Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Village Panchayat, Dharna Wadhona Buzruk v. Commissioner, Nagpur Division

Bombay High Court
Sep 13, 1966
Smart Summary (Beta)

Structured Summary of the Opinion (Abhyankar, J.)

Factual and Procedural Background

This petition under Articles 226 and 227 of the Constitution challenges Notification No. C-27102-1686-VPT-64 published in the Maharashtra Government Gazette on December 2, 1965, purportedly issued under section 4(2) of the Bombay Village Panchayats Act, 1958. Petitioners are (1) the Village Panchayat for the local area comprising the villages Dharna and Wadhona Buzruk and (2) five individual members of that Panchayat. The notification purported to exclude Wadhona Buzruk from the combined Dharna-Wadhona Buzruk Panchayat for the establishment of a separate Village Panchayat for Wadhona Buzruk.

Relevant antecedent events in the record are: (a) a resolution passed on July 18, 1961 by the then Panchayat (reproduced as Annexure A) requesting separation of Wadhona Buzruk into a separate panchayat; (b) fresh elections in 1962 and a unanimous resolution on July 29, 1963 by the newly constituted Panchayat opposing separation and requesting continuation of the combined Panchayat; and (c) a later resolution on December 7, 1964 (Annexure C) reflecting the same view as 1963.

Petitioners contend that the notification was issued without consulting the Panchayat as required by section 4(2) of the Act. Respondent No. 2 (Zilla Parishad, Yeotmal) filed a return and defended the notification; respondent No. 5 (a member) also opposed the petition and filed a return supporting the notification. Respondent No. 4 supported the petition. Respondent No. 1 (the Commissioner of Nagpur Division), who signed the notification, filed no return and made no appearance.

Legal Issues Presented

  1. Whether the notification issued under section 4(2) of the Bombay Village Panchayats Act was valid where petitioners allege there was no consultation with the Panchayat concerned as required by the statute.
  2. Whether an earlier resolution (the 1961 resolution) in favour of creating a separate Panchayat for Wadhona Buzruk could substitute for contemporaneous consultation with the Panchayat as constituted at the time the notification was issued.
  3. Whether the exercise of power under section 4(2) is an administrative policy decision immune from judicial review (i.e., non-justiciable), as contended by respondents relying on authority.

Arguments of the Parties

Petitioners' Arguments

  • The notification of December 2, 1965 was issued without consultation with the Village Panchayat of Dharna-Wadhona Buzruk as required by section 4(2) of the Bombay Village Panchayats Act, 1958.
  • Because the notification has the effect of dissolving the existing panchayat and causing its members to vacate office (per the Act), the statutory consultation requirement is essential and was not met.

Contesting Respondents' Arguments (primarily Respondent No. 2 and Respondent No. 5)

  • There was no need for a fresh consultation since the 1961 resolution of the Panchayat had already accepted the desirability of splitting the two villages; no contrary indication was brought to the authorities.
  • The Standing Committee of the Zilla Parishad was consulted by Respondent No. 1 and accepted the change; therefore the procedural requirement is satisfied.
  • Respondent No. 1 must be presumed to have been aware of the 1961 resolution (pursuant to the rules requiring copies of proceedings to be forwarded), and that knowledge would suffice as compliance with section 4(2).
  • The decision is administrative in nature and, it was argued, not ordinarily justiciable under Articles 226/227; reliance was placed on Radeshyam v. State of M.P. (A.I.R. 1959 S.C. 107) for this proposition.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Radeshyam v. State of M.P. (A.I.R. 1959 S.C. 107) Support for the proposition that an administrative/policy decision may be ordinarily non-justiciable by certiorari (decision involved s. 53-A of the C.P. & Berar Municipalities Act). The court considered and distinguished this authority. It held that the power exercised under section 4(2) of the Bombay Village Panchayats Act is statutory and not merely administrative policy; therefore Radeshyam was not of assistance to respondents and did not preclude judicial review of compliance with statutory requirements.

Court's Reasoning and Analysis

The court's analysis proceeded in the following steps, reflecting only the reasoning contained in the opinion:

  1. The court rejected the contention that the power exercised under section 4(2) was a non-justiciable administrative policy decision. The court held that Respondent No. 1 acted under statutory powers and therefore must comply with the statute; any exercise in contravention of the statute is reviewable by the Court.
  2. The court examined the consequences of action under section 4 (and section 160) and emphasized the seriousness of those consequences: a panchayat previously in existence ceases to exist and all its members vacate office automatically when a notification reconstitutes a village. Because of these drastic effects, the statutory requirement to consult the panchayat under sub-section (2) of section 4 is of special importance.
  3. The petition contained a specific averment (para. 5) that the Panchayat was not consulted and was not granted hearing before the notification. The court observed that the only proper party to rebut that allegation was Respondent No. 1 (the authority required by law to consult the Panchayat). Respondent No. 1 filed no return and made no appearance; in that absence, the court found it impossible to hold the allegation refuted.
  4. The court considered respondents' alternative argument that the 1961 resolution (requesting separation) or the presumed presence of that resolution in official records obviated the need for fresh consultation. The court analyzed the phrase "the panchayat concerned" in section 4(2) and concluded it means the panchayat as constituted at the time the decision is required to be taken, not merely the legal entity in the abstract.
  5. The court reasoned that the composition of a Panchayat changes over time (e.g., due to elections) and a prior resolution cannot bind a subsequently constituted body for all time. Therefore, a prior resolution cannot substitute for the required contemporaneous consultation with the then-existing Panchayat.
  6. The court further held that a presumption that records (such as the 1961 resolution) had been forwarded to successor bodies was not reliable evidence of actual consultation by Respondent No. 1. Even if the Zilla Parishad had reference to the earlier resolution, that reference could not substitute for the statutory duty of Respondent No. 1 to consult the Panchayat when action was being taken under section 4(2).
  7. The court clarified the content of the consultation requirement: consultation must be with the Panchayat as a whole — i.e., the totality of its membership — not merely with office-bearers or selected representatives. This conclusion was supported by principles of natural justice and by the significant impact of the decision on the status of members.
  8. Because the record did not show that Respondent No. 1 independently gave the Panchayat or its members an opportunity to express their views when the notification was proposed or initiated, the court found a "serious lacuna" in the exercise of the statutory power under section 4(2).
  9. On that basis, the court held that the notification was not validly issued insofar as it affected the Dharna-Wadhona Buzruk Village Panchayat.

Holding and Implications

Holding: The petition is allowed. The notification dated December 2, 1965 (No. C-27102-1686-VPT-64) is quashed so far as it affects the Village Panchayat of the local area comprising Dharna and Wadhona Buzruk. Petitioners are entitled to costs against Respondent No. 2. The Court ordered that "the consequences of the quashing of the notification will follow in due course."

Implications:

  • Direct effect on the parties: The challenged notification is declared ineffective with respect to the Dharna-Wadhona Buzruk Panchayat; the petitioners succeed and receive costs against Respondent No. 2 (Zilla Parishad, Yeotmal).
  • The decision emphasizes that statutory consultation requirements (here, s. 4(2) of the Bombay Village Panchayats Act) must be complied with in substance and not satisfied by reliance on antecedent resolutions or indirect references in other bodies' records; consultation must be with the Panchayat as constituted at the time the decision is taken.
  • The court distinguished prior authority relied upon by respondents (Radeshyam) and clarified that an exercise of statutory power with prescribed procedural requirements is subject to judicial review; the opinion does not purport to establish a broader new legal doctrine beyond the statutory interpretation and application in this case.

Result declared in the opinion: "Petition allowed." (Final line: "Petition allowed.")

Show all summary ...

Abhyankar, J.:— This petition under arts. 226 and 227 of the Constitution raises an interesting question of the interpretation of s. 4 of the Bombay Village Panchayats Act, 1958.

2. Petitioner No. 1 is a villlage panchayat of the local area of villages Dharna and Wadhona Buzruk, while petitioners Nos. 1(a) to 5 are some of the members of this Village Panchayat. They have challenged the validity of a notification No. C-27102-1686-VPT-64, published in the Maharashtra Government Gazette, dated December 2, 1965, in Para-1-A of the Nagpur Supplement, page 619. The relevant notification is as follows:

No. C-27102-1686-VPT-V-64.—In exercise of the powers conferred by sub-section (2) of section 4 of the Bombay Village Panchayats Act 1958 (Bom. III of 1959), read with Government Notification Local Self-Government and Public Health Department, No. VPS-2459-P, dated the 25th May 1959, and after consultation with the Standing Committee of the Yeotmal-zilla Parishad and the Village Panchayats of (1) Wagada, (2) Dharna and (3) Sakhi Bk. in Pandharkaoda Panchayat Samiti in Kelapur Taluka of the Yeotmal district, I, M.N Desai, Commissioner, Nagpur Division, Nagpur, with effect from the date of publication of this notification in the official Gazette, hereby exclude from the villages shown in column (3) of the following table, the local area comprising the villages shown in column (4) of the table for establishment of separate Village Panchayats:—

Serial No. Name of Group Village Panchayat Jurisdiction over villages Villages to be excluded from the Group Village Panchayat Serial No. Name of Village Panchayat to be established/reconstituted Jurisdiction (1) (2) (3) (4) (5) (6) (7) X X X X X X X 2. Dharna 1. Dharna 2. Wadhona Bk. … Wadhona Bk. 3 Dharna 1 Dharna X X X X X X X”

3. The notification purports to have been issued under s. 4(2) of the Bombay Village Panchayats Act, 1958. The grievance of the petitioners is that they have not been consulted before the issue of the notification as required by the provisions of s. 4 and, therefore the notification is bad. Under the Bombay Village Panchayats Act, power is given to the State Government to constitute a panchayat for every village. Under s. 2(24) of the Act, a “village” is defined as “any local area declared to be a village under section 4 or deemed to be a village.” Under s. 4(1) of the Act, the State Government is empowered to declare any local area comprising a revenue village or a group of revenue villages or hamlets forming part of a revenue village, or other such administrative unit or part thereof, to be a village. Thus, under the statutory definition of a village, area comprising more than two revenue villages can form a unit as a village panchayat under the Act. Such a village panchayat was constituted for the two villages of Dharna and Wadhona Buzruk, combined under one unit of administration as a village panchayat.

4. In 1961, to be precise, on July 18, 1961, the then members of the Village Panchayat of Dharna-Wadhona Bk. passed a resolution, which has been reproduced by the petitioners as Annexure A, resolving that in view of the demand of the villagers of Wadhona Bk. Wadhona Bk. village may be made separate and accordingly a request was made by the Village Panchayat to the State Government. In other words, by this resolution, petitioner No. 1, the Village Panchayat recommended to the State Government that villages Dharna and Wadhona Bk. should have separate village panchayats.

5. Fresh elections seem to have taken place when a new body came into office in 1962. On July 29, 1963, the Village Panchayat passed a unanimous resolution expressing an opinion exactly contrary to that expressed by their resolution of 1961. By this resolution, the Panchayat resolved that it was the desire of villagers of both the villages, i.e Dharna and Wadhona Bk., that they should continue to form one village panchayat and it was resolved that this decision should be brought to the notice of the Government. A similar resolution was also passed subsequently on December 7, 1964, of which Annexure C is a copy.

6. The petitioners' grievance is that inspite of these later resolutions, respondent No. 1, i.e the Commissioner of Nagpur Division, had issued the notification reproduced above but without consulting either petitioner No. 1 the Village Panchayat or any of its members, who are affected by the notification.

7. The petition is contested pricipally by respondent No. 2, i.e the Zilla Parishad, Yeotmal, representing its Standing Committee. They have filed a return in this case, and the learned Additional Government Pleader supported the action of respondent No. 1 on their behalf. A return is also filed on behalf of respondent No. 5, who is a member of the Village Panchayat. Respondent No. 4 has supported the cause of the petitioners while respondent No. 5, who is also a member, has opposed the petition. It may be noted at this stage that respondent No. 1 has not filed any return nor any appearance is entered on behalf of respondent No. 1.

8. In supporting the action of respondent No. 1, respondents Nos. 2 and 5 contend that there was no occasion, nor any necessity, for a fresh consultation with any of the petitioners inasmuch as the resolution of 1961 had already accepted the desirability of splitting up of the two villages into two separate units as panchayats and there being no contrary indication before the authorities, the action taken by respondent No. 1 is not open to challenge on any ground. The Standing Committee of the Zilla Parishad, respondent No. 2, was consulted by respondent No. 1, and they have accepted the desirability of splitting up of the two villages into two separate panchayats inasmuch as the villagers of Wadhona Bk. desired a change in their status.

9. It is further urged on behalf of the contesting respondents that at no stage petitioner No. 1 or any of the other members, who are now making a grievance, brought to the notice of respondent No. 1 that they did not desire the splitting up of the two villages into two separate panchayats and if respondent No. 1 acted on the basis of the resolution of 1961, that would be adequate compliance with the provisions of s. 4(2) of the Bombay Village Panchayats Act. In this connection, it is pointed out that respondent No. 1 must be presumed to be aware of the resolution of 1961, because, under rule 40 of the Rules framed for regulating the meetings of the village panchayats under the Bombay Village Panchayats Act, a copy of the proceeding had to be submitted to the Chairman of the District Village Panchayat Mandal within seven days of the meeting. A presumption would, therefore, arise that a copy of the resolution of 1961 must have been submitted to the District Village Panchayat Mandal as required by the rules, Under the Bombay Village Panchayats Act a District Village Panchayat Mandal was to be constituted under s. 134 of the Act. There being a presumption of official acts being done properly and regularly, if such a resolution had been forwarded to the District Village Panchayat Mandal, that resolution would, in its turn, form part of the record of the Zilla Parishad. There is a reference to this resolution in the proceedings before the Standing Committee when the Standing Committee was consulted by respondent No. 1 with regard to the proposal for reconstitution of the Panchayats. In this manner respondent No. 1 being made aware of the opinion of the Panchayat as reflected in its resolution of 1961, there was neither any necessity nor occasion for a further consultation and, in absence of any complaint to the contrary, the exercise of power by respondent No. 1 cannot be challenged. It is further submitted that the scheme of the village panchayats act is that every village should have its own panchayat. In pursuance of this objective, steps are being taken to give a separate panchayat for each village as a unit of village administration and, in the course of implementation of this policy, if action is taken by respondent No. 1 in this case, it cannot be seriously objected to. It is claimed that the decision is an administrative decision and is not open to challenge nor justiciable in these proceedings under art. 226 or 227 of the Constitution. Support is claimed for this latter contention from a decision of the Supreme Court in Radeshyam v. State of M.P . [1959] A.I.R S.C 107.

10. After hearing the contesting respondents, we have come to the conclusion that the objections are not well founded. It will be convenient, to deal with the last objection to the jurisdiction of this Court. The power that is vested in the State Government and delegated to respondent No. 1 in this case under s. 4(2) of the Bombay Village Panchayats Act is not an exercise of an administrative power. Respondent No. 1 is acting under a statute and is bound by the terms of the statute. We are unable to appreciate how in exercising the power under any provision of the statute, any question of policy, other than that laid down by the Legislature, is germane or claim protection from scrutiny. If the exercise of the statutory power is shown to be in contravention of the provisions of the statute, persons affected by such exercise of the power are certainly entitled to invoke the jurisdiction of this Court. The matter which went before the Supreme Court was under s. 53-A of the C.P & Berar Municipalities Act, and, as far as we can see, what seems to have been decided is that, when power is vested in an authority to take a policy decision in respect of exercise of an administrative power, it is not vulnerable nor is it justiciable ordinarily by a writ of certiorari. We do not, therefore, think that the decision on which reliance is placed is of any assistance to the respondents.

11. The consequences of action under s. 4(2) of the Bombay Village Panchayats Act are provided for in s. 160 of that Act. That section is as follows:

“160. (1) Where any local area comprised within the limits of a village ceases to be a village and is declared as constituting two or more new villages by virtue of a notification under section 4, with effect from the date on which such notification is issued (hereinafter in this section referred to as ‘the said date’), the following consequences shall ensue, that is to say,—

(a) the panchayat constituted in respect of such local area shall cease to exist and all the members of the panchayat shall vacate office;

(b) until panchayats are constituted for the new villages, the State Government shall appoint an administrator or administrators to exercise the powers and perform the functions of the panchayat for each of the new villages;

(c) the unexpended balance of the village fund and all the property (including arrears of rates, taxes and fees) belonging to such panchayat shall vest in the new panchayat in such proportion and in such manner as the State Government may direct;

(d) the officers and servants of such panchayat shall be allocated by the State Government to the new panchayats in such manner as the State Government may direct;

(e) subject to clauses (a) to (d) the provisions of section 159 shall mutatis mutandis apply to the administrator or administrators of the new panchayats and their members.

(2) Within one year of the said date the panchayats for the new villages shall be constituted in accordance with the provisions of this Act.

(3) If any difficulty arises in giving effect to the provisions of section 159 or this section, the State Government may, by order, as the occasion may require, do anything which appears to it to be necessary to remove the difficulty.”

12. It will be seen that one of the effects of a decision to reconstitute or making a declaration under s. 4 is that a panchayat previously functioning as constituted prior to the action taken under s. 4, ceases to exist and a further effect of such notification is that all the members of that panchayat vacate office automatically. Thus, a notification under s. 4(2) of the Bombay Village Panchayats Act has a two-fold effect; Firstly, the ex-panchayat in respect of which a notification is issued ceases to exist as a legal entity. The second and more serious effect is that the members constituting that panchayat automatically vacate office. The notification thus affects the status of the members as representing their wards in the local body. It is precisely for this reason, in our opinion, that the Legislature has made advisedly a provision in sub-s. (2) of s. 4 for consulting the panchayat concerned before action is taken under s. 4(2) of the Bombay Village Panchayats Act.

13. There is a specific averment in para. 5 of the petition that the Panchayat was not consulted nor was it granted a hearing to place its point of view before the notification, was issued. This allegation raises a question of fact, viz. whether, in fact, petitioner No. 1 the panchayat was or was not consulted by respondent No. 1. The only party which could have made any statement in reply to this averment would be, with propriety, respondent No. 1. It is respondent No. 1 who is required by law to consult the Village Panchayat, and we are constrained to observe that, in absence of any return being filed or any appearance being entered on behalf of respondent No. 1, it is not possible to hold that this allegation has been refuted as required by law. It is true that respondent No. 2 has denied this allegation. But respondent No. 2 is not an authority which would have any direct knowledge about the fact of consultation by respondent No. 1 with petitioner No. 1, the Panchayat. The alternative argument that the resolution passed by petitioner No. 1 in 1961 and a knowledge of that resolution would be adequate compliance with the requirements of sub-s. (2) of s. 4 is also not tenable. Section 4(2) speaks of consultation with “the panchayat concerned.” The panchayat concerned will not only mean the panchayat with respect to which the action is proposed to be taken but the panchayat as constituted at the time when consultation has to be made. It is true that the Village Panchayat constituted under the Act is a legal personality or entity and is having a perpetual seal and succession. But it is well-known that the complexion of the panchayat will change from time to time and especially when new bodies come in. There is nothing like un-alternability of decisions of the deliberative body like panchayat constituted as a corporation. It will be, therefore, difficult to uphold the contention that, because of the resolution of 1961, the Panchayat was bound by the resolution for all time to come. We put it to the learned counsel for respondent No. 2 whether a resolution of a prior date could be operative and held good against the Panchayat for all time to come. The resolution may be good in the light and context of circumstances then prevailing. But, if there is nothing in law preventing the Panchayat from coming to a contrary or different conclusion, then we fail to see why respondent No. 1 was not liable to consult the Panchayat when action was actually proposed to be taken, i.e when the notification in dispute was about to be issued or action was initiated for issuing of such a notification.

14. We are also not satisfied that there is any reliable evidence on record to presume that the resolution of 1961 passed by petitioner No. 1 was within the cognizance of respondent No. 1. The process of reasoning by which such an argument is pressed before us is as follows: The resolution passed in 1961 must, in the ordinary circumstances and in compliance with the rules of meetings then prevailing, have been forwarded to the District Village Panchayat Mandal. The District Village Panchayat Mandals, which were functioning under s. 134 of the Panchayat Act, were abrogated as a result of the Maharashtra Zilla Parishads Act which came into force on May 1, 1962. Zilla Parishad is the succeeding district unit of local administration and should be taken as a successor of the District Village Panchayat Mandal under s. 134 of the Bombay Village Panchayats Act. If the records of the District Village Panchayat Mandal could properly be sent and might have been sent along with the resolution of the Panchayat which must have been sent through the Panchayat Mandal to the Zilla Parishad, the Zilla Parishad would have access to such resolution. Support is sought for this submission on the basis of reference to this resolution passed by petitioner No. 1, in the proceedings of the Standing Committee of the Zilla Parishad (respondent No. 2), which assented to the change proposed by respondent No. 1. Respondent No. 2 has not filed a copy of those proceedings before us. But even assuming that there is a reference to the resolution of 1961 passed by petitioner No. 1 Panchayat agreeing to split up the two villages, we fail to see how a mere reference to that resolution is a substitute of the requirement of consultation with the Panchayat by respondent No. 1 when he proposed to take action under s. 4(2) of the Act.

15. The Panchayat concerned which ought to be consulted is the Panchayat as constituted on the date the decision is required to be taken by respondent No. 1. Under s. 9 of the Bombay Village Panchayats Act, the Panchayat is made a corporate body; but under s. 10 what shall comprise or consist of the panchayat is provided, and under s. 10(1)(a) a panchayat shall consist of such number of members as the Collector may determine. So all members of the panchayat are a vital and integral part of the panchayat itself When any action is proposed to be taken under s. 4(2), it has its impact, on the status of the members constituting the panchayat. If for nothing else, at least in obedience to the well accepted principles of natural justice, the members, who constitute the panchayat and are affected by the action, have a right to be consulted. Consulting the panchayat does, not mean consulting office bearers or any selected representative, but the panchayat as a whole comprising of totality of its membership. An opportunity must, therefore, be given to all the members comprised in the panchayat to express their opinion with respect to the proposal initiated by respondent No. 1 under s. 4(2) of the Bombay Village Panchayats Act. If that has not been done and we must observe in this case that, that is not complied with in this case, then an action taken under s. 4(2) is liable to be struck down as an exercise of power without compliance with the requirement of the section itself.

16. Even in absence of a provision like s. 4(2) regarding consultation, one should have thought that in exercise of a power under the Act, the authority exercising the power would normally consult the persons affected by the exercise of such power. This principle is a salutary principle in dealing with representative institutions and that has been recognized by the Legislature in the provision it made in s. 4(2). The requirement of this important provision, therefore, cannot be either ignored or whittled down by following a circuitous procedure. In the instant case, it is not even averred by the authority concerned, that such a procedure was followed. The mere statement in the notification that the power is exercised after consultation with the Panchayat concerned, will be no answer to the charge when there is a specific averment that no such consultation had taken. From the facts disclosed on record also, it does not appear that respondent No. 1 independently, at any time, gave an opportunity to petitioner No. 1 and its members constituting the Panchayat to say what they wanted with respect to the proposal for splitting up the two villages. In view of the serious lacuna in the exercise of the power, it must be held that the notification concerning these villages is not validly issued and is ineffective. We accordingly quash that notification, so far as it affects Village Panchayat of local area of Dharna and Wadhona Bk. The petition is allowed. In the circumstances, the petitioners will be entitled to costs from respondent No. 2. The consequences of the quashing of the notification will follow in due course.

17. Petition allowed.