B. Sambasiva Reddy v. K. Kondanna .

Andhra Pradesh High Court
Aug 8, 1996
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The plaintiff filed Suit O.S. No. 364/83 seeking specific performance of an agreement of sale. The suit was decreed on 31-3-1986, directing the defendant to execute a sale deed in favor of the plaintiff within one month, with the plaintiff ordered to pay the balance sale consideration. The defendant failed to execute the sale deed, prompting the plaintiff to file an Execution Petition and deposit the balance consideration. The Court executed the sale deed on 29-7-1987 and gave notice to the defendant. The Execution Petition was closed on 31-7-1987.

Subsequently, the defendant filed Suit O.S. No. 31/89 seeking to declare the Court-executed sale deed unenforceable, which was dismissed on 15-2-1993. The defendant appealed by filing A.S. No. 74/93, which remains pending. Meanwhile, the defendant filed I.A. No. 1227/93 under Section 28 of the Specific Relief Act seeking to declare rescission of the contract based on the plaintiff's alleged failure to act according to the mandatory direction, despite the registered sale deed executed by the Court and delivery of possession. The lower Court allowed this petition in 1993. The present Revision challenges that order.

Legal Issues Presented

  1. Whether an application under Section 28 of the Specific Relief Act for rescission of contract can be filed after the decree for specific performance has been executed and the Execution Petition closed.
  2. Whether the defendant's Interlocutory Application filed about six years after execution of the sale deed is barred by limitation.
  3. Whether the Court becomes functus officio after passing a decree for specific performance, thereby precluding further applications under Section 28 in the same suit.

Arguments of the Parties

Revision Petitioner’s Arguments

  • The sale deed was executed on 29-7-1987 and the Execution Petition was closed on 31-7-1987, which has become final.
  • The defendant had notice of and contested the Execution Petition and also filed O.S. No. 31/89, which was dismissed.
  • The defendant’s Interlocutory Application filed in 1993, about six years later, is time barred and not maintainable.
  • After the decree is passed, the Court becomes functus officio and cannot entertain an application under Section 28 of the Specific Relief Act.
  • Relied on precedent that an application for rescission must be filed within three years from the date the right to apply accrues.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kantamaneni Venkateswara Rao and Anr. v. Meka Venkateswara Rao and Anr. An application for rescission of contract must be filed within three years from when the right to apply accrues. The Court applied this principle to hold that the defendant’s application filed about six years later was time barred and not maintainable.
Kerala State Electricity Board, Trivandrum v. T.P. Kunhaliumma Supports the limitation principle for rescission applications under Section 28 of the Specific Relief Act. The Court relied on this Supreme Court judgment to reinforce the limitation period for filing rescission applications.

Court's Reasoning and Analysis

The Court noted that the sale deed was duly executed by the Court on 29-7-1987, and the Execution Petition was closed shortly thereafter with notice and opportunity to the defendant to contest. The defendant was aware of the sale deed execution and contested the Execution Petition as well as filed a separate suit, which was dismissed. The defendant’s interlocutory application under Section 28 of the Specific Relief Act was filed after approximately six years, well beyond the three-year limitation period established by precedent. The Court reasoned that since the suit was already decreed and the Execution Petition closed, the Court had become functus officio and could not entertain the application. Therefore, the impugned order allowing the application was erroneous and was set aside.

Holding and Implications

The Revision is allowed and the impugned order is set aside.

The direct effect of this decision is to dismiss the defendant’s application for rescission as barred by limitation and to uphold the finality of the execution of the sale deed. No new precedent was established; the Court reaffirmed existing principles concerning limitation periods for rescission under Section 28 and the finality of decrees once executed and closed.

Show all summary ...

1. This Revision is directed against the order passed in I.A. No. 1227 of 1993 in O.S. No. 364/83 on the file of Principal District Munsif, Anantapur.

2. The plaintiff filed the suit O.S. No. 364/83 for specific performance of the agreement of sale. The suit was decreed on 31-3-1986 directing the defendant to execute a sale deed in favour of the plaintiff within one month and the plaintiff was directed to pay the balance of sale consideration to the defendant. However, the defendant failed to execute the sale deed. Thereupon, the plaintiff was constrained to file Execution Petition. He also deposited the balance sale consideration. The Court executed the sale deed in favour of the plaintiff on 29-7-1987 and there was a notice to the defendant in the Execution Petition. The Execution Petition was closed on 31-7-1987; Subsequently the defendant filed OS. No. 31/89 to declare the sale deed executed by the Court on 29-7-1987 as not enforceable etc. That suit was dismissed on 15-2-1993. Against that the defendant preferred A.S. No. 74/93 and it is pending. Now, the defendant filed I. A. No. 1227/93 Under Section 28 of the Specific Relief Act to declare that there is recission of contract in view of the failure on the part of the respondent to act upto the mandatory direction resulting in coming into existence of a registered sale deed executed by the Court followed by delivery of possession and for restoration of possession etc. This petition which was filed in 1993 was allowed, by the lower Court.

3. Aggrieved by the said order the present Revision is filed.

4. Sri T. Bali Reddy, senior counsel appearing on behalf of the Revision petitioner submitted that the sale deed was executed on 29-7-1987. The Execution Petition was closed on 31-7-1987. That has become final. In the Execution Petition there was a notice to the defendant and he contested the petition. Not only that, he also filed O.S. No. 31/89 which ended in dismissal. Now, in the year 1993, i.e., after about 6 years, the defendant cannot file an Interlocutory Application in the suit which was already decreed. Therefore, the Application itself is time barred. He also submitted that when the suit is decreed the Court passing the decree becomes functus-officio and the application cannot be filed Under Section 28 of Specific Relief Act.

5. In support of his contention he relied upon the judgment of this Court in Kantamaneni Venkateswara Rao and Anr. v. Meka Venkateswara Rao and Anr., . In the said case, the Court, in similar circumstances, held that an application for recission of contract has to be filed within three years from the date when the right to apply for recission accrues. The learned Judge also relied upon the judgment of the Supreme Court in Kerala State Electricity Board, Trivandrum v. T.P. Kunhaliumma, .

6. The ratio of that judgment, in all force, applies to the facts of this case. It is not the case of the defendant that he does not know the execution of the registered sale deed in favour of the plaintiff. He also contested the Execution Petition. Therefore, the Interlocutory Application is certainly filed beyond the period of limitation and it is not maintainable. Further, the suit was already decreed. There is no appeal against the decree passed in O.S. No. 364 /83. In such a case, the Application Under Section 28 of the Specific Relief Act cannot be filed. The reasons given in the impugned order are not correct.

7. In the result, the impugned order is set-aside and the revision is allowed, without costs.