(c) The department may amend the adopted work program to transfer fixed capital outlay appropriations for projects within the same appropriations category or between appropriations categories, including the following amendments which shall be subject to the procedures in paragraph (d):
1. Any amendment which deletes any project or project phase estimated to cost over $150,000;
2. Any amendment which adds a project estimated to cost over $500,000 in funds appropriated by the Legislature;
3. Any amendment which advances or defers to another fiscal year, a right-of-way phase, a construction phase, or a public transportation project phase estimated to cost over $1.5 million in funds appropriated by the Legislature, except an amendment advancing a phase by 1 year to the current fiscal year or deferring a phase for a period of 90 days or less; or
4. Any amendment which advances or defers to another fiscal year, any preliminary engineering phase or design phase estimated to cost over $500,000 in funds appropriated by the Legislature, except an amendment advancing a phase by 1 year to the current fiscal year or deferring a phase for a period of 90 days or less.
Beginning July 1, 2013, the department shall index the budget amendment threshold amounts established in this paragraph to the Consumer Price Index or similar inflation indicators. Threshold adjustments for inflation under this paragraph may be made no more frequently than once a year. Adjustments for inflation are subject to the notice and review procedures contained in s. 216.177.