of the petitioner to use its own TDR acquired from some other place on its own land. The dispute between Respondent 7 and the petitioner is, who has the right to use the TDR on the construction already made by the petitioner and Respondent 7. It has nothing to do with the provisions of the MRTP Act or the orders made thereunder. The plan sanctioned by the authority under S. 45 need not be challenged and what is the challenge by the petitioner is infringement of petitioner's right to use its own TDR on its own site, the TDR by Respondent 7 cannot be utilised in breach of the agreement between the parties on the land belonging to the petitioner. Even if such plan is sanctioned and can be operated the construction thereon, in accordance with the provisions of the MRTP Act and other relevant clause for the time being in force is an activity to be undertaken by Respondent 7. Respondent 7 can be prevented from doing so by an injunction of the competent civil court granted on the basis of the pleading of the agreement on the face of which Respondent 7 is seeking to develop the land, however is not available to him. There is therefore in our opinion, in existance efficacious alternate remedy and therefore the argument of Mr. Aney that in such a situation the parties should be relegated to the alternate or efficacious remedy to decide all the disputed facts and agreement and the writ jurisdiction of this Court is not available. We are therefore of the considered view that the law on the point of alternate remedy being the effective step for maintaining the writ petition under Arts. 226 and 227 of the Constitution. This question comes up before the Court in regular intervals and the tendency to flout the rule of law is on increase and consequently judicial activism is also increased, and in several cases writ jurisdiction is moved in spite of the fact that alternative efficacious remedy is available on a specious plea and it is expedient in public interest to do so. In an exceptional case of public interest where large number of people are affected it may be that a writ petition could be entertained but the question is whether it would be a writ jurisdiction to be invoked as a matter of course even in dispute intra parties where there is no public interest at all or involved at all. Taking into consideration the fact that the question is ever reputed, we are pressed to decide that question so that as far as our Court is concerned the same principle of law that writ jurisdiction should not be invoked where alternate remedy is possible, has to be followed.

15. It was then contended by Mr. Tulzapurkar that S. 45 postulates grant of hearing to the objectors. Petitioner had objected well in advance the grant of application by Respondent 7 for development. He was not heard and therefore the order granting sanction under S. 45 is violative of principles of natural justice. The submission of the learned counsel then was that even if the alternate remedy is held available, a writ is maintainable in the present case for the reason that principles of natural justice were violated.

16. Mr. Aney, the learned counsel for Respondent 7 countered this argument by saying that action under S. 45 is to sanction and what is required by the Planning Authority is to see that the development plan as put in with the application under S. 44 confirms to the requirements of law, rules, instructions, bye-laws, etc. framed in that behalf by the Planning Authority. That being a pure administrative action there is no question of principles of natural justice being attracted in the consideration of the application under S. 45. We are unable to accept the submission of Mr. Tulzapurkar that S. 45 postulates grant of hearing to the objectors. Firstly because the process of granting application under that section is purely a mechanical and administrative process. The authority has to process the application for development and on finding it to be in conformity with the requirements of law grant it, and if it is not in conformity, it will be rejected. There is, therefore, no room for granting any hearing to any person. The provisions of S. 45 if read in whole, do not contemplate hearing even to the person applying under S. 44 and the only remedy available to such person after the order is made is that, without hearing as contemplated by S. 45, it will have to be held that both the applicant and the objectors if any, are entitled to hearing. The very fact that no such hearing is contemplated by provisions of S. 45 is evident from the fact that the appeal is made available to persons aggrieved by grant of or refusal of permission under that section. In our opinion putting such prayer under S. 45 is also a hazard or to put in objections in various multi-crore development plans (sic) the claim demand and delaying the execution of the development scheme. Such is not the intention of S. 45 and therefore we reject the submission that it postulates the hearing.

17. That takes us to the main question of entertaining writ petition when alternate remedy by way of civil suit is available. In our opinion the law on the point is settled. However, since the question is of recurring nature, we think to deal with the problem exhaustively with the sincere hope that hereafter the rule will be observances of the alternate remedy in appropriate forum and exception in every exceptional case would be entertaining of writ petition directly.

18. In Election Commission, India v. Saka Venkata Rao AIR 1953 SC 210 the Chief Justice of India Mr. Patanjali Sastri has observed way back in 1953 as under: (AIR p. 212)

“[T]he makers of the Constitution, having decided to provide for certain basic safeguards for the people in the new set up, which they called fundamental rights, evidently thought it necessary to provide also a quick and inexpensive remedy for the enforcement of such rights and, finding that the prerogative writs, which the courts in England had developed and used whenever urgent necessity demanded immediate and decisive interposition, were peculiarly suited for the purpose, they conferred, in the State's sphere, new and wide powers on the High Courts of issuing directions, orders, or writs primarily for the enforement of fundamental rights, the power to issue such directions, etc. ‘for any other purpose’ being also included with a view apparently to place all the High Courts in this country in somewhat the same position, as the Court of King's Bench in England.”

19. It will be seen therefore that Art. 226 is meant for issuing writs for protection of fundamental rights and protection of such rights which are vital and basic, but are not mentioned in Part III of the Constitution. It must be borne in mind that the petition for issuance of a writ as contemplated by Art. 226 is a remedy for protection of rights and not a forum for resolving the intra parties disputes for which the Civil Procedure Code is created. It will also be borne in mind that Art. 226 came into existence only in 1950. Prior to that civil suit was the only remedy and bar of that jurisdiction must be specific and wherever it is, it must be construed strictly.

20. In K.S Rashid v. Income tax Investigation Commission AIR 1954 SC 207 the Supreme Court has observed thus: (AIR p. 208)

“The remedy provided for in Art. 226 of the Constitution is a discretionary remedy and the High Court has always the discretion to refuse to grant any writ if it is satisfied that the aggrieved party can have an adequate or suitable relief elsewhere.”

In the instant case, we are convinced that such relief can be obntained by the petitioner in civil suit.

21. In Union Of India v. T.R Varma AIR 1957 SC 882 Justice Venkatarama Aiyar observed that following of alternate remedy before entering a writ jurisdiction was a well-settled law in 1957 itself. It has also observed that: (AIR p. 882)

“Under the law a person whose services have been wrongfully terminated, is entitled to institute an action to vindicate his rights, and in such an action the court will be competent to award all the reliefs to which he may be entitled, including some which would not be admissible in a writ petition. It is well settled that when an alternative and equally efficacious remedy is open to a litigant, he should be required to pursue that remedy and not invoke the special jurisdiction of the High Court to issue a prerogative writ. It is true that the existence of another remedy does not affect the jurisdiction of the court to issue a writ; but, the existence of an adequate legal remedy is a thing to be taken into consideration in the matter of granting writs. And where such remedy exists, it will be a sound exercise of discretion to refuse to interfere in a petition under Art. 226, unless there are good grounds therefor.”

22. In the very decision it is also observed by the Supreme Court that: (AIR p. 882)

“Where there is a question on which there is a serious dispute, which cannot be satisfactorily decided without taking evidence, it is not the practice of courts to decide it in a writ petition.”

In the present case also there are serious disputes regarding scope and meaning of the agreements between the petitioner and Respondent 7.

23. In the present case the petitioner and Respondent 7 seriously dispute the correct interpretation of various documents, agreements between them. Serious disputed facts arise in the present case. Where on an interpretation of a particular agreement such right to use TDR remains with the petitioner or Respondent 7 is a most serious dispute and the question of entering into that, as observed by the Supreme Court, in writ jurisdiction is not proper exercise of that jurisdiction. It is in this light that we have stated earlier that the writ jurisdiction is a remedy for protection of fundamental rights and it is not a forum for resolving intra parties disputes arising out of contractual obligations depending upon the contractual interpretations. For that purposes the best court is the civil court as created by the Civil Procedure Code in 1908, almost 42 years prior to creation of Art. 226 of the Constitution.

24. In State Of U.P v. Mohammad Nooh . AIR 1958 SC 86 this position is resettled, which is as under: (AIR p. 93, para 10)

“The fact that the aggrieved party has another and adequate remedy may be taken into consideration by the superior court in arriving at a conclusion as to whether it should, in exercise of its discretion, issue a writ of certiorari to quash the proceedings and decisions of inferior courts subordinate to it and ordinarily the superior court will decline to interfere until the aggrieved party has exhauted his other statutory remedies.”

25. Then in D.L.F Housing Construction (P) Ltd. v. Delhi Municipal Corpn. 1976 3 SCC 160 the Supreme Court sounded the note of caution and observed that it would be hazardous to embark upon a determination of the points involved: (AIR p. 386)

“In a case where the basic facts are disputed and complicated questions of law and fact depending on evidence are involved the writ court is not the proper forum for seeking relief. The right course for the High Court in proceedings under Art. 226 is to dismiss the petition on this preliminary ground without entering upon merits of the case. In the absence of firm and adequate factual foundation, it is hazardous to embark upon a determination of the points involved.”

26. The view that alternate remedy should normally be availed of before requiring exercise of writ jurisdiction has been constantly observed by the Supreme Court of India. The Supreme Court in State of H.P v. Raja Mahendra Pal 1999 4 SCC 43 observed that it is the duty of the court to see that alternate remedy is followed: (SCC p. 53, para 6)

“It is true that the powers conferred upon the High Court under Article 226 of the Constitution are discretionary in nature which can be invoked for the enforcement of any fundamental right or legal right but not for mere contractual rights arising out of an agreement particularly in view of the existence of efficacious alternative remedy. The constitutional court should insist upon the party to avail of the same instead of invoking the extraordinary writ jurisdiction of the court. This does not however debar the court from granting the appropriate relief to a citizen under peculiar and special facts notwithstanding the existence of an alternative efficacious remedy. The existence of the special circumstances are required to be noticed before issuance of the direction by the High Court while invoking the jurisdiction under the said article. In the instant case, the High Court did not notice any special circumstance which could be held to have persuaded it to deviate from the settled proposition of law regarding the exercise of the writ jurisdiction under Article 226 of the Constitution.”

27. In the present case the dispute is regarding right either of the petitioner or of Respondent 7 to use TDR on a given plot of land. It certainly therefore is not a special circumstance requiring exercise of writ jurisdiction and deviating from the settled proposition of law regarding the exercise of the writ jurisdiction under Art. 226. Then the Supreme Court observes regarding jurisdiction of the High Court, which reads as follows: (SCC p. 54, para 6)

“The High Court appears to have adopted a very generous, general and casual approach in applying the right to livelihood to the facts and circumstances of the case apparently for the purpose of clothing itself with the power and jurisdiction under Article 226 of the Constitution. We are sure that if the High Court had considered the argument in the right perspective and in the light of various pronouncements of this Court, it would not have ventured to assume jurisdiction for the purposes of conferring the State largess of public money, upon an unscrupulous litigant who preferred his claim on his proclaimed assumption of being as important as the Government of the State and equal thereto.”

28. To hold, in the present case that the principles of natural justice are liable to be observed while deciding an application under S. 45 of the Act is so liberally construing the provisions for the purpose of clothing us with the jurisdiction under Art. 226. As has been rightly observed by the Supreme Court we do not venture to assume jurisdiction in this case by stretching language of S. 45 beyond permissible limits.

29. Then in LIC v. Asha Goel 2001 2 SCC 160 the Supreme Court reiterates the legal position in regard to observance of alternate remedy. It says thus: (SCC pp. 161 & 162)

“The courts must bear in mind the self-imposed restriction consistently followed by High Courts all these years after the constitutional power came into existence in not entertaining writ petitions filed for enforcement of purely contractual rights and obligations which involve disputed questions of facts.

Ordinarily, the High Court should not entertain a writ petition filed under Article 226 of the Constitution for mere enforcement of a claim under a contract of insurance. Where an insurer has repudiated the claim, in case such a writ petition is filed, the High Court has to consider the facts and circumstances of the case, the nature of the dispute raised and the nature of the inquiry necessary to be made for determination of the questions raised.”

30. In Kerala SEB v. Kurien E. Kalathil 2000 6 SCC 293 the Supreme Court considered interference of the High Court under Art. 226 in contractual matter and observes thus: (AIR p. 2573)

“A contract would not become statutory simply because it is for construction of a public utility and it has been awarded by a statutory body. A statute may expressly or impliedly confer power on a statutory body to enable it to discharge its functions. Dispute arising out of the terms of such contracts or alleged breaches have to be settled by the ordinary principles of law of contract. The fact that one of the parties to the agreement is a statutory or public body will not of itself affect the principles to be applied. The disputes about the meaning of a convenant in a contract or its enforceability have to be determined according to the usual principles of the Contract Act. Every act of a statutory body need not necessarily involve and exercise of statutory power.”

Then the Supreme Court went on to observe on the question of construction of a contract which reads thus: (SCC pp. 298-99, paras 10 & 11)

“10. We find that there is a merit in the first contention of Mr. Raval. Learned counsel has rightly questioned the maintainability of the writ petition. The interpretation and implementation of a clause in a contract cannot be the subject-matter of a writ petition. Whether the contract envisages actual payment or not is a question of construction of contract. If a term of a contract is violated, ordinarily the remedy is not the writ petition under Article 226. We are also unable to agree with the observations of the High Court that the contractor was seeking enforcement of a statutory contract. A contract would not become statutory simply because it is for construction of a public utility and it has been awarded by a statutory body. We are also unable to agree with the observation of the High Court that since the obligations imposed by the contract on the contracting parties come within the purview of the Contract Act, that would not make the contract statutory. Clearly, the High Court fell into an error in coming to the conclusion that the contract in question was statutory in nature.

11. A statute may expressly or impliedly confer power on a statutory body to enter into contracts in order to enable it to discharge its functions. Dispute arising out of the terms of such contracts or alleged breaches have to be settled by the ordinary principles of law of contract. The fact that one of the parties to the agreement is a statutory or public body will not by itself affect the principles to be applied. The disputes about the meaning of a convenant in a contract or its enforceability have to be determined according to the usual principles of the Contract Act. Every act of a statutory body need not necessarily involve an exercise of statutory power. Statutory bodies, like private parties, have power to contract or deal with property. Such activities may not raise any issue of public law. In the present case, it has not been shown how the contract is statutory. The contract between the parties is in the realm of private law. It is not a statutory contract. The disputes relating to interpretation of the terms and conditions of such a contract could not have been agitated in a petition under Article 226 of the Constitution of India. That is a matter for adjudication by a civil court or in arbitration if provided for in the contract. Whether any amount is due and if so, how much and refusal of the appellant to pay it is justified or not, are not the matters which could have been agitated and decided in a writ petition The contractor should have relegated to other remedies.”

31. In Chairman, Grid Corpn. of Orissa Ltd. v. Sukumari Das 1999 7 SCC 298 the Supreme Court reiterated that writ jurisdiction should not be exercised where alternate remedy of civil suit is available. (AIR p. 3412)

“Held, High Court committed an error in entertaining the writ petitions even though they were not fit cases for exercising power under Art. 226 of the Constitution.” (SCC p. 301, para 6)

Even though they were not fit cases for exercising power under Art. 226 of the Constitution the Supreme Court went on to observe that: (AIR pp. 3412-13)

“It is the settled legal position that where disputed questions of facts are involved a petition under Art. 226 of the Constitution is not a proper remedy. The High Court has not and could not have held that the disputes in these cases were raised for the sake of raising them and that there was no substance therein. The High Court should have directed the writ petitioners to approach the civil court.” (SCC p. 302, para 6)

32. In our opinion the dicta of the Supreme Court following the well-settled law is very clear. In fact it is a mandate issued by the Supreme Court that the powers therein i.e Art. 226 shall not be exercised in cases where alternate remedy is available, always leaving apart certain well known glaring exceptions.

33. In U.P State Coop. Land Development Bank Ltd. v. Chandra Bhan Dubey 1999 1 SCC 741 the Supreme Court has observed regarding exercise of jurisdiction under Art. 226 as under: (SCC p. 753, para 22)

“22. The language of Article 226 does not admit of any limitation on the powers of the High Court for the exercise of jurisdiction thereunder though by various decisions of this Court with varying and divergent views, it has been held that jurisdiction under Article 226 can be exercised only when a body or authority, the decision of which is complained, was exercising its power in the discharge of public duty and that writ is a public law remedy.”

From the above dicta of the Supreme Court it will be clear that the jurisdiction under Art. 226 i.e the jurisdiction to issue writs is a public law remedy, a dispute between the parties to a contract, as to the interpretation of that contract (sic public) law, the remedy under public law cannot therefore be invoked.

34. In Rohtas Industries Ltd. v. Staff Union 1976 2 SCC 82 the Supreme Court has issued a serious caution regarding exercise of jurisdiction under Art. 226. It would be beneficial to note verbatim what the Supreme Court has to say: (SCC p. 88, para 9)

“[I]t is one thing to affirm the jurisdiction, another to authorise its free exercise like a bull in a china shop. This Court has spelt out wise and clear restraints on the use of this extraordinary remedy and High Courts will not go beyond those wholesome inhibitions except where the monstrosity of the situation or other exceptional circumstances cry for timely judicial interdict or mandate.”

35. The position in law regarding not exercising the writ jurisdiction when alternate remedy is available is so well settled that it was not necessary to have restated the entire law on the point as laid down by the Supreme Court. In the recent past we have noticed that the tendency to invoke the extraordinary jurisdiction is growing for various reasons. We may briefly note this aspect also. The first and foremost reason for rushing in writ jurisdiction is to seek instant adjudication of their disputes, which if taken to regular forums take years for adjudication. This being obviously an outcome of tremendous arrears pending at courts and therefore advocates canvas it as substantial reason for coming directly in writ jurisdiction. However in doing so the fact of arrears in the High Court on writ jurisdiction itself are ignored. The fact that because of large number of writs are filed in cases where alternate remedy is available and ought to be pursued, most of the time of the High Courts is consumed in resolving those newly instituted writ petitions of the kind the present one is. As a necessary corollary to which the pendency of old writ petitions continues to mount, it may be noted that this Bench has been constituted for deciding old writ petitions since June 2002. In the last one and half months, we have seen that cases are pending in the High Court in its writ jurisdiction way back to year 1990. It therefore takes normally a period of 10 years for a writ petition to be decided in this Court. If the figures of arrears in the entire moffusil are statistically analysed, it will be seen that by and large 80% of the civil suits or applications before various tribunals are decided within a period of 2 or 3 years. The argument therefore that, for an expeditious relief the High Court is approached in writ jurisdiction is proved to be incorrect. A writ petition takes more time to be decided than a civil suit or any other equal efficacious remedy.

36. Judicial notice also must be taken of the facts that large number of cases are filed where the civil suit is the only remedy solely with a view to avoid the payment of court fees. To take a concrete illustration, a writ petition is filed in the High Court seeking a direction to the respondent which invariably includes a private educational institution and educational authority which directs the payment, the direction sought for is, it is the duty of the State to pay and therefore writ is maintainable. It is obvious that if it is the duty of the State to pay the payment, it can be recovered by filing a civil suit. A civil suit for such recovery of money will be decided in a span of 2 or 3 years whereas the petitions for that relief are pending in this Court since 1992. No relief of any kind is received by the litigant. To carry further the illustration in such a petition claiming arrears of salary, it may be presumed that the salary arrears for the period of three years are approximately one lakh rupees. A civil suit will require payment of court fees to the tune of Rs. 3000 or so. Attempt is made to deny the revenue to the State by filing a writ petition with court fee of Rs. 250. Apart from denial of revenue to the State, in our opinion, exercise of writ jurisdiction in such cases is lending active assistance to the litigants to override the provisions of statute which require court fee for adjudication of the cases. Exercise of writ jurisdiction cannot be invoked therefore in cases where the consequences of loss of revenue, the loss of time, circumvention of law is involved.

37. In view of the above observations of the Supreme Court made so recently, it is obvious that the High Court should not interfere in contractual matters even if the contracts are with the statutory authorities. The Supreme Court has clearly observed that merely because the statutory authorities are involved, the contract does not become a statutory contract and even in matters of statutory contract, in our opinion no interference under Art. 226 is possible unless the effect of that breach of contract or violation of the conditions of the contract have direct bearing upon the fundamental right of a person.

38. From the aforesaid discussion based on the judgments of the Supreme Court it will be clear that throughout during the subsistence of Art. 226 since its inception it has been recorded that the sound and settled principle of law that whatever alternate and efficacious remedy available, it should be availed of before a writ jurisdiction is sought to be exercised. No doubt 2 or 3 exceptions of these rules have been carved out but they must be in the nature of things remain to be an exception. We need not go into those exceptions as present case is not one which could be said to have been covered by any of the exceptions. In our opinion therefore this petition is liable to be rejected for availability of alternate remedy of civil suit because it is in the civil suit that the petitioner Company can lay foundation for its claim that injunction is liable to be issued against Respondent 7 restraining it from using the sanction granted, under S. 45 of the Act. It can lead evidence in the civil suit on the documents to prove as to what was intended to be given under the agreement entered into between the petitioner and Respondent 7. That aspect of the matter cannot be gone into a writ jurisdiction. No injury is caused to the petitioner as he has chosen to come to the court directly under Art. 226 even for the appropriate relief, which can be claimed from appropriate civil court.

39. In fact the legal position, as also the observations made hereinabove embark as a settled position in law and there is no need to reiterate it at length. We feel obliged to do it because in spite of the clear law existing, a tendency to file writ jurisdiction circumventing the normal and alternate remedy is on the increase. The abovequoted are not the only reasons to such circumvention and there could be many more. But we do not intend to go on to analyse those reasons also, in this case. Ultimately, therefore, we most sincerely hope that this aspect of not entertaining writs when alternate remedy is available would be adequately considered by all courts having this jurisdiction.

40. There is no reason whatsoever therefore for this Court to exercise its extraordinary jurisdiction under Art. 226 for effectuating certain contractual obligations of right. In the result, therefore, the petition fails and it is dismissed.

41. Parties to act on the authenticated copy of this order.

42. After the judgment was pronounced, Mr. V.V Tulzapurkar the learned counsel for the petitioner submitted that an interim order was operative in favour of the petitioner. In view of this judgment holding that a suit will have to be filed, he seeks continuance of that order for further period of four weeks to enable the petitioner to take appropriate steps in that regard.

43. Looking to the controversy involved, we think, the request should be granted for a period of four weeks. Though we are extending the stay order for four weeks, the extention should not be considered in any manner as an expression of opinion of this Court. Trial court shall proceed with the matter only in accordance with the law. Hence the interim order made in this petition earlier will continue for four more weeks in favour of the petitioner.