- Bookmark
- Share
- CaseIQ
M/S. Bharat Barrel &... v. The Municipal Corpor...
Factual and Procedural Background
The appellants, manufacturers of barrels and drums, consumed electricity supplied by the B.E.S.T Undertaking (respondent No. 1). The appellants challenged a notice dated October 31, 1972, threatening disconnection of their electricity supply due to non-payment of Rs. 3,30,853.68. Initially, metering equipment with a current transformer (C.T.) ratio of 40:5 was installed based on the appellants' connected load. In April 1961, due to installation of a new transformer increasing the maximum demand, the C.T. ratio was changed to 80:5, necessitating the doubling of meter readings to reflect actual consumption. Due to an administrative oversight, the meter readings were not multiplied by two, resulting in undercharging from April 17, 1961 to January 1972. The B.E.S.T Undertaking discovered this in January 1972 and demanded payment of the undercharged amount, including electricity duty, through letters in May and July 1972. The appellants disputed the claim, alleging lack of knowledge about the meter change and contended the claim was barred by limitation. They also disputed the power of the Undertaking to demand deposits or disconnect supply under the Indian Electricity Act, 1910. The matter was referred to the Electrical Inspector, who confirmed the necessity of doubling the meter readings. The trial court dismissed the appellants' petition with costs, leading to the present appeal.
Legal Issues Presented
- Whether the licensee (B.E.S.T Undertaking) was entitled under Section 24 of the Indian Electricity Act, 1910, to disconnect the appellants' electricity supply for non-payment of charges claimed for the period prior to three years, including amounts allegedly barred by limitation.
- Whether a bona fide dispute existed regarding the correctness of the meter readings or the liability to pay the claimed amounts, thereby precluding disconnection under Section 24(1) of the Electricity Act.
- The proper construction of the word "due" in Section 24 of the Electricity Act, particularly whether it includes claims barred by limitation.
- The applicability and effect of Section 26 of the Electricity Act concerning meter disputes and the limitation period for claims based on meter correctness.
Arguments of the Parties
Appellants' Arguments
- A large portion of the claim was barred by the law of limitation except for the three years immediately preceding the demand.
- Under Section 24 of the Electricity Act, the Undertaking was not entitled to disconnect supply for amounts barred by limitation.
- The appellants disputed the replacement date of the metering equipment, asserting a bona fide dispute existed, thus disallowing disconnection under Section 24(1).
- The appellants contended that the Undertaking had no power to demand deposits either with itself or the Electrical Inspector as a condition precedent to disconnection.
- They relied on the provisions of Section 26(6) of the Electricity Act, asserting disputes about meter correctness limited claims to six months prior to the claim.
- They argued the word “due” should be construed narrowly, excluding claims barred by limitation, referencing analogous provisions under the Companies Act and the Transfer of Property Act.
Respondents' Arguments
- The claim was based on a mistake in the application of the meter multiplier and not on a faulty meter, so the limitation period under Section 26 did not apply.
- The word “due” in Section 24 of the Electricity Act should be given a wider, dictionary meaning, including amounts barred by limitation.
- There was no bona fide dispute regarding the date of meter replacement or the liability to pay the claimed amounts.
- The Undertaking was entitled to disconnect supply after due notice for non-payment of amounts owed.
- The appellants’ denial of meter replacement and characterization of the claim as time-barred was frivolous and vexatious, aimed at avoiding payment.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Ramrao Raoji Palkar v. Amir Kasam Bhagwan, 1955 58 Bom. L.R 284 | Interpretation of the word "due" in statutory context, including amounts barred by limitation. | The Court adopted the wider dictionary meaning of "due" including claims barred by limitation in construing Section 24 of the Electricity Act. |
| K.G.U Trust v. Shri Ram Chandraji Mandir, 1978 1 SCC 44 | Approval of wider meaning of "due" in rent control legislation. | Supported the wider interpretation of "due" in the Electricity Act context, aligning with prior High Court decisions. |
| Nagpur Corporation v. N.E.L & P. Company, [1958] A.I.R Bom. 498, S.C 60 Bom. L.R 1446 | Requirement of bona fide dispute to preclude action under Section 24(1) of Electricity Act. | Held that no disconnection under Section 24(1) can be made if a bona fide dispute exists between licensee and consumer. |
| M.S.E.B v. Madhusudandas, [1966] A.I.R Bom. 160, S.C 67 Bom. L.R 919 | Recognition of bona fide dispute as a defense against disconnection under Section 24(1). | Confirmed that disconnection is unjustified if a bona fide dispute exists even if the consumer's interpretation is ultimately incorrect. |
| Famous Cine Laboratories and Studios Ltd. v. Municipal Corporation for Greater Bombay, 1972 O.C.J Misc. Petition No. 167 of 1967 | Consumer's bona fide dispute negates neglect to pay under Section 24(1). | Held that a genuine dispute prevents characterization of non-payment as neglect, barring disconnection. |
| Naini Tal Hotel v. Municipal Board, [1946] A.I.R All. 502 | Limitation does not extend the period for recovery but affects suit claims. | Referenced to argue that limitation bars suit claims but does not affect disconnection rights under Electricity Act. |
| Firm Attar Singh v. Amritsar Municipality, [1938] A.I.R Lah. 338 | Similar to above, limitation bars suit claims but not necessarily other statutory remedies. | Used to support respondent’s position on limitation and disconnection rights. |
| M. Gordhandas & Co. v. M.W Industries, 1971 3 SCC 632 | Definition of "due" in Companies Act context excluding time-barred claims. | Distinguished by the Court as inapplicable to Electricity Act provisions. |
| Amalgamated Commercial Traders Pte. Ltd. v. Krishnaswami, 1965 35 Comp. Cas. 456 | Similar principle as above under Companies Act. | Distinguished and not applied to Electricity Act interpretation. |
Court's Reasoning and Analysis
The Court analyzed the statutory scheme of the Indian Electricity Act, 1910, focusing on Sections 22, 24, and 26. It recognized the licensee's obligation under Section 22 to supply electricity to all consumers within the supply area and the power under Section 24 to discontinue supply if charges are unpaid after due notice.
The Court rejected the appellants' contention that the word "due" in Section 24 should be narrowly construed to exclude amounts barred by limitation. It relied on authoritative interpretations, including the division bench decision in Ramrao Raoji Palkar, which adopted a wider dictionary meaning of "due" to include all outstanding amounts irrespective of limitation. The Court held that the right to discontinue supply is a statutory relief distinct from the right to recover amounts through suit, which may be barred by limitation. Thus, the licensee may discontinue supply for all unpaid charges, including those barred in a suit.
Regarding Section 26, the Court clarified that the six-month limitation on meter disputes applies only to disputes about meter correctness, not to claims arising from failure to apply the correct multiplier, which was a different issue. The Electrical Inspector's report confirmed the necessity to multiply meter readings by two, validating the Undertaking's claim.
The Court also examined the requirement of a bona fide dispute to preclude disconnection under Section 24(1). It reviewed prior case law establishing that a genuine dispute negates neglect to pay. However, it found that the appellants' denial of meter replacement and blanket claim of limitation barred the entire demand were not bona fide but frivolous and vexatious. The appellants failed to respond adequately to detailed explanations and continued to dispute facts contrary to established evidence.
Consequently, both conditions for action under Section 24(1) were satisfied: the appellants owed a debt, and they neglected to pay it. The notice threatening disconnection was lawful and not liable to be quashed.
Holding and Implications
DISMISSED - The appeal was dismissed, affirming the trial court's decision to uphold the notice of disconnection.
The Court held that the licensee is entitled under Section 24 of the Indian Electricity Act, 1910, to disconnect supply after due notice for non-payment of charges, including amounts barred by limitation in a civil suit. The appellants' denial of liability was not bona fide, and therefore, the threat of disconnection was lawful. The decision clarifies that statutory powers to discontinue supply are distinct from civil remedies and are not limited by limitation periods applicable to suits. No new precedent was set beyond affirming the existing statutory interpretation and principles regarding bona fide disputes and the scope of "due" charges under the Electricity Act.
Desai, J.:— The appellants before us are the original petitioners in Miscellaneous Petition No. 765 of 1972. They have preferred this appeal from the decision of Nain, J. in the said petition dismissing the same with costs.
2. The appellants are manufacturers of barrels and drums and for the purpose of their manufacturing activity consume electricity which is supplied by the B.E.S.T Undertaking owned by the respondent No. 1 Corporation. The respondent No. 2 to this appeal, who was also the respondent No. 2 to the original petition, was at the relevant time an officer of the B.E.S.T Undertaking. The appellants filed their petition for an appropriate writ, order or direction requiring the respondents to withdraw or cancel the notice dated October 31, 1972, by which it was threatened that the electric supply of the petitioners would be disconnected on account of non-payment of the sum of Rs. 3,30,853.68 mentioned in the said notice. In order to understand the rival contentions, it will be necessary to mention the following facts. Prior to April 1, 1960 the appellants had been provided with metering equipment consisting of current transformers of the ratio of 40:5 on the basis of the appellants' then connected load which was 485 KW with an authorised maximum demand of 210 KW. The said metering equipment recorded direct reading of the energy consumed on the dial provided for that purpose. At or about that time the appellants had placed an order with the Government Electric Factory, Bangalore, for the supply of 1000 KVA transformer to feed the appellants' new automatic plant imported by them which had been erected for the appellants by the General Electric Company, Bombay. On April 8, 1961 the appellants by a letter to the B.E.S.T Undertaking informed them that the appellants desired a shut down of the power supply to their factory with a view to enable the appellants to connect their new KVA transformer. On April 13, 1961 one H.B Shivdasani, a representative of the appellants, called on the Superintendent of the B.E.S.T Undertaking with a view to finalise the arrangement to meet the additional load that would be required by the appellants through the new transformer. By reason of the new plant and the new requirement the authorised maximum demand at the appellants' factory was revised upward from 210 KW to 500 KW. The existing metering equipment viz. the current transformer having the ratio of 40:5 became inadequate to meet this revised maximum demand and it became necessary, therefore, to provide metering equipment, with a higher ratio. Accordingly on April 17, 1961 the old current transformers with the ratio of 40:5 were replaced by those having a ratio of 80:5. It is the case of the respondents that as a result of the said replacement, it became necessary to multiply the reading recorded on the dial of the existing meter by two with a view to arrive at the correct number of units of energy consumed by the appellants. According to the respondents, further, it was about that time that the reading activities of the B.E.S.T Undertaking were transferred to their northern zonal office and due to some mistake the concerned officer of the northern zonal office was not informed of the changes effected. It is the case of the respondents that because of this mistake the electric energy consumed at the appellants' factory continued to be charged on the basis of the actual reading recorded on the dial of the existing meter without the reading being multiplied by two as had become necessary. According to the respondents, the said mistake was detected by the staff of the B.E.S.T Undertaking only in January 1972 and after checking the records it was found that the appellants had been undercharged from April 17, 1961. As the multiplier that was required to be applied, according to the respondents, was two, it would follow that the undercharging was to the extent of one-half. By a letter dated May 4, 1972 the Superintendent, Consumers, (North) of the B.E.S.T Undertaking apprised the appellants of this position and requested them to make payment of the amount mentioned in the letter. A statement of amounts claimed by the B.E.S.T Undertaking was annexed to the said letter and the statement indicated that the amount claimed represented charges for electric supply made and not billed for as also the electricity duty payable thereon. This was followed by a subsequent letter dated May 24, 1972 sent by the Undertaking by way of a reminder, in which for the first time disconnection of supply for non-payment was hinted at. On May 31, 1972 the appellants recorded their surprise at the claim made in the Undertaking's letters dated May 4, and 24, 1972. It was claimed in this letter that the appellants were not aware of the replacement of the meter. The appellants further contended that the threat to discontinue supply was uncalled for. The appellants sought time and facility to check the calculations made by the B.E.S.T Undertaking and to confirm the amounts claimed. It was also pointed out that the appellants had based their costing on the electricity bills sent by the B.E.S.T Undertaking which had been duly paid and they would not be entitled to recover the supplementary fabrication charges from their customers, which would entail great loss. The B.E.S.T Undertaking sent a detailed reply by their letter dated July 13, 1972 in which the facts set out earlier in this judgment were briefly and chronologically indicated. This was followed by a reminder dated August 25, 1972. By their letter dated September 4, 1972 the appellants mentioned that they were unable to check up their earlier records in view of the unsettled labour conditions at their factory and promised to check up the past records as soon as possible and write to the Undertaking further thereafter. Ultimately on October 31, 1972 the B.E.S.T Undertaking sent to the appellants the notice which had been impugned in the petition pointing out that the amount claimed viz. Rs. 3,30,853.68 had not been received and calling upon the appellants to pay the same within seven days, failing which it was stated that the Undertaking would be constrained to disconnect the appellants' electricity supply for non-payment of the dues. By the said letter it was further mentioned that in case the appellants raised any dispute, the amount could be deposited either with the B.E.S.T Undertaking or with the Electrical Inspector to the Government of Maharashtra. By their letter dated November 3, 1972 the appellants characterised the claim of the B.E.S.T Undertaking as false. They repeated the earlier contentions raised by them in their letter of May 31, 1972 and described the Undertaking's letter dated July 13, 1972 as alleging various irrelevant facts. As regards the amount claimed for the period 1961 to 1972 it was contended that the claim would be barred by the law of limitation. It was further mentioned that appellants were disputing the claim of the Undertaking bona fide and therefore the electricity supply of the appellants could not be disconnected under the provisions of s. 24 of the Indian Electricity Act, 1910 (hereinafter referred to as “the Electricity Act” for the sake of brevity). As regards the demand for making a deposit in case there was a dispute, the appellants contended that they had no objection to refer the dispute to the Electrical Inspector under s. 26 of the Electricity Act, but urged further that the Undertaking had no power to call upon the appellants to deposit the sum claimed either with the Undertaking or with the Electrical Inspector. By another letter of the said date addressed by the appellants to the Electrical Inspector, Government of Maharashtra, enclosing a copy of their letter to the B.E.S.T Undertaking, the appellants demanded that the dispute and the contentions raised by the appellants should be adjudicated by him. In the said letter the dispute referred to was one in respect of the meter reading for the said period viz. April 17, 1961 to December 31, 1971. The contention of the appellants that the whole of the claim was barred by the law of limitation was also brought to the attention of the Electrical Inspector. This correspondence was followed by the petition filed on November 13, 1972, in which it was, inter alia, repeated (para 11(d)) that the whole claim of the Undertaking was barred by the law of limitation.
3. Before the learned trial Judge at the time of hearing of the application for interim relief, a consent order was made on February 19, 1973 by which the Electrical Inspector to the Government of Maharashtra was appointed as a referee to inspect the electric meter installed by the B.E.S.T Undertaking bearing No. 546017 and the C.T and the P.T connected thereto in the premises of the appellants, and he was required to report whether the type of the equipment was such that the units recorded by the meter had to be multiplied by two in order to arrive at the actual consumption of electrical energy. On February 28, 1973 the report of the said Inspector was received and in the report it was, inter alia, reported that it had been established that the meter under test was geared for half the ratio for direct reading and that the metering equipment with Meter No. 546017 with C.T ratio 80:5 and the existing power transformer ratio of 6600:110 connected therewith was such that the units recorded by the meter had to be multiplied by two in order to arrive at the actual consumption of the electrical energy. In other words, to paraphrase the substance of the report, the claim of the undertaking that the actual meter reading had to be multiplied by two in order to arrive at the actual consumption of electric energy by the consumer was upheld in toto.
4. Two principal contentions were taken before the learned trial Judge. The first of them was that a large portion of the claim of the Undertaking was time-barred except that for the period of three years immediately preceding the demand. In Court the appellants offered to pay whatever amount would fall within this period of three years and therefore not time-barred. It was contended that under s. 24 of the Electricity Act the Undertaking was not entitled to disconnect the appellants' supply for non-payment of that part of the claim which was barred by the law of limitation. The further contention of the appellants was that as there was a bona fide dispute with regard to the date from which the new metering equipment was installed, the B.E.S.T Undertaking could not disconnect the supply under the provisions contained in s. 24(1) of the Electricity Act.
5. The learned trial Judge dealt with the latter contention first and observed that on reading the correspondence and the affidavits he was completely satisfied that there was no bona fide dispute existing between the parties as regards the date from which the new metering equipment was installed. We are in total agreement with this view and it may be fairly stated that counsel for the appellants did not press any such contention before us.
6. What was strenuously pressed was the first contention earlier mentioned, viz. that action under s. 24 of the Electricity Act was not warranted and detailed arguments were advanced on various aspects and facets of this submission.
7. In order to appreciate these several submissions reference may be made to some of the provisions of the electricity act which are relevant for our purposes. Section 22 refers to the obligation on a licensee to supply energy to every person within the area of supply who makes an application for such supply. Sections 22A and 22B confer power on the State Government to give directions to a licensee in regard to supply of energy to certain class of consumers, and the latter section confers power to control the distribution and consumption of energy. Section 23 prohibits the licensee from showing undue preference to any person in making any agreement for the supply of energy. We then come to s. 24 which is extremely material for our purposes and may therefore be fully set out; it reads as follows:
“24.—Discontinuance of Supply to Consumer Neglecting to Pay Charge.—
(1) Where any person neglects to pay any charge for energy or any sum, other than a charge for energy, due from him to a licensee in respect of the supply of energy to him, the licensee may, after giving not less than seven clear days' notice in writing to such person and without prejudice to his right to recover such charge or other sum by suit, cut off the supply and for that purpose cut or disconnect any electric supply-line or other works, being the property of the licensee, through which energy may be supplied, and may discontinue the supply until such charge or other sum, together with any expenses incurred by him in cutting off and re-connecting the supply, are paid, but no longer.
(2). Where any difference or dispute which by or under this Act is required to be determined by an Electrical Inspector, has been referred to the Inspector before notice as aforesaid has been given by the licensee, the licensee shall not exercise the powers conferred by this section until the Inspector has given his decision:
Provided that the prohibition contained in this sub-section shall not apply in any case in which the licensee has made a request in writing to the consumer for a deposit with the Electrical Inspector of the amount of the licensee's charges or other sums in dispute or for the deposit of the licensee's further charges for energy as they accrue, and the consumer has failed to comply with such request.”
8. Section 26 provides for meters. Some reliance was placed by counsel for the appellants on the provisions contained in sub-s. (6) of s. 26 and, therefore, sub-ss. (1) and (6) of the said section which alone were referred to may therefore be fully set out:
“26. Meters.—
(1) In the absence of an agreement to the contrary, the amount of energy supplied to a consumer or the electrical quantity contained in the supply shall be ascertained by means of a correct meter, and the licensee shall, if required by the consumer, cause the consumer to be supplied with such a meter:
Provided that the licensee may require the consumer to give him security for the price of a meter and enter into an agreement for the hire thereof, unless the consumer elects to purchase a meter….
(6) Where any difference or dispute arises as to whether any meter referred to in sub-section (1) is or is not correct, the matter shall be decided, upon the application of either party, by an Electrical Inspector; and where the meter has, in the opinion of such Inspector ceased to be correct, such Inspector shall estimate, the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time, not exceeding six months, as the meter shall not, in the opinion of such Inspector, have been correct; but save as aforesaid, the register of the meter shall, in the absence of fraud, be conclusive proof of such amount of quantity:
Provided that before either a licensee or a consumer applies to the Electrical Inspector under this sub-section, he shall give to the other party not less than seven days' notice of his intention so to do….”
9. It was urged on behalf of the appellants that s. 24 of the Electricity Act provided an alternative drastic and penal remedy or method which may be followed by a licensee in preference to or by way of an alternative to filing a suit. It was submitted that such a provision should be strictly construed and the construction which was submitted for our acceptance was that by such coercive method or power of with-holding electric supply, the licensee ought not to be allowed to recover old or state claims going back over a period of ten years when it was obvious that such claims could not have been recovered by the licensee fully by means of an ordinary civil suit. For the purposes of this argument concentration was lavished on the phrases “neglects to pay” and “charge or sum due from him”, and it was submitted that an amount, the recovery of which was barred by the law of limitation, viz. could not be properly regarded as ‘due’ by the consumer i.e the appellants to the licensee i.e the B.E.S.T Undertaking. It was further submitted that if the appellants bona fide disputed their liability, then there was no neglect on their part to pay the amount even if ultimately in the view of the Court the ground or the basis of that refusal to pay was found or held to be erroneous or incorrect.
10. In connection with the first head of this argument our attention was drawn to several decisions given by Courts applying ss. 433 and 434 of the Companies Act where the word ‘due’ was required to be considered in connection with a claim between the creditor of a company and the company. It was submitted that it was well-settled that a company could not be regarded as unable to pay its debt and therefore required to be wound up when the amount claimed by the creditor was in respect of or pertained to a time-barred claim. A number of authorities were cited in connection with this branch of the argument resting with M. Gordhandas & Co. v. M.W Industries . 1971 3 SCC 632, in which there is reference to an earlier Supreme Court decision in Amalgamated Commercial Traders Pte. Ltd. v. Krishnaswami . 1965 35 Comp. Cas. 456..
11. It was contended on behalf of the respondents that the discussion in these authorities, which was on the question of winding up of a company on the ground of non-payment of the debt due, which restricted the debts due to those which would fall within the period of limitation only, was entirely inappropriate to the statutory provisions under consideration, and we find considerable substance in this approach. For consideration of the financial solvency of an individual as also of a company, attention must be concentrated only on such claims of the creditors as would fall within the period of limitation, and other claims falling outside such period must be excluded from consideration for obvious reasons. Similar consideration would not necessarily apply to the statutory provisions with which we are concerned viz. sub-s. (1) of s. 24 of the Electricity Act. It appears to us that what is provided is not a method of recovery of any amount by the licensee but a provision whereby the licensee would be relieved of his obligation under s. 22 to supply electricity to a consumer who has not paid to the licensee the amount owed by that consumer to the licensee.
12. The learned trial Judge referred in connection with this branch of the argument to a decision of our High Court in Ramrao Raoji Palkar v. Amir Kasam Bhagwan* . 1955 58 Bom. L.R 284., where a division Bench of this Court had occasion to consider the provisions contained in s. 12(3)(b) of the Bombay Rent Act. The words which were being considered by the division Bench were ‘rent then due’ occurring in s. 12(3)(b) of the Bombay Rents, Hotel and Lodging House Rates Control Act, 1947. In the judgment Chainani, J. (as he then was) who spoke for the division Bench considered several meanings of the word ‘due’ to be found in Webster's and Murray's Dictionary, in Wharton's Law Lexicon and Stroud's Judicial Dictionary as also in other decisions and observed as follows (p. 287):
“The word ‘due’ is, therefore, used in two different senses. In some statutes it has been held to mean all moneys owed or payable, even though their recovery may be barred by the law of limitation. In other statutes, a more restricted meaning has been given to this word and that is, moneys legally recoverable or those which can be recovered by action.”
13. The question which was then considered by the division Bench was: which of these two meanings should be given to the word ‘due’ in s. 12(3)(b)? It considered and construed the provision to refer to all rent in arrears or outstanding, including rent which cannot be recovered through the process of the Court owing to the bar imposed by the Limitation Act. Thus, the wider meaning—the dictionary meaning—was applied in preference to the narrower meaning which had been found appropriate whilst applying some of the sections of the Companies Act (e.g s. 186 of the Indian Companies Act, 1913 = s. 469 of the Companies Act, 1956).
14. In a very recent decision of the Supreme Court viz. in K.G.U Trust v. Shri Ram Chandraji Mandir . 1978 1 SCC 44, the view of the above division Bench appears to have been approved though the Supreme Court was concerned not with the bombay rent act but with a similar enactment viz. U.P Urban Buildings (Regulation of Letting, Rent and Eviction) Act (XIII of 1972). Relevant observations are to be found in para 4 of the report.
15. It was submitted by counsel for the appellants that the meaning given to the word ‘due’ in these provisions under the Rent Act was on account of special considerations which he indicated and it was submitted that there were no such special considerations inherent in the provisions under the Electricity Act which would warrant the wider meaning being adopted in perference to the narrower meaning. His argument was based upon the general provision in the Transfer of Property Act by reason of which a landlord would be permitted to forfeit a lease on the ground of non-payment of rent (and presumably all leases would contain an express condition for this purpose). It was submitted that where a landlord took action by way of forfeiture of the lease on such ground and moved the Court to secure possession of the demised premises, s. 114 of the Transfer of Property Act conferred discretion on the Court to grant relief against forfeiture to the lessee if the lessee paid or tendered to the lessor the rent in arrears together with interest thereon and the full costs of the suit at the time of hearing of the suit. It was submitted that the scheme of these provisions under the Rent Act should be considered to be similar to this power of granting relief against forfeiture. It was further submitted that where such relief was required to be granted, the provision had to be construed in the manner in which it had been done, giving or adopting the wider meaning for the word ‘due’ as to be inclusive of all amounts due to the landlord including the amounts which were barred by the law of limitation inasmuch as it was a discretion to be exercised in favour of the tenant. It was submitted that there was no warrant for adopting any such construction for s. 24 of the Electricity Act. It would appear to us that s. 24 has to be properly appreciated in the context of the obligations cast and the restriction placed on the licensee under the provisions of the electricity act, which we have earlier referred to. Within the supply area the licensee is obliged to supply electricity on an application to any consumer and cannot discriminate between one consumer and another. The licensee is also obliged to follow certain directions given by the State Government as also made subject to the power of the State Government to control the distribution and consumption of energy within the area of the licence. Section 24 regulates the licensee's power to disconnect the supply to a consumer within this area of supply who has defaulted in respect of payment of amounts owing to the licensee and a further restriction is imposed on the licensee, which is that he can discontinue the supply only until such time as the charges or the sums due are not paid by the consumer together with reimbursement of the additional expenses incurred by the licensee for cutting off and reconnecting the supply. Immediately the charge or the sums due and these additional expenses are paid, the supply has to be restored to the consumer whatever be the nature of the default, the number of defaults or the period and extent of the default. We see no warrant in the light of these statutory provisions to read the word ‘due’ in the Electricity Act in the narrower sense viz. as only restricted to amounts within the period of limitation or which could be successfully claimed by a suit. In other words there is no legal basis shown for preferring the narrower construction to the ordinary construction—the wider one—which is in accordance with the dictionary meaning as set out in Ramrao Raoji's case.
16. It was submitted that the interpretation canvassed for by counsel for the appellants was more valid by reference to the language employed in sub-s. (1) of s. 24, which preserved the licensee's right to file a suit to recover the charges or sums due. It was argued that if in such suit the licensee can only recover the charges or sums within the period of limitation, these could be the only charges or sums (viz. those within the period of limitation) for the non-payment of which the electric supply could be cut off by the licensee. In our opinion, the argument is not well founded. It has to be provided that the right to discontinue the supply of electricity is without prejudice to the licensee's right to file a suit to recover the amounts, since by reason of disconnection of the supply the licensee will not necessarily obtain the amounts due from the consumer. It became necessary therefore to protect the licensee's right to recover such amounts by ordinary civil action and merely because in such an action the defendant to the suit i.e the consumer may have the defence of limitation open to any portion of the claim would not warrant such considerations being applied to the licensee's right of discontinuance of supply for non-payment of the amounts owed to the licensee. The provision contained in s. 24(1) which enables the licensee to discontinue electric supply to a particular consumer is mainly by way relieving of the licensee of the obligation on him to be found contained in s. 22 viz. to make supply of electricity on application to all consumers within the area of supply. Once the proper position is perceived, then there is no warrant for obliging the licensee to go on supplying electricity to a consumer who has not paid the amounts in respect of the supplies made to him in the past on the ground that if the licensee were to file a suit, the claim or part thereof would be barred by the law of limitation. The provision, in our opinion, would clearly warrant the wider meaning to be given to the word ‘due’ rather than the narrower meaning, as the wider meaning would be more in accord with the scheme of the statutory provisions under consideration as also with commercial honesty.
17. In this connection our attention was drawn repeatedly by counsel for the appellants to the policy underlying the Limitation Acts and it was submitted that it could not be regarded that such contentions or defences were merely technical or could be regarded as dishonest or improper. The policy of the Limitation Acts has been indicated in para 330 of Halsbury's Laws of England, third edn., vol. 24. It is unnecessary to lavish any time on this contention inasmuch as we have not adopted the wider meaning or rejected the narrower meaning of the word ‘due’ on the basis of any consideration that the defence by way of the bar of limitation ought to be regarded as dishonest or improper. Reading the statutory provisions together and in their correct perspective there is no warrant for considering the charge due as restricted to charge falling within the period of limitation and excluding the charge owing for any earlier period.
18. Before dealing with the second submission we may dispose of the argument based on the provisions contained in s. 26 which might seem to have a bearing both on the words ‘due’ and ‘neglects to pay’. It was submitted that the provisions contained in s. 26 make it abundantly clear that a claim can be made by the licensee or by the consumer only in respect of the dues for the six months prior to the date of the claim and not for any period prior thereto. This appears to us to be based on a mis-reading of the provisions contained in s. 26. If either the licensee or the consumer disputes the correctness of the meter, then it is true that s. 26 enables the dispute to be resolved by the Electrical Inspector but such right of correction is restricted to a period of six months. But that can have no bearing on the claim made by the licensee in the matter before us. Very briefly stated, the learned trial Judge rejected the argument on the simple basis that additional amounts for the eleven-year period were claimed not on the basis of a faulty meter but on the basis of failure to multiply the reading by two, which was an entirely different thing. That there was such a mistake was contended by the licensee and the Electrical Inspector (on a reference by the Court) held that the reading of the meter was required to be doubled in order to show the real consumption. Under s. 26 of the Electricity Act the restriction as to six months period does not seem to apply to such a claim made by the licensee.
19. This brings us to a consideration of the other branch of the argument, which was that there was no neglect on the part of the consumer i.e the appellants to pay the charge claimed by the licensee i.e the Undertaking and, therefore, action under s. 24 of the Electricity Act was not warranted. In connection with this branch of the argument our attention was drawn to several authorities, to which reference may now be made.
20. Counsel for the appellants drew our attention to several authorities both of the other High Courts and of the Bombay High Court and we shall first discuss three decisions of the Bombay High Court, one of which is unreported. The first of these decisions is Nagpur Corporation v. N.E.L & P. Company . [1958] A.I.R Bom. 498, S.C 60 Bom. L.R 1446.. In the said decision a dispute had arisen between the licensee company and the Nagpur Corporation concerning the supply of electricity by the company to the Municipality, which was, according to the municipality, by reason of the large difference between the consumption set out in the bills for public lighting submitted by the company and the consumption which was actually recorded in the meters. Mudholkar, J. speaking for the division Bench considered the provisions of s. 24(1) of the Electricity Act along with cl. XII of the schedule and observed that where, as in the case before the Bench, charges are claimed from a local authority and there was a dispute between the local authority and the electrical undertaking as to such amounts or charges, the matter was first required to be determined by an arbitrator under cl. XII. It was further observed that it is only after the arbitrator gave his award and determined what the charges due were that it would be open to the electrical undertaking to avail itself of the provisions of s. 24 of the Electricity Act. It is in this connection that the Court had occasion to consider the words ‘neglects to pay’. It was contended by the advocate for the Municipality relying upon the observations of Jessel M.R in In re London and Paris Banking Corporation6, that negligence in law means “omitting to pay without reasonable excuse. Mere omission by itself does not amount to negligence”. This appears to have been approved. It was held further by the division Bench that if there is a bona fide dispute between the licensee and the consumer as to what was payable, action under s. 24(1) could not be taken or threatened by the licensee. Our attention was drawn to observations to be found in para 34 of the report, where it is indicated that the powers under s. 24(1) must be regarded as very drastic and, therefore, strict compliance with the provisions of the sub-section was required.
21. The second Bombay decision, also reported, was M.S.E.B v. Madhusudandas . [1966] A.I.R Bom. 160, S.C 67 Bom. L.R 919.. The consumer in that case had entered into an agreement for supply and the licensee had agreed to supply electrical energy for a period of five years. Clause 20 of the agreement, however, provided that the rates were flexible in the sense that they were payable according to the tariffs fixed by the Board from time to time. The licensee purported to revise the charges and claimed higher amounts from the consumer. According to the consumer, refixing at a higher rate than the one indicated in the agreement between the parties was ultra vires and the claim for higher amounts was therefore resisted. On behalf of the consumer reliance was placed on cl. 30 of the agreement between the parties. According to the division Bench, cl. 30 was nothing but a corollary to the liability created between the parties under cl. 20. It was contended on behalf of the consumer that even if the consumer's interpretation of the agreement was incorrect and his contention as to the invalidity of the claim made by the licensee appeared to the Court as unsound, there was in fact a bona fide dispute between the parties when the consumer failed to pay for the supply of energy and if there was such bona fide dispute, the cutting off of the supply was unjustified. The Nagpur Corporation's case was considered and the view, that action under s. 24 would not be justified when there is a bona fide dispute between the parties i.e the consumer and the licensee, appears to have found favour with the latter division Bench also.
22. Our attention was also drawn by counsel for the appellants to an unreported desision of a single Judge of this Court (K.K Desai, J.) given in Famous Cine Laboratories and Studios Ltd. v. Municipal Corporation for Greater Bombay . 1972 O.C.J Miscellaneous Petition No. 167 of 1967, decided by K.K Desai, J., on June 21, 1972 Unrep.., where the licensee had called upon the consumer to pay the amount of Rs. 17,552.17 after a lapse of more than five years, and it was held by the learned single Judge that it was difficult to accept the licensee's submission that the consumer had neglected to make payment of the amount claimed or that the dispute raised in regard to the balance of the amount claimed by the impugned notice was not bona fide. In the opinion of the Court, there was a genuine dispute raised on behalf of the consumer and, therefore, the consumer could not be regarded as guilty of negligence under s. 24(1) of the Electricity Act. In the view of the Court, therefore, the licensee i.e the B.E.S.T Undertaking was not entitled to discontinue the supply of electricity to the consumer as threatened in the notice impugned in the said petition. In all these authorities ‘negligence’ has been regarded as something more than a mere failure or omission to pay; and relief has been granted to the consumer where, in the opinion of the Court, the omission to pay was a result of the consumer raising a bona fide dispute with the licensee as to his liability to pay the amount demanded from him.
23. It was submitted by counsel for the appellants before us that the appellants had disputed their liability to pay and even if, in the opinion of the Court, the basis of the dispute may be regarded as erroneous, it could not be said that there was no bona fide dispute; and if that was so, the appellants could not be said to have neglected to pay the amount claimed. Before considering the correctness or the ramifications of such contentions further, brief reference may be made to decisions of other High Courts in India to which our attention was drawn at the Bar. These were principally cited to show that if the respondents No. 1 had attempted to recover the amount in a regular suit, a large portion of the claim i.e the claim for the period excluding the three years' period prior to the filing of such suit would have been time-barred. It was urged that the mere mistake of the licensee's employee could not extend the period of limitation in any way and the starting point of limitation for the purposes of the suit would run from the date of the supply and not from the date when the licensee became aware of the mistake. In connection with this aspect our attention was drawn to Naini Tal Hotel v. Municipal Board . [1946] A.I.R All. 502., and to Firm Attar Singh v. Amritsar Municipality . [1938] A.I.R Lah. 338.. It was submitted that what could not be recovered by a suit was being sought to be recovered from the consumer by the threat of disconnection. It was urged that if the consumer resisted the demand on the footing that the claim or a large part theeof was barred by the law of limitation (apart from raising other disputes), the consumer must be regarded as disputing the claim bona fide and therefore cannot be held to have neglected to pay the charges demanded. It was submitted that in these circumstances the licensee was not entitled to threaten to discontinue the electric supply.
24. It is true that in the two reported Bombay judgments the power of the licensee under s. 24 has been referred to or described as a drastic power and the Court has required strict compliance with the provisions of sub-s. (1) in order to uphold the threat given by the licensee. Although the consequence of non-supply of electricity to the consumer may be serious, particularly for a consumer such as the appellants, it must be borne in mind that this cannot be regarded in the same manner as or equated with penal or taxing provisions of a statute which, it is well settled, are required to be strictly construed. As already indicated, in a way the provision relieves the licensee from its obligation imposed by s. 22 of the Electricity Act which compels and obliges it to supply all consumers within the area of supply on necessary application being made. It is relieved of this obligation if the consumer has not paid to it the charges for the electricity supplied. If a claim is made for such charges and if it is found that the reasons offered by the consumer are not genuine but may be regarded as indicative of a mere desire not to pay, the dispute raised by the consumer ought not to be regarded as bona fide and the failure to pay in that particular case must be held as equivalent to ‘neglect to pay’. Mr. Singhvi rightly contended that the Court in each case will have to scrutinise the attitude of the consumer and consider the reasons given by him to the licensee for not meeting with the demand made by the licensee. As indicated in the earlier part of this judgment, the Undertaking by their letters dated May 4, 1972 and July 13, 1972 gave full explanation in respect of the amounts claimed from the appellants for the period April 17, 1961 to January 31, 1972. By their letter dated May 31, 1972 the appellants characterised the demand as illegal and unjustified and sought time to check up and verify the claim. After receipt of the letter dated July 13, 1972, which gave all the necessary details, the appellants did not seek any explanation or clarification but only sought time on account of labour trouble at their factory and even after the impugned notice was given, the appellants by their letter of November 3, 1972 characterised the Undertaking's letter of July 13, 1972 as containing various irrelevant facts. In their letters the appellants have gone on denying that any meter was changed on April 17, 1961, a fact which was not alleged in these terms by the Undertaking. The reason for the denial is obvious and that was to bring the dispute within the four comers of s. 26 of the Electricity Act. Again, in their letters as well as in the petition the appellants contended that the whole of the claim was barred by the law of limitation. In our opinion, the bar of limitation pleaded had no real relevance but the point is being emphasised to indicate the attitude of the consumer when the consumer ought to have been aware that a part of the claim (of which a full statement was explained) was patently and obviously within time. What then must be the reason why the entire claim was characterised as barred by the law of limitation? The reason must be to allege subsequently that there is a dispute and to contend that since there was a bona fide dispute the electric supply could not be disconnected. We have a somewhat curious situation here. Detailed explanations are sent by the Undertaking explaining the basis of its claim; in reply the letter containing the explanation is characterised by the consumer as containing irrelevant allegations. It is obvious that the whole claim cannot be time-barred and a part of the same at any rate must be within time; the consumer describes the whole claim as time-barred. When to this is added the entirely frivolous discussion regarding the replacement of the meter, which is not what was claimed by the Undertaking but something totally different which was fully explained by the letter of July 13, 1972, we are forced to conclude that the dispute raised on behalf of the consumer was neither proper nor bona fide. It is true that if a change in the rate of tariffs is opposed or if it is claimed that the higher claim on some footing contrary to the meter reading is controverted, the consumer cannot be said to have ‘neglected’ to pay the amount claimed although in the opinion of the Court its contentions could not be upheld or were ultimately found to be untenable. The initial contentions raised by the appellants before us would, in our opinion, not qualify to be considered as raising a bona fide dispute. If the consumer raises a bona fide dispute, he cannot be said to have ‘neglected’ to pay the amount claimed by the licensee. If the consumer merely disputes the amount or the claim but the dispute cannot be regarded as bona fide, then, the omission on the part of the consumer to pay the amount, the failure to pay the amount, must be regarded as ‘neglect’ to pay the amount, which neglect will entitle the Undertaking to take recourse to disconnection as provided by s. 24 of the Electricity Act. The analogy of the provisions under the Companies Act and the claim of the creditors of the company vis-a-vis the company sought to be wound up or considerations of provisions such as those contained in s. 186 of the Indian Companies Act, 1913, or in s. 469 of the Companies Act, 1956, are totally inappropriate in order to realise the true implication of the provisions contained in s. 24 of the Electricity Act.
25. Bearing in mind all the circumstances earlier indicated, it is not possible to accept the submission that the Undertaking had sought to exercise its powers under s. 24 wrongly, improperly, unreasonably or not bona fide. On the other hand, the dispute raised in the correspondence by the appellants cannot be characterised as bona fide and can indeed, if properly considered, be regarded as frivolous and vexatious.
26. It is in this sense that we must consider the two authorities of the Bombay High Court on which great reliance was placed by counsel for the appellants. The nature of the dispute raised in those cases was entirely different from the type of dispute raised in the matter before us as we have held that the contention that a part of the claim is time-barred was not open and could not be the subject-matter of a bona fide dispute. This is even apart from the fact that it was not the case of the appellants that a portion of the claim was time-barred but rather that the entire claim was time-barred.
27. We are, therefore, of opinion that both the conditions required for the licensee to take action under s. 24(1) of the Electricity Act are satisfied; these are; that there was a debt due from the appellants to the licensee and that the appellants had neglected to pay the amount which was owing. If that is so, the impugned notice dated October 31, 1972 cannot be characterised as contrary to law. It would follow that the same is not required to be quashed as alleged or for any other reason.
[The rest of the judgment is not material to this report.]
Alert