Factual and Procedural Background

The petitions challenge an order dated December 21, 1999 of the Industrial Court. The common facts arise from a complaint filed under items 5 and 9 of Schedule IV to the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971 (MRTU & PULP Act). The complainant (respondent before this Court) was employed as a clerk by the erstwhile Kohinoor Mills Company Limited. By a 1983 Ordinance (later replaced by an Act of 1983) the Cotton Textile Undertakings of 13 mills, including Kohinoor Mills, were taken over; the Industrial Court proceeded on the basis that no notification had been issued suspending the operation of the complainant's contract of employment.

During the 1982 textile strike the complainant offered to work but was not assigned work nor paid salary. He alleged the employer's refusal to assign work attracted Item 9 of Schedule IV and sought relief including a declaration of unfair labour practice, a direction to be assigned work and payment of arrears of salary and benefits (from August 1, 1990), and an application under Section 33-C(2) of the Industrial Disputes Act, 1947 for salary for the prior period ending June 30, 1990.

The National Textile Corporation (the petitioner before this Court) filed a written statement before the Industrial Court and argued, inter alia, that the employer's refusal to provide work amounted to a closure under Section 3(8A) of the Bombay Industrial Relations Act (BIRA), which would give rise only to a claim for compensation and would require adjudication of the legality of the closure. Several writ petitions had earlier been remanded following a single judge judgment in S. D. Phansekar v. N.T.C. (1997 II CLR 801); pursuant to one such remand the Industrial Court reheard the matter and passed the impugned order on December 21, 1999.

Legal Issues Presented

  1. Whether the employer's refusal to assign work to the complainant amounts to a "closure" within the meaning of Section 3(8A) of the Bombay Industrial Relations Act and, if so, whether that characterisation limits the remedy to compensation only and requires adjudication under the BIRA.
  2. Whether the employer-employee relationship between the complainant and the National Textile Corporation continued after the 1983 take-over (in particular having regard to Section 14 of the Act of 1983) or whether the contract of employment had been terminated.
  3. Whether remedies under the Bombay Industrial Relations Act operate to oust or exclude remedies available under the MRTU & PULP Act, 1971 (and relatedly the scope of proceedings under Section 33-C(2) of the Industrial Disputes Act, 1947).

Arguments of the Parties

Appellant (National Textile Corporation) — Arguments

  • The refusal of work by the employer to the workman may amount to a closure within the meaning of Section 3(8A) of the Bombay Industrial Relations Act, which would entitle workers only to claim compensation for the closure.
  • If such a closure is established, the legality and validity of the closure would need to be adjudicated and justified under the BIRA, and the quantum of compensation would be assessed under Item 7 of Schedule III of that Act.
  • Remedies under the BIRA (including adjudication of closure) should be available and may be a necessary route to obtain relief, implying that complaints under the MRTU & PULP Act would not be maintainable to obtain the relief sought by the complainant.

Respondent (Workman / Complainant) — Arguments

  • The complainant's services were not terminated by the erstwhile employer nor by the National Textile Corporation after the take-over; no notification suspended the contract of employment under the Act of 1983.
  • Although the 1982 strike occurred, the complainant offered himself for work and was not assigned work nor paid salary; by not assigning work the Corporation attracted Item 9 of Schedule IV of the MRTU & PULP Act and was duty bound to pay salary.
  • The complainant sought (a) a declaration of the commission of an unfair labour practice, (b) a direction to be assigned work, and (c) payment of arrears of salary and benefits from August 1, 1990; he also applied under Section 33-C(2) of the Industrial Disputes Act for payment of prior salary up to June 30, 1990.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
S. D. Phansekar v. N.T.C., 1997 II CLR 801 That matters such as refusal to give work, and the reasons for such refusal, could not be investigated in proceedings under Section 33-C(2) of the Industrial Disputes Act. The Court noted that earlier remand orders to the Industrial Court were made in view of this judgment; it distinguished the present case because findings were reached after evidence in complaints under the MRTU & PULP Act, rather than via Section 33-C(2) proceedings alone.
NTC v. RMMS, reported 1993-I-LLJ-954 (at 958) Affirms that a principal object of the Act of 1983 is to protect interests of workmen already employed in textile mills; and that provisions such as Section 3(3) and 3(4) do not have the effect of terminating contracts of employment without compliance with statutory safeguards (custodian must give notice or one month's wages when terminating if in opinion contract is unduly onerous). The Court relied on this precedent to underline the protective purpose of the 1983 Act and to support the view that employees continued in service unless their contracts were validly terminated in accordance with the Act; this informed the Court's conclusion that the employment relationship had not been terminated.

Court's Reasoning and Analysis

The Court's analysis proceeded along these lines (as expressed in the opinion):

  1. Admitted Employer-Employee Relationship: The Court began from the admitted factual premise that there was an employer-employee relationship between the complainants and the Corporation and that this relationship had never been terminated either before or after the take-over legislation.
  2. Statutory Effect of the 1983 Take-over: The Industrial Court had relied on Section 14 of the Act of 1983 which provides that persons who immediately before the appointed day were employees of the textile undertakings would become employees of the National Textile Corporation on the same service conditions and continue until their employment was duly terminated. The present matter had no evidence of any such termination.
  3. Lack of Evidence of Termination or Closure Permission: The Industrial Court found that the witness examined by the Corporation was not concerned with the complainant's department and that the Corporation produced no evidence that the services of the workmen had been terminated. The department where the complainant worked was still functioning and some employees had been provided work after 1983. There was also no permission for closure under section 25-O of the Bombay Industrial Relations Act; therefore there was no lawful closure.
  4. Unjustified Selection of Some Employees: Given that the department continued to function and other employees were assigned work, the Court concluded it was not open to the Corporation to single out a few employees to be given work while excluding the complainant without justification.
  5. Concurrent Remedies and Scope of Section 33-C(2): The Court held that remedies under the Bombay Industrial Relations Act do not oust remedies available under the MRTU & PULP Act; concurrent remedies are available. The Court also relied on S. D. Phansekar to note that where liability needs determination, Section 33-C(2) proceedings are inappropriate — but distinguished the present case because the Industrial Court had conducted a fresh hearing and reached findings after evidence in complaints under the MRTU & PULP Act.
  6. Purpose of the 1983 Act: The Court emphasized that one of the principal objects of the 1983 Act is to protect the interests of workmen employed in the textile mills (citing NTC v. RMMS). The Court quoted the passage explaining that sections such as 3(3) and 3(4) do not have the effect of terminating contracts of employment absent compliance with the statutory safeguards (e.g., notice or payment in lieu).
  7. Conclusion of Consistency with Law: On the basis of the admitted facts, the lack of evidence of termination or closure permission, the functioning of the department, and the protective object of the 1983 Act, the Court concluded that the Industrial Court's orders were consistent with the legal position and the statute's object.

Holding and Implications

Final Disposition: The petitions were dismissed. The Court found no substance in the petitions challenging the Industrial Court's order dated December 21, 1999.

Direct Effect on the Parties: The Industrial Court's direction (as described in the opinion) that the Corporation provide work to the complainant workmen on the posts they were occupying and pay salary together with attendant benefits from July 1, 1990, stands as upheld by this Court. The Court also observed that the Corporation had not adduced evidence or raised requisite pleas after remand, which weighed against it.

Broader Implications: The opinion reinforces the protective object of the 1983 take-over legislation (as explained in NTC v. RMMS) and confirms that employees continue in employment post take-over unless their contracts are validly terminated in accordance with the statute. It also confirms that remedies under different industrial statutes may be concurrent and that the limited scope of Section 33-C(2) (as stated in S. D. Phansekar) does not preclude relief obtained after a full hearing on complaints under the MRTU & PULP Act where evidence has been led.

Certified and ordinary copies of the order were to be made available as noted in the opinion.

Show all summary ...

1. By these petitions, the order dated December 21, 1999 passed by the Industrial Court is sought to be impugned by the petitioner which is the National Textile Corporation. All the petitions raise a common question. The facts are similar and those in the first petition may briefly be adverted to.

2. The complaint in question was filed under items 5 and 9 of Schedule IV to the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971. In the first complaint, the Complainant, respondent herein, was in the employment of the erstwhile Kohinoor Mills Company Limited as a clerk. In 1983, an Ordinance known as the Textile Undertakings (Taking over of Management) Ordinance, 1983 came to be promulgated by "virtue of which the Cotton Textile Undertakings of 13 Mills including Kohinoor Mills Company Limited were taken over. The Ordinance was subsequently replaced by an Act of 1983. The case of the respondent herein before the Industrial Court was that his services were neither terminated by the erstwhile Kohinoor Mills Company Limited nor at any time thereafter by the National Textile Corporation after take over. No notification was issued by the Central Government under the Act of 1983 suspending the operation of the contract of employment. In 1982 there was a textile strike which crippled the textile industry. The complainant, however, was not one of those workers who proceeded on strike but he, in fact, offered himself for work during the period of the strike. However, he was neither assigned any work, nor was paid any salary. In the circumstances, it was alleged that by not assigning work to the complainant, the provisions of Item 9 of Schedule IV of the Act were attracted. The Corporation, according to the Respondent, was duty bound to pay his salary which it had refused to pay. Some time in February 1990, it is alleged that 10 to 15 clerks were called for work by the Corporation but no work was assigned to the complainant Respondent though he reported for work and continued to do so. Besides, a declaration of the commission of an unfair labour practice, the workman, inter alia, sought a direction that he should be assigned work and for the payment of arrears of salary and attendant benefits with effect from August 1, 1990. The workman had also moved an application under Section 33-C(2) of the Industrial Disputes Act, 1947 for the payment of salary for the prior period ending on June 30, 1990.

3. A written statement was filed by the Corporation before the Industrial Court. One of the points canvassed in the Written Statement and which was the only point urged before me, was the refusal of work by the employer to the workman may amount to a closure within the meaning of Section 3(8A) of the Bombay Industrial Relations Act which would merely give a right to claim compensation for such closure. Further it is submitted that in such a case the legality and validity of the closure would need to be adjudicated upon and justified and the quantum of compensation as provided under Item 7 of Schedule III of the Act would need to be assessed in accordance with law.

4. The impugned order of the Industrial Court dated December 21, 1999 came to be passed in pursuance of an order of remand passed by a learned single Judge of this Court on August 4, 1997. By the order dated August 4, 1997, the learned single Judge R.M. lODHA, J. relied upon earlier orders passed in similar cases remanding several writ petitions for fresh hearing to the Industrial Court. It may be mentioned that these remand orders came to be passed in view of a Judgment of a learned single Judge of this Court (S.H. KAPADIA, J.) in S. D. Phansekar v. N. T.C. reported in 1997 II CLR 801. Upon remand, the Industrial Court heard the parties again and passed the impugned order. In the order which is impugned in these proceedings, the Industrial Court essentially held that in so far as the workmen in these cases are concerned, there was no cessation of the relationship of employer and employee at any stage. The Industrial Court relied on the provisions of Section 14 of the Act of 1983 and held that at no stage had the relationship of employer and employee been terminated between the parties. In para 26 of its order, the Court noticed the fact that the witness examined on behalf of the Corporation was not concerned with the working of the department where the complainant had been engaged and on whose Muster Roll his name was borne. There was no evidence forth coming on behalf of the Corporation to the effect that the services of the workmen had been terminated in any manner. The department in which the complainant was working was functioning and the Corporation had provided work to some employees even after 1983. In these circumstances, the Industrial Court held that there was no reason why the complainant had been singled out while other employees had been preferred for providing employment. In fact, the Industrial Court noted that even after the remand pursuant to the order of this Court, the Corporation had neither raised the requisite pleas nor had adduced any evidence in the light of the observations contained in the order of this Court. The department wherein the complainant was working before the strike, was held to be still functioning. Though it was sought to be urged on behalf of the Corporation that under a settlement with the recognized union, a cut off date for reporting for work had been laid down, yet, it was found that some of the employees had been allowed to resume duties even after the alleged cut off date. Finally, the Industrial Court held that even the case of a closure, which was sought to be made out, would be of no avail since the requisite permission for closure had not been obtained. In the premises, the Court directed the Corporation to provide work to the complainant-workmen on the posts they were working and to pay salary together with the attendant benefits from July 1, 1990.

5. The only point which was sought to be urged by the learned counsel appearing on behalf of the Corporation was that even if there was a refusal to provide work as alleged, this would amount to a closure and, nonetheless, the legality and justification for the closure would need to be determined in an adjudication under the Bombay Industrial Relations Act, in the absence of which the workers would not be entitled to any relief. There is no substance whatsoever in this submission. First and foremost, there is an admitted relationship of employer and employee between the complainant workmen and the Corporation. That relationship has never been terminated or brought to an end either before the Take Over legislation or subsequent thereto at any stage. The Industrial Court in its order referred to the provisions of Section 14 of the Act of 1983 under which every person who was a workman within the meaning of the Industrial Disputes Act, 1947 and had been immediately before the appointed day in the employment of the Textile Undertakings would become on and from the appointed day an employee of the National Textile Corporation on the same service conditions and would continue to do so until his employment was duly terminated. Admittedly, there has been no termination of the relationship of employer and employee. Secondly, the admitted position is that more than 100 employees were employed in the establishment. There was no closure permission within the meaning of Section 25-O of the Act. There was no valid or lawful closure. Thirdly, as a matter of fact it has been found that the department where the complainants were working still continued to function. The Industrial Court justifiably held that in these circumstances, it was not open to the Corporation to select a few employees for : being allotted work and for the payment of wages. Fourthly, the remedy, if any, under the provisions of the Bombay Industrial Relations Act cannot operate to oust the remedy under the MRTU & PULP Act, 1971. Concurrent remedies are available under the provisions of Industrial Legislation and merely because one remedy was available could not be a ground to legitimately hold that complaints under the MRTU & PULP Act were not maintainable. : What the decision of the learned single Judge in S.D. Phansekar v. NTC (supra), underlined was that matters such as the refusal to give work, and the reasons thereof could not be investigated into in proceedings under Section 33-C(2) of the Industrial Disputes Act, 1947. This followed the well settled position in law in regard to the nature of the proceedings under Section 33-C(2), so that where the liability of the parties needs to be determined, recourse cannot be had to the proceedings under Section 33-C(2). In the present case, on the other hand, findings have been arrived at after evidence was led in complaints under the MRTU & PULP Act, 1971. Finally, regard must be had to the fact that the object of the 1983 Act, was to reorganize and rehabilitate the textile undertakings and thereby protect the interests of the workmen employed therein. As the Supreme Court held in NTC v. RMMS, ,

"this recital in the preamble makes it clear that one of the principal objects of the Act is to protect the interests of the workmen who were already employed in the textile mills."
The Court further held thus 1993-I-LLJ-954 at 958:

"14. The said provisions state that if the contract of employment of a workman is to be terminated, the custodian can do so if he is of the opinion that it is unduly onerous. However, while terminating the contract, he has to give one month's notice in writing or salary or wages, as the case may be, for one month in lieu of the notice. This provision is consistent with the object of the Act and also with the provisions of the I.D. Act. It is, therefore, amply clear that Section 3(3) and 3(4) do not have the effect of terminating the contract of employment of the workmen. It is also not disputed that neither the custodian nor the appellants who stepped into his shoes had at any time put an end to the contract of employment of any of the workmen involved in the present dispute pursuant to the provisions of section 13."

6. From this perspective therefore, the orders passed by the Industrial Court in these cases are consistent with the legal position and subserve the underlying spirit of the legislation. Consequently, I do not find any substance in the petitions which are accordingly dismissed.

7. Certified copy of this order expedited.

8. An ordinary copy of this order may be made available to the parties.