G.V.P.R Engineers Limited v. Bharat Heavy Electricals Limited, Tamil Nadu And Another

Andhra Pradesh High Court
Nov 12, 1999
Smart Summary (Beta)

Structured Summary of the Opinion

Factual and Procedural Background

Bharat Heavy Electricals Limited (BHEL), a Government of India undertaking, was commissioned by the National Thermal Power Corporation (NTPC) to carry out civil and related works for the Simhadri Thermal Power Project. Certain items of the work, including the "Raw Water Reservoir," were to be contracted out. The petitioner, G.V.P.R Engineers Limited, was one of the tenderers for the Raw Water Reservoir item.

Initially, tenders were invited and eight tenderers (including the petitioner and respondent No. 2) were short‑listed. The first set of bids was opened on 5-5-1999, with respondent No. 2 then lowest at Rs. 32,49,24,300 and the petitioner at Rs. 44,47,83,334. The process was not proceeded with and a limited fresh tendering exercise was conducted among the eight shortlisted tenderers; those bids were opened on 21-9-1999.

On 21-9-1999 respondent No. 2 quoted Rs. 36,98,99,190 while the petitioner quoted Rs. 41,18,83,992 and offered a 9.9% discount if work was allotted within two weeks (discounted figure Rs. 37,07,36,781.20). Respondent No. 1 (BHEL) awarded the contract to respondent No. 2—communication of award by telefax on 5-10-1999—and respondent No. 2 took mobilisation steps thereafter.

On 22-9-1999 (the day after the second bids were opened) the petitioner submitted a representation asserting a bona fide mistake in its tender: that rates for item 5 (Geotextiles) and item 7 (HDPE Film) had been transposed and requesting rectification by interchanging the rates. The petitioner reiterated and expanded this request by a letter of 5-10-1999, alleging among other things that respondent No. 2's earlier samples had failed tests and that BHEL's limited re-tendering afforded respondent No. 2 an opportunity to escape consequences of defective material while the petitioner should be permitted to rectify its bona fide mistake. The petitioner sought an order directing respondent No. 1 to consider and grant the requested interchange of rates and, consequently, to award the contract to the petitioner (or otherwise allow consequential relief).

The petitioner filed the present writ petition challenging BHEL's conduct and seeking judicial relief under Article 226 of the Constitution. The writ petition was filed after the contract had been awarded to respondent No. 2 (the petition was filed on 11-10-1999 as noted in the opinion).

Legal Issues Presented

  1. Whether the 1st respondent (BHEL) ought to be directed to permit rectification by interchanging the rates quoted by the petitioner for items Nos. 5 and 7 and, on that basis, award the Raw Water Reservoir contract to the petitioner.
  2. Whether the action of the 1st respondent in permitting the 2nd respondent to submit a revised tender (the limited re‑tendering among eight shortlisted tenderers) was illegal.
  3. Whether the refusal to permit the petitioner's rectification constitutes arbitrary, irrational or extraneous State action warranting interference under Article 226 of the Constitution of India.
  4. Whether the limited re-tendering process should be characterised as negotiations which obligated respondent No. 1 to secure the maximum advantage for BHEL and, on that basis, permit the petitioner's requested rectification.

Arguments of the Parties

Petitioner's Arguments

  • The petitioner asserted that a bona fide mistake had occurred: the rates for item 5 (Geotextiles) and item 7 (HDPE Film) in its tender were transposed, and requested that the rates be interchanged, which—after application of the offered discount—would have rendered the petitioner's bid the lowest.
  • It was submitted that respondent No. 1, as a State entity, is bound by constitutional and public law obligations to act rationally and fairly and to obtain the best possible bargain; fairness required permitting rectification of the manifest mistake.
  • The petitioner argued that the limited re‑tendering among the eight shortlisted tenderers was, in essence, negotiations and that in that context respondent No. 1 should have considered permitting the rectification so as to secure greater advantage (noting a claimed gain to BHEL of Rs. 1,06,89,180 if the petitioner's corrected bid had been accepted).
  • The petitioner relied on authorities (cited in the petition) to support the submission that State contracting authorities must act to secure best value and fair opportunity (cases cited in the petition: Food Corporation of India v. M/s Kamdhenu Cattle Feed Industries; Raunaq International Limited v. I.V.R Constructions Limited; Punjab Communications Limited v. Union of India).

Respondent No. 1 (BHEL)'s Arguments

  • Equal opportunity was afforded to all eight shortlisted tenderers in the limited re‑tendering; permitting respondent No. 2 to submit a revised tender was not illegal because every shortlisted bidder had the same opportunity.
  • The relief claimed was unsustainable because the contract had already been awarded to respondent No. 2 (award communicated on 5-10-1999) and the writ petition was filed subsequently.
  • BHEL explained that due to wide variance in quoted rates for Geotextile and HDPE Film components, it had requested samples and tested respondent No. 2's samples (which failed to meet technical requirements). To ensure conformance, BHEL identified acceptable supply agencies/products in consultation with NTPC and asked all eight tenderers to submit revised bids with those specified suppliers; this process was documented (letter dated 7-9-1999 with annexure specifying products).
  • BHEL contended the petitioner's allegation of an inadvertent transposition was misconceived and made with ulterior motive. The petitioner had quoted other rates in the initial bid and had not sought rectification earlier (after the first bid opening or on the date of the second bid opening). The petitioner's representations came only after it learned it was not the lowest bidder on re‑tendering.
  • Allowing rectification after bids are opened would undermine the sealed tender system; the petitioner's attempt was characterised as an effort to subvert that policy and gain an unfair advantage.
  • BHEL maintained there was no error, irrationality, arbitrariness or extraneous consideration in awarding the contract to respondent No. 2 and that no facts warranted judicial interference.

Respondent No. 2's Arguments

  • Respondent No. 2 reiterated the aspects urged by respondent No. 1 (BHEL) in opposition to the petitioner's case.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Food Corporation Of India v. M/S Kamdhenu Cattle Feed Industries, (1993) 1 SCC 71 : AIR 1993 SC 1601 Relied on by the petitioner to support the submission that State contracting authorities must act rationally, fairly and secure the best bargain; invoked in the context of judicial review of contractual decisions. The court recorded that the petitioner relied on this authority, but on analysis of the facts and applicable law the court found no principle from the petitioner's case or authorities warranting interference; the court did not accept the petitioner's claim for rectification.
Raunaq International Limited v. I.V.R Constructions Limited, (1999) 1 SCC 492 Relied on by the petitioner in support of submissions about the scope of public law obligations in tendering and contractual award processes. The court noted reliance on this case but determined, on the facts of the present matter, that there was no arbitrary or irrational conduct by respondent No. 1 to warrant interference despite the petitioner's reliance on such authorities.
Punjab Communications Limited v. Union of India, (1999) 4 SCC 727 Relied on by the petitioner to reinforce submissions concerning procurement law principles and fairness in awarding contracts by public authorities. The court acknowledged the citation but concluded that the factual matrix did not establish grounds for judicial intervention; the court dismissed the petition notwithstanding the cited precedents.

Court's Reasoning and Analysis

The court set out the governing principle of judicial review in the context of State contracting: while the lowest tenderer has no absolute right to have its tender accepted and the inviting authority has the power to reject tenders (or divide/award as it sees fit), such power cannot be exercised arbitrarily or irrationally and must rest on rational reasons. The object of tendering is to afford equal opportunity, secure competitiveness, obtain the most advantageous rate while ensuring required quality and timely execution.

Applying these principles to the facts before it, the court proceeded as follows:

  1. It examined the sequence of events: initial shortlisting and testing of samples, identification of acceptable suppliers in consultation with NTPC, the limited re‑tendering among the eight shortlisted bidders with specified suppliers (letter dated 7-9-1999), opening of revised bids on 21-9-1999, and the award communicated on 5-10-1999.
  2. The court observed that respondent No. 1 had required samples for testing because of significant variance in earlier rates and to ensure technical conformity; respondent No. 2's samples had been tested and found not to conform, which prompted BHEL to identify acceptable suppliers and seek revised bids from all shortlisted tenderers.
  3. The court considered the timing and motive of the petitioner's representations: they were made only after the petitioner realized it was not the lowest bidder on the re‑tendering (first representation dated the day after the second opening). The petitioner's representations seeking rectification were therefore seen by the court as attempts to take advantage of information gained after bids were opened.
  4. The court emphasized the policy of sealed tenders: permitting rectifications based on post-opening information would undermine that policy and could amount to an unfair advantage; the petitioner had not sought any correction earlier (after the first bid-opening or at the time of the second opening).
  5. The court balanced competing public interests: while further deliberations may sometimes secure a more advantageous price, endless negotiations undermine expedition in execution. Respondent No. 1 was found to be entitled to consider time and expedience as material public interest factors and to close the negotiation/deliberation process at an appropriate point.
  6. On the record, the court concluded that BHEL's refusal to accept the petitioner's belated request for rectification and its decision to award the contract to the then lowest tenderer (respondent No. 2) could not be characterized as arbitrary, irrational or extraneous conduct warranting judicial intervention.

The court therefore found no legal principle or factual basis in this case that would justify setting aside the award or directing rectification of the petitioner's tender.

Holding and Implications

HOLDING: The writ petition is DISMISSED. No costs.

Implications and direct consequences based on the opinion:

  • The contract award to respondent No. 2 (communicated on 5-10-1999) stands; the court declined to direct respondent No. 1 to permit interchange of rates in the petitioner's tender or to award the work to the petitioner.
  • The court found that the respondent No. 1's conduct in permitting the limited re‑tendering and subsequently awarding the contract did not exhibit arbitrariness or irrationality warranting interference under Article 226.
  • The opinion did not announce or establish a new legal principle; the court applied established tendering and public‑law principles (equal opportunity, non‑arbitrariness, and the public authority's discretion to balance price and expedition) and concluded that those principles did not require intervention on the facts of this case.
Show all summary ...

1. Bharat Heavy Electricals Limited, (BHEL), Government of India undertaking, has been commissioned by the National Thermal Power Corporation (NTPC) to undertake certain civil and other works for the Simhadri Thermal Power Project.

2. Some of the items of the work undertaken by the BHEL have been earmarked for contracting out to others. One of the items of such work is “Raw Water Reservoir”.

3. The petitioner G.V.P.R Engineers Limited, is one of the tenderers for this item of work. Aggrieved by certain developments to which reference would be made hereinafter, the petitioner has filed the present application seeking that this Court direct the 1st respondent to consider and grant the request of the petitioner contained in representations dated 22-9-1999 and 5-10-1999 regarding interchange of the rates quoted by the petitioner for items Nos. 5 and 7 of the Tender Schedule as regards the work relating to Raw Water Reservoir Tank, tender specification No. BHEL:PS:SCT:809, and thereupon award the contract of work relating to raw water reservoir to the petitioner, if necessary, by declaring that the action of the 1st respondent in permitting the 2nd respondent to submit a revised tender for the said work, is illegal and consequently direct the 1st respondent to award the contract to the petitioner as the rates quoted by the petitioner are the lowest and allow all consequential benefits.

4. At one stage, Sri E. Manohar, learned senior Counsel appearing for the 1st respondent BHEL, has faintly sought to contend that the extant general principles contouring judicial review of contractual relations in which the State is one of the parties, is inapplicabie to the present factual scenario since BHEL, though a State, is not directly entering into contractual relationships with private individuals, but is in effect sub-contracting a part of the work in respect of which it itself has entered into a contract with another viz., NTPC. This contention has, however, not been pursued further and the principal debate has proceeded on merits of the respective contentions and thus this Court is relieved of the obligation to adjudicate this nuance of the principle of judicial review of contractual relations to which the State is a party.

5. The established factual scenario relevant to the lis in issue is as under:

(a) The disputant area pertains to the item of work-Raw Water Reservoir.

(b) On initial invitation to tender for the said work by the 1st respondent, inter alia, the petitioner and the 2nd respondent submitted their bids for which the last date of submission of tender was 26-6-1998. The bids were opened on 5-5-1999 and the 2nd respondent was found to be the lowest of the 8 tenderers shortlisted, having quoted an amount of Rs. 32,49,24,300/- as against that of the petitioner at Rs. 44,47,83,334/-. The process was however, not proceeded with and a fresh, though limited, tendering process was initiated by the 1st respondent by giving tender schedules to the shortlisted 8 tenderers Bids, pursuant to this process, were opened on 21-9-1999.

(c) In the bids opened on 21-9-1999 the 2nd respondent quoted Rs. 36,98,99,190/-, whereas the petitioner quoted Rs. 41,18,83,992/- and has also offered a discount of 9.9% on the total value, if the work were to be allotted within a period of two weeks. The value of the quotation of the petitioner, on the application of the discount, would come to Rs. 37,07,36,781.20ps.

(d) Pursuant to the opening of the bids on 21-9-1999, the bid of the 2nd respondent being the lowest, the contract was awarded to the 2nd respondent on 5-10-1999 communicated by a Telefax, pursuant to which the 2nd respondent sent a communication on 6-10-1999 appointing a Project Manager. Thereafter, the 2nd respondent entered into an agreement and proceeded to take various steps to execute the work, including mobilisation of resources for distributing the work, entering into memoranda of understanding with suppliers and the like.

(e) A day after the opening of the bids, on 22-9-1999 the petitioner submitted a representation to the Senior Deputy General Manager (Contracts) of the 1st respondent stating that in the tender submitted on 20-9-1999 the petitioner's Engineer has entered item-5 (Geotextiles) at Rs. 135/- per Sq. Mt. and for item-7 (HOPE Film) at Rs. 54/- per Sq. Mt., by over-sight instead of the rates vice-versa for the above items. The representation further stated that it is an evident mistake as is apparent from the quotations received from the approved suppliers which are stated to have been enclosed and based on which the rates are said to have been quoted. The representation requested that the “bona fide mistake” may be ignored and the rates of Rs. 54/- for item-55 and Rs. 135/- for item-7 may be considered and that if so considered the petitioner's bid will come to Rs. 35,92,10,010.60 ps., after taking into account the offer of discount of 9.9%. The representation ended with a request that the petitioner's offer be accepted and work awarded in his favour. By yet another letter dated 5-10-1999 the theme contained in the earlier letter dated 22-9-1999 was reiterated. This later letter of 5-10-1999 further stated that petitioner has come to learn that the respondent No. 2 had earlier quoted based on samples of Geotextiles and HDPE Film furnished by the said respondent and the samples having been tested were found not to confirm to the technical norms and specifications and that by the respondent No. 1's conduct of permitting the limited re-tendering the respondent No. 2 was afforded an opportunity to escape the consequences of defective quality and not confining to tender specifications. This letter also stated that if the change of rates as requested in the earlier letter dated 22-9-1999 and reiterated in this letter were to be accepted, the petitioner's tender would have been the lowest, instead of that of the respondent No. 2 and the respondent No. 1 would be getting a profit of Rs. 1,06,89,180/- and that in view of an opportunity having been provided to the respondent No. 2 for escaping the consequences of supplying defective material as per their initial tender, by the process of permitting the 2nd tender, a similar opportunity should be accorded to the petitioner to rectify the error and permit change if the rates of items 5 and 7. In conclusion this letter also requested that in view of the general terms and conditions of the tender document the respondent No. 1 retains an option and right to divide the work and in that view of the matter the petitioner by also be given an opportunity may dividing the work between the petitioner and the respondent No. 2.

6. Sri V. Venkataramana, learned Counsel for the petitioner urged that respondent No. 1 being a State is obligated by Constitutional and public law injunctions to act rationally, fairly and with a view to achieve the best possible bargain for itself even in areas where it enters into contractual relationship with the individuals. In this view of the legal position and in view of the factual circumstances of the issue encapsulated above the respondent No. 1 ought in fairness to permit rectification of the error in the bid submitted by the petitioner in respect of items 5 and 7 and consider the petitioner's bit which would have, in that event and on application of the discount offered, been the lowest bid and would have permitted the respondent No. 1 to profit Rs. 1,06,89,180/-. It has further been urged that in view of the second process having been limited to the 8 tenderers short listed pursuant to the initial tendering process, this later process, in principle and substance, falls to be characterised as negotiations and in that view of the matter permitting the rectification requested by the petitioner ought to have been considered and non-consideration of the same, considering the respondent No. 2's bid as the lowest and awarding the work to the said respondent on that basis constitutes an arbitrary, irrational and extraneous exercise of power warranting interdiction by this Court under Article 226 of the Constitution of India, more so when the result of the said conduct of the respondent No. 1 has occasioned a loss to the public authority in a quantum exceeding One Crore rupees. It has also been urged that the second process which is in the nature of negotiations ought to have been proceeded with to result in a maximum advantage to the BHEL which is a public authority [a submission which is reiteration of the submission earlier set out, though in a conceptual form]. In support of the submissions the petitioner relied on Food Corporation Of India v. M/S Kamdhenu Cattle Feed Industries., (1993) 1 SCC 71 : AIR 1993 SC 1601, Raunaq International Limited v. I.V.R Constructions Limited, (1999) 1 SCC 492, and Punjab Communications Limited v. Union of India,, (1999) 4 SCC 727.

7. Sri E. Manohar, learned senior Counsel appearing on behalf of the respondent No. 1 BHEL, urged as under:

(a) that the relief as claimed is unsustainable as it is pursuant to the 2nd process of tendering that both the petitioner and the respondent No. 2 also submitted their tenders and in that context the action of the respondent No. 1 in permitting respondent No. 2 to submit a revised tender cannot be said to be illegal as equal opportunity was provided to all the 8 tenderers including the respondent No. 2 and the petitioner. The other relief to direct respondent No. 1 to award the contract to the petitioner is also unsustainable as the contract was awarded to the respondent No. 2 who was the lowest on 5-10-1999 itself while this writ petition was filed on 11-10-1999.

(b) that during the initial process of short listing itself respondent No. 1 has by a Fax message dated 24/28-12-1998 requested all tenderers to confirm that they meet the specific requirements as per the tender and intimate details of the vendors from whom they secure the materials to be used in the work and that in response thereto the tenderers furnished information about the agencies supplying these materials. That while the evaluating rates quoted by the shortlisted tenderers the respondent No. 2 was found to have offered to supply indigenously manufactured material identical to the tender specifications but in view of the vast difference in the rates quoted by the tenders in respect of the two components viz., Geotextile and HDPE Film, the respondent No. 1 requested respondent No. 2 to supply samples for the purpose of testing to ensure that indigenously manufactured material would meet the technical requirements of BHEL/NTPC. Consequent thereupon the samples were tested at IIT, Chennai and the test report indicated that the samples do not meet the technical requirements. In this view of the matter and in view of the vast variance in the rates quoted by the 8 short listed tenders, the respondent No. 1 came to the conclusion that there was an inadequate understanding by the tenders about the two components. The respondent No. 1 therefore, decided to identify the supply agencies for these components in consultation with the NTPC and such identified suppliers/products were initimated to all the 8 tenderers including the petitioner and the 2nd respondent and all were requested to send revised bids vide respondent No. 1's letter dated 7-9-1999. In the annexure thereto the specifications of the product, names and addresses of the manufactures and the Indian agencies of the product were intimated;

(c) that consequently revised bids having been received were opened on 21-9-1999 in the presence of the tenderers and/their representatives. On the opening of the bids the tender submitted by the respondent No. 2 for Rs. 36,98,99,190/- was found to be the lowest as against the petitioner's bid for Rs. 41,18,83,992/-, which latter was with conditional offer of discount of 9.9% on the tender amount if the work order was given to it within two weeks;

(d) that the allegation of the petitioner as contained in his letters dated 22-9-1999 and 5-10-1999, that there has been a mistake in the quotation of bids between items 5 and 7 is an allegation that is misconceived and made with an ulterior motive. Even in the initial bid the petitioner has quoted Rs. 126/- as against item-5 and Rs. 180/- as against item-7 and even after the offer of 29.79% discount on the petitioner's rates as against items 5 and 7, the rates for these items would have come to Rs. 100.80 and Rs. 144 respectively, the petitioner made representations having come to know that his bid was higher than that of respondent No. 2 as is evident from the fact that the 1st representation dated 22-9-1999 was made on the day after the opening of the second set of bids on 21-9-1999. No such representation was made to rectify the so called error either after opening of the 1st bid on 5-5-1999 or on the date of the opening of the 2nd bid on 21-9-1999. In any view of the matter such a representation cannot be entertained. Any consideration of the plea of the petitioner in this regard would be inconsistent with the policy underlying sealed tenders. The entire effort of the petitioner is to subvert the policy underlying awarding of contracts by a sealed tender system and to gain undue advantage based on the knowledge acquired after the bids were opened when the petitioner found himself not being the lowest tenderer;

(e) that there is neither any error, irrationality, arbitrariness nor any other extraneous consideration underlying the action of the respondent No. 1 in awarding the contract to the 2nd respondent who happened to be the lowest tenderer; and

(f) that there is nothing in any of the facts and circumstances pleaded or urged by and on behalf of the petitioner warranting interference by this Court.

8. Sri M.P Chandramouli, learned Counsel for the respondent No. 2 has reiterated the aspects urged on behalf of the respondent No. 1.

9. The contours of judicial review into the State action in the matter of entering contracts with individuals are too well recognised to necessitate an exhaustive analysis. In the limited context of the issues arising in this case, the principle applicable is that though the lowest tenderer can claim no right to the acceptance of his tender, and there in heres a power while inviting tenders to reject all the tenders, yet such power ought not to be exercised irrationally or arbitrarily and must depend for its validity on the existence of rational reasons. The object of inviting tenders for execution of a work is to provide an equal opportunity to all interesting bidders to compete, to obtain the most advantageous rate for execution of the work together with the requisite expedition in execution and quality, warranted. Thus, the fundamental principle governing the State action in the matter of awarding contracts for its works is equal opportunity, ensuring competitiveness and advantageous rate to the public authority duly ensuring requisite quality. There is yet another aspect of the matter. Infinite deliberations and dilemma leading to endless negotiations may secure a more advantageous price but at the cost of expedient execution of the work which is an equally fundamental norm. Good governance cannot be founded on mere endless deliberations and negotiations. A time comes in every decision making where negotiations and deliberations must end and decision made on available facts and circumstances and the best bargain evaluated on such circumstances. In the case on hand the initial bids were opened on 5-5-1999 and tenders were again called for from the eight short listed tenderers and these later bids were opened on 21-9-1999. The respondent No. 1 acting upon these bids had identified respondent No. 2 as being the lowest tenderer and has awarded the work to it on 5-10-1999. The fact that the petitioner has become conscious of the alleged error in his quotation in respect of items 5 and 7 on the day after the bids were opened on the second occasion coupled with the request contained in its representation dated 5-10-1999 for splitting up of the work and award of half of it to the petitioner also, is clearly indicative of the fact that the petitioner wants to avail the advantage of the knowledge obtained on the opening of the bids. The refusal of the respondent No. 1 to keep the process of deliberations open endlessly and in refusing to negotiate further with the petitioner or the refusal in aceding to the petitioner's request for rectification of the so called error in its prices quoted, cannot be characterised by any standards as an arbitrary, irrational or extraneous conduct. The contract is for the execution of a work, which is a component of a Thermal Power Project. If the respondent No. 1 has in the totality of circumstances considered time to be the essence, then such consideration cannot be faulted. Respondent No. 1 is the best judge for balancing competing public interests as between a more advantageous price obtainable by endless and prolonged deliberations and negotiations on the one hand and a time frame within which such deliberations must end and the work begin, on the other. The petitioner's endeavour to secure a contract for itself despite not being the lowest tenderer is sought to be canvassed under the rubric of subversion of public interest. Such an endeavour ought not to have the benediction of this Court.

10. In the facts and circumstances set out above and on the analysis of the applicable law this Court is unable to discern any principle warranting interference by this Court.

11. The writ petition is accordingly dismissed. No costs.