Login

Del. Code 25, § 2717 : Property — Mechanics' Liens — Enforcement In Superior Court — Proof of work done or materials furnished as prima facie evidence of extension of credit on structure

Current through 2016 Legislative Session, Act 399

Proof by the claimant that labor or materials, or both, was performed or furnished upon or to any structure, or immediately adjacent thereto, or that construction management services were provided in connection with the performance or furnishing of such labor or materials, shall be prima facie evidence that the same was performed or furnished or provided for and on the credit of such structure.

Del. C. § 2717
16 Del. Laws, c. 145, § 1; Code 1915, § 2843; 29 Del. Laws, c. 225; Code 1935, § 3324; 25 Del. C. 1953, § 2717; 72 Del. Laws, c. 203, § 6.;